Escolar Documentos
Profissional Documentos
Cultura Documentos
Alberto Gomez
MBA, Key Expert EU 2007 PHARE Project Romania
Project Cycle Management (PCM), that includes the Logical Framework Matrix (LFM), is the Methodology used by the European Commission (EC) to design , execute and evaluate economic , social and regional Programmes and Projects . It is similar to the one used by all major Multilateral Institutions (UN, WB, IDB, etc.)
Evaluation
Identification
Progress & Monitoring Report Decision whether to continue as planned or reorient the project
Implementation
Formulation
Decision on funding
Decisions to take
Documents to produce
Problem Analysis
STEP 1: brainstorm on problems considered to be a priority by the stakeholders STEP 2: select individual starter problem STEP 3: identify related problems to the starter problem STEP 4: begin to establish a cause-effect relationship STEP 5: all other problems are sorted in the same way (cause-effect) STEP 6: problems are connected with cause-effect arrows showing the links STEP 7: revise the diagram to find out if some problems have not been identified STEP 8: the diagram is revised accordingly and distributed
A different, yet similar, method for Problem analysis is the Fishbone diagramme, or Ishikawa Root-cause analysis
Analysis of objectives
SMEs are able to better access int. markets
Analysis of strategies/options
1. if all the problems have to be faced or only a selection of them; 2. positive opportunities on which we can build on (from SWOT); 3. combination of interventions which is likely to better achieve the results and ensure sustainability; 4. which option is best promoting local ownership; 5. which is the most cost effective option; 6. which option best impact on the needs of the poor/most vulnerable groups
Indicators
How the Overall Objective has to be measured including Quantity, Quality, and Time? How the Purpose has to be measured including Quantity, Quality, and Time?
Sources of verification
How will the information be collected, when and by whom?
Assumptions
Purpose (often called specific objectives) direct benefits to the target groups
Same as above
If the purpose is achieved, what assumptions must hold true to achieve the Overall Objective? If results are achieved, what assumptions must hold true to achieve the Purpose?
Results (often called outputs) tangible products or services delivered by the project
How the Results have to be measured including Quantity, Quality, and Time?
Same as above
Activities (sometimes referred to Inputs) which have to be undertaken to deliver the desired results
If activities are completed, what assumptions must hold true to deliver the Results?
Activity Schedule
ID N o m e a tt iv it 22 C2 . I n s t i t u t i o n B u i l d i n g f o r R D P
E s ta b lis h a S tr a te g y C o m m itt e e in e a c h r e g io n Id e n t i f y a n d m e e t w it h m e m b e r s o f t h e S C D e v e lo p m o d a l it i e s & m e c h a n is m f o r t h e o p e r a t i o n o f t h e S C S u b m i t S C m e m b e r s h i p t o E C D e le g a t io n a n d P r o j e c t P a r t n e r s E s ta b lis h W o r k in g G r o u p s in e a c h r e g io n D e f i n e t h e m a t ic W o r k in g G r o u p s Id e n t i f y m e m b e r s o f t h e W o r k i n g G r o u p s D e v e lo p m e c h a n i s m a n d m o d a l i t i e s f o r t h e o p e r a t io n o f t h e W G s S u b m i t W G m e m b e r s h i p t o E C D e l e g a t i o n a n d P r o je c t B e n22 22i e s e /f ic ia r T r a in in g o n R D P fo r b o th S C a n d W G m e m b e r s D e s ig n a n d a g r e e t r a in i n g p r o g r a m m e o n R D P S e le c t p a r t i c i p a n t s O r g a n is e & d e li v e r t r a in in g w o r k s h o p s in R D P E v a lu a t e t h e p e r fo r m a n c e & s u p p l e m e n t a r y t r a i n in g s a s n e e d e d A s s i s t r e g i o n a l o f f i c i a l s w i t h d r a f t i n g R D s t r a t e g i e sR
2222 2222 2222 2222 2222 2222 2222 MG L A S ONDG F MA MG L A S ONDGF MA MG L A SONDGF MA MG L A S OND GF MA MG L A S ONDGF MA MG L A SOND GF MA MG L A S O RDA
RDA
RDA
22 22 22 22 22 22 22
DA
A s s i s t t o c a r r y o u t R e g io n a l S o c i o - E c o n o m i c A n a l y s e s A s s i s t t o s e t p r i o r i t ie s & d r a f t R D s t r a t e g i e s A s s i s t t o f o r m u la t e a c t io n p la n s f o r i m p l e m e n t a t i o n o f R D s t r a t e g i e s F a c i li t a t e a c c e p t a n c e o f R D P s b y t h e C e n t r a l G o v e r n e m e n t D e v e lo p & i m p l e m e n t M a r k e t in g S t r a t e g y t o i m p l e m e n t R D P
ACTIVITIES / INPUTS
Unit
Project Total
th 2Q
C22Establish WGs in each region . Equipm ent computers no. fax, modem no. furniture lump Salaries & allow ances office staff mm counterparts mm ETC
2 2 2 2 2
22 22 22 2 22 22 2 2 2 2 22 2 22 2
22 22 22 2 22 22 22 2 22 2
22 22
22 22 22 2 22 22 22 2 22 2 22 2 22 2 22 22 22 22 22 22 22 22
2 2
22 2 22 2
Monitoring
Focus of the analysis Planned vs actual (efficiency) Risk & Assumptions Design (relevance) Project results (effectiveness) Sustainability Impact Questions to answer
Is the project doing what was originally planned?
