Escolar Documentos
Profissional Documentos
Cultura Documentos
UNIT 2
POWER POOLING AND TRADING
Power cannot be stored, hence generation = demand
Sample system of UK :
Regional and national grid companies form a pool
The companies compete for wholesale generation
Energy is sold in bulk in wholesale market
Spot price is determined for half-hour basis in national power load curve
period through competitive bidding by individual generators
Pool is a mechanism to allow trading or sharing between power utilities and
generators
Long term contracts in sales and purchase are made between utilites and
generating companies based on set of rules evolved
Spot trading in short term market reflect supply and demand on short term
basis
POWER POOLING AND TRADING
Settlement system in UK :
Price and payments are calculated under pool wheeling arrangements
Grid operator seeks to schedule and despatch generating units subject to
constraints , to meet demand and maintain reserve
It is done on merit order on generators’ offer of price and availability of
units
Before 10am on the day ahead of actual operation, each utility submits to
the grid operator an offer for generating sets :
Generators’ price
Availability
Operating characteristics of the set
POWER POOLING AND TRADING
All offers of the period + demand forecast + planned reserve are fed to
the computer to match the demand and supply at least cost
Physical constraints at this point are ignored
The schedule is generated – pool purchase price (PPP) is decided for half
hour
PPP consists of :
system marginal price :
price derived from offer prices of the marginal generating sets scheduled in the
unconstrained schedule for the relevent period
Capacity element :
calculated according to Loss of Load Probability (LOLP)
PPP-PSP = uplift
India :
Yet to formulate commercial guidelines for wheeling of power
A rational tariff structure to encourage selling and buying of power
Measures are devised to discourage high frequency operation of grid
COGENERATION / CAPTIVE POWER
Potential industries Mandatory industries
Sugar Cement
Textile Aluminium
Alcohol Fertilizers
Paper Chemical plants
Petrochemicals Heavy industries
Metallurgical Induction / arc furnace
The above plants (above 5 MW) must install cogeneration plants for
economical power generation
COGENERATION / CAPTIVE POWER
A cogeneration facility produces useful thermal energy through various means
for product development which is inefficiently utilised
This waste steam is recaptured and used for power generation
Cogeneration is a conventional technology, modern technology is more
efficient
With advanced packed cogeneration units, hospitals, complexes have involved
in cogeneration
To determine the feasibility of cogeneration :
Economic and energy factors must be considered
Rates of purchase and sale of electrical energy are important
Cost of equipments v/s energy saving cost is a major economic factor
Other factors : Degree of waste recovery, duty cycle, capital cost,
fuel and electricity prices, taxes , reliability and size
COGENERATION / CAPTIVE POWER
Process , which cogeneration facility can utilize :
Topping cycle :
Electricity is produced first and waster energy is recovered in the form of thermal energy
Common configurations used :
boiler produces steam which is used to power a steam turbine generator
Steam required is obtained from the exhaust of the turbine
Avoided cost
= rate at which utilities are obligated to purchase cogeneration power
= cost that the utilities will incur if it were to make arrangements to supply an equivalent amount of
power
Efficiency standard :
Applicable only if oil or natural gas is used
Annual electric power + half of useful thermal energy = 42.5 % of total natural gas and oil
energy input
If thermal energy output < 15 % of total energy output, then 45 %
For bottoming cycle facilities, annual useful power output must be atleast 45 % of energy
input of oil and gas used for preheating the water / steam
COGENERATION / CAPTIVE POWER
Operating standard :
New topping cycle facility must produce at least 5 % of the total energy output as useful
thermal energy
Ownership :
Utility may not own more than 50 % of the cogeneration facility
For selling power to the utility, useful thermal output and PURPA efficiency standards must
be satisfied
COGENERATION / CAPTIVE POWER
DECIDING PURCHASE PRICE FOR COGENERATION
Typical correlation :
COGENERATION / CAPTIVE POWER
DECIDING PURCHASE PRICE FOR COGENERATION
Unit cost of generation form conventional alternative in case of short supply
Consists of three major components:
Fuel and lubricating oil charges
Capital charges
O & M charges
Typical correlation :
COGENERATION / CAPTIVE POWER
DECIDING PURCHASE PRICE FOR COGENERATION
Unit cost of generation from biomass based power generation system
Typical correlation :
TRANSMISSION AND DISTRIBUTION
PLANNING
Transmission
system:
Transfers bulk power
from the generating
system to
distribution system
Sub transmission
system:
segregates power into
dist. systems
Distribution
system:
Between transmission
and consumers
VOLTAGE LEVELS
Generation :
11 KV
Primary transmission :
220 KV
Secondary transmission :
33 KV
Primary distribution :
6.6 KV
Secondary distribution :
415 V
Consumers :
415 / 230 V
TRANSMISSION NETWORK
Interconnection permits power exchange
PRIMARY LOOP
Provides power from 2 feeders
Supply depends on switch status of sectionalizes and reclosers
Loop is normally operated with tie sectionalize switch open
Outage time due to fault is reduced
Additional line increases frequency of faults
TYPE OF DISTRIBUTION NETWORK
PRIMARY SELECTIVE
Each transformer gets supplied from two
sources (feeders)
Transfer of feeder in event of fault is
automatic , therefore fault duration is
minimised
System reliability is high
Used for large essential or continous
process industrial consumers
TYPE OF DISTRIBUTION NETWORK
SECONDARY SELECTIVE
A primary feeder has its own transformer, feeding a
load each
Tie Switch is normally open and interlocked between
secondary feeder switches
Used for industrial plants and large institutions like
hospitals
Primary operational switching is eliminated
Duplicate transformers eliminate interupption time
Each feeder + transformer system must have capacity
to supply entire load
Transfer is automatic upon loss of voltage on either
feeder with static switching equipment
TYPE OF DISTRIBUTION NETWORK
SPOT NETWORK
Has maximum service reliability
Transformers are operated in parallel
The LV bus is continuously energized by all D.Ts
operating in parallel
Automatic disconnection is obtained by reverse
power relays
Feeder fault is eliminated by isolating the feeder,
while supply is continued through remaining lines
Used in high load density , metropolitan areas, for
essential services
Long duration outages don’t exist in this system
TYPE OF DISTRIBUTION NETWORK
GRID NETWORK
Has maximum service reliability
and operational flexibility
Most economical and effective
method
For high density loads in
metropolitan cities
Grid is supplied from multiple
feeders
No outage even during feeder maintenance
Improved voltage regulation due to parallel operation of transformers
Grid can handle abrupt load changes and disturbances
Voltage fluctuation due to fault is very localized
HV TRANSMISSION (HVAC / HVDC)
HV preferred due to :
increasing requirement of bulk power transfer over long distances
Feasibility i.e. economical and ecological advantages of generating power
near the fuel source instead of load centres
Observation :
The capital cost per MW-km decreases with Higher Voltage
P(1*800 KV line) = P(4*400 KV lines) for same distance
For PL(800KV) = 1/10th of PL(400 KV)
HVDC LINKS
Asynchronous HVDC links is used where
Connecting system widely differs
AC mode of connecting systems is impossible
MV network planning :
Half the review period goes in planning general load growth
New additions will have to be incorporated in middle of planning period
SUBSTATION DEVELOPMENT
Technical and economical considerations for planning the density and size of substations :
Load density
Load growth
Utilization of transformer capacity
Maximum fault levels
Flexibility
Siting