GENARAL REQUIREMENTS
• 1)Take clearance from all concern sections & check cancellation of all related permits of various systems / auxiliar
clearance from all concern sections & check cancellation of all related permits of various systems / auxiliaries
condition.
• 2)All filters & coolers are cleaned & necessary lubrication of equipment is done.All control & power supplies are
available
• 3)Ensure that HT /LT boards are in healthy condition', Ensure that All Fans/pumps /coal mills lub oil system and
cooling systems are in service.
• Ensure that All turbine drains are in open condition
• Ensure all drum vents, super heater vents , start up vents , super heater drains are open.
• Open ring header drains, Economiser drain for filling . Drain to IBD should be closed.
• All oil guns are cleaned. HP-LP bypass valve trials are taken & found OK.
Boiler filling
1 Boiler filling started at ……………….Hrs with Boiler fill pump No : A / B
AC scanner fan is running ( Discharge pressure > 200mm).Ensure DC scanner fan pick up on auto
Compressor started at ………….Hrs ( Two IACS &SAC are in service and Discharge Pr. 6 kg/cm2)
3 Ensure A/H lub oil pump is running & auto selection is made
3) Ensure furnace seal truf & bottom ash hopper are filled up.Ensure that
refractory cooling pump in service
4 ID Fan A ………..FD Fan A ……….. Started at Hrs
ID Fan B ………..FD Fan B ……….. Started at Hrs
ID A VFD CH-I VFD CH-II
Speed (>100rpm) IGV Open %
Amp (@335Amp) ID Fan A Brg Temp DE/NDE deg C
FD A Discharge damper Amp Vane Opening % disc. press mmWC Temp of air deg C
FD B Discharge damper Amp Vane Opening % disc. press mmWC Temp of air deg C
Start EOP & check oil leakage from bearing. If no leakage observed start AOP
& stop EOP, ensure Auto operation of EOP