Information needed
Activity schedule Resource schedule Logframe matrix Project Reports Interviews Risk matrix Logframe matrix Logframe matrix Stakeholders Analysis (etc LFA) Logframe matrix, Project Reports Interviews
Are the assumptions holding true? Are new risks emerging? Was the project design relevant? Is it still relevant? What difference is the project making? Are the project purposes likely to be sustainable? Will the project impact on the overall objective?
Logframe matrix
Evaluation
Focus of the analysis Relevance Questions to answer
Is the project design relevant?
Information needed
Logframe matrix Stakeholders Analysis, Problem Analysis, Analysis of Objectives, Analysis of Strategies (if available) Monitoring Reports Logframe matrix
How well the various activities transformed the available resources into the intended results?
How far the projects results were used Logframe matrix or their potential benefits were realised? To what extent the benefits received by the target beneficiaries have had a wider overall effect? Are the positive outcomes of the project at purpose level likely to continue after the external funding? Logframe matrix Interviews
Sustainability
Interviews
ISO 10,006: 2003- Quality Management in projects, 20 pages of text, is a very general standard, only covers quality area, see www.iso.org .
PMBOK (Project Management Body of Knowledge or PMBOK) of the Project Management Institute (PMI), 425 pages its 3rd - 2004 edition. US-based professional association, 170,000 members worldwide and 100 chapters, see www.pmi.org. Certifies project professionals as PMPs . IPMA , www.ipma.ch , Prince 2 www.prince2.com , Ten Step , www.tenstep.com ,etc
Key documents are the Charter, the Scope (similar to terms of reference) and the Project Plan
Stakeholders analysis in Private PM In private PMI standards there is no specific way to analyze the stakeholders. There is no template or specific technique recommended , although the need to do so is mentioned . Neither ISO 10.006 nor Prince2 specifically mention the stakeholder analysis nor the method to do so.
In the International PM Standards these problems have their definition and scope and strategies in their different sections in the Project cycle of the PMBoK . Scope definition and strategies, and product definition and analysis , are also treated in the ISO, IPMA (ICB Level4) and Prince 2 ones. But a difference exists with the International Standards ,since none establishes a specific tool or methodology to carry out the problem or objectives analysis of the target group, as the PCM does (Logical Framework Approach, LFA)
Ecofin in private PM
Economic and Financial Analysis (Eco-Fin): PMBOK mentions the feasibility study in the chapter : Project phase and Product life cycle, but not the type of analysis to carry out IPMA ICB has the PM Content Element 3 Programme and Project Portfolio, but its neither the economic justification , not its technique are mentioned ISO 10.006 does not deal with the Economic and Financial justification , or economic analysis at all. Prince 2 talks about the Business Case as a prerequisite to approve the project, therefore it is part of the process SU 4, as for project brief.
Conclusions
The different objectives of Public and Private PM Projects and Programmes , determine the emphasis in the Methodology. While in International PM ,there are some tools that are obligatory ,in PM Private Methodologies the standards are more varied and flexible. But certainly they are complementary and useful.
Some of the tools and templates used in Private PM methodologies, are very useful and to a certain extent more detailed than the tools necessary to manage a Public Project. And that is positive ,since the a Manager has to use those tools that in her/his mind are more appropriate to achieve the Project deliverables.
Conclusions
There some areas that in the PCM are not covered in depth: it is the human resources, quality ,or risk and alternative strategies during the actual problem. PCM does not go very deep in time management , or critical path, network diagram , or project management office ,PMO . Which is necessary in large and complex projects. A important aspect of PCM is the fact managers do not deal just with the quantitative issues , but with people perceptions of varied stakeholders with sometimes, different interests and agendas.
Conclusions
A Methodological comparison shows that PCM manages the
Project Cycle (design ,plan .execution , monitoring, evaluation, budgeting and indicators) very well, compared with other Private methods such as PMBOK, or IPMA-ICB, ISO 10,006,or Prince2 . The stakeholders, Contracting institutions, implementing institutions and beneficiaries issue ,which is more complex in International PM is also a key difference. Experience in International PM and people management, is a good help for that. The Private PM methodologies deal with some other areas ,such as human resources, team management, quality and risk