Escolar Documentos
Profissional Documentos
Cultura Documentos
• Requirement identification
• WBS
• Network Diagram
• Activity on Arrow or Arrow Diagramming Method
• Activity on Node (AON) or Precedence Diagramming Method
(PDM)
• Dependencies - Types
• Critical Path
• Slack/ Float
• Lead/ Lag
• Program Evaluation Review Technique – PERT
• Fast Tracking/ Crashing
• Critical Chain
• Resource Leveling
• mpp to plan and control schedule, resource
1. For a network using PERT for determining activity durations, one of the activities in the network is having a
standard deviation of 10 minutes. This activity has a pessimistic time duration of 75 minutes. What is the optimistic
time duration of this activity(in minutes)?
a.65
b.85
c.135
d.15
e.none of the above
2. The project manager has just received a change request from the customer that does not affect the project schedule
and is easy to complete. What should the project manager do first?
(a) make the changes happen as soon as possible
(b) contact the project sponsor for permission
(c) go to the change control board
(d) evaluate the impacts on other project constraints & cost of project
(e) none of the above
(f) all of the above
3. Your organization is considering to run a project which will entail an investment of $1,000,000 in the 0 th
year and will earn revenues for next three years only. The product from the project is forecasted to create
revenues of $250,000 in the first year after the end of the project and of $420,000 in each of the two
following years. What is true for the net present value of the project over the three years cycle at a
discount rate of 10%(which gives a factor of 0.91 for year 1, 0.83 for year 2 and 0.75 for year 3)?
(a) The net present value is positive, which makes the project attractive.
(b) The net present value is positive, which makes the project unattractive.
(c) The net present value is negative, which makes the project attractive.
(d) The net present value is negative, which makes the project unattractive.
(e) none of the above
Activity Predecessor Duration (days)
I.Excavation - 20
II.Sanit. Main Excavation 20
III.Footing 1 Excavation 40
IV.Footing 2 Sanit. Main 40
V.Wall 1 Footing 1 30
VI.Wall 2 Wall 1, Footing 2 30