Escolar Documentos
Profissional Documentos
Cultura Documentos
Biopharmaceutical
Facility Design
INTAS BIOPHARMACEUTICALS LIMITED
1 of 20
Program
Introduction
Key Design Parameters
Emerging Trends
Design Process
2 of 20
12-Feb-09
Introduction
Traditional: Single
product facilities
1990’s: Multi-
product facilities
introduced
GMP evolves to
permit multi-
product operations
with shared
equipment
3 of 20
12-Feb-09
Key Design Parameters
Process Flows / Unit Operations
Process Volumes
Biosafety
Viral Segregation
Multi-product V/s Single Product
Regulatory Requirements
4 of 20
12-Feb-09
Process Flows
“Biopharma facilities are built around the process”
5 of 20
12-Feb-09
Process Flows
Segregation
Inoculum prep
Centrifugation: noisy, aerosol generating, difficult to
clean
Pre viral & post viral steps in DSP
Column packing areas: open, manual operations
Solvent use areas: flame-proof zone
Product changeovers: Segregation in overlapping
batches
6 of 20
12-Feb-09
Process Volumes
Large (~ >1500L) Small
Stationary systems
Mix of stationary, mobile
CIP hardpiping preferred
Hard piped COP/SOP possible
CIP/SIP Multiple CIP units
Centralized CIP Large MALs, corridors
Long pipe runs Space for clean staging
Multistoried units
12-Feb-09
Biosafety
BL1 preferred.
Exponential rise in capital cost with higher Biosafety
levels
8 of 20
12-Feb-09
Viral Segregation
Detection of potentially harmful viruses in DS (Porcine
parvovirus in Factor VIII)
Principle concern: “Segregation of post-viral material from
pre-viral”.
Extended to segregation in area, airlocks, washing.
Separate AHUs and washing areas
9 of 20
12-Feb-09
Multi Product /Single
product
Multi Product Facility Single Product Facility
Need flexibility for One/two batch sizes,
accommodating processes defined process
Equipment more flexible in Sizing, flows
operating ranges straightforward
Utilities oversized Utilities sized to batch
Pre-determined, multi- volumes & process
directional transfer paths schedules
Larger quantum of extra Defined operating range
space provision Fixed equipment preferred
More disposables used over disposables
No additional space
provisions required.
10 of 20
12-Feb-09
Regulatory requirements
Which regulator will approve the facility? What do they
require?
Are there any key flags to look for?
Talk to the regulators & get a feel of their opinion prior to
basic/detail design.
12-Feb-09
Emerging Trends in Facility
Design
Disposable/ Single use systems
12-Feb-09
Single Use Products: Influence
on Facility Design
Reducing requirement of
cleaning spaces –
SIP/CIP/SOP/COP, Staging,
tank movement …
Reduced Size of Utilities and
Piping – both Central Utilities
and within a process room
Easily validatable closed
systems allow use of lower air
classification
Rapid deployment – less
planning due to low cost of
capital
13 of 20
12-Feb-09
Use of CNC Areas
14 of 20
12-Feb-09
Multi-product facilities with
parallel operations
Historically:
Multiproduct Operation = Campaign mode
Newer technologies for closed operations and risk
based approach
Manufacturers pushing for simultaneous multi-product
operations
Regulators more open to concept – Ok if segregation
and cross contamination issues are addressed
15 of 20
12-Feb-09
Modular Plants and
Superskids
Superskids: Reduce sitework, shrink
timelines, offsite Qualification
Modular plants: Designed, constructed,
integrated offsite
Reduce sitework
Condense Construction Timelines
Pre-tested & integrated- no last minute
surprises
Higher Cost, Suited for midsized plants,
infrastructural constraints
16 of 20
12-Feb-09
Workplaces not Factories
To provide better working environment
Moving away from windowsless artificially lighted rooms
Contract manufacturers- key drivers: To attract potential
customers
Influence Design – room placements, adjacencies
17 of 20
12-Feb-09
Designing a Facility
Start with defining the process, lay down operational
requirements
12-Feb-09
The Facility Design Process
Facility URS
Conceptual Design (3-4 months) Basic layouts, site plan, building
sizing, utilities-basic plan and sizing, line diagrams, equipment
lists, overall philosophies & budget cost (+ 25%)
Basic Design (3-4 months)- Room sizing, utility sizing, detailed
layout, equipment URSs, P & IDs and cost (+ 10%)
Detailed Design (8-12 months): Full/detailed designing of all
elements. 1000s of drawings, 2D and 3 D designing
19 of 20
12-Feb-09
If you are lucky….
12-Feb-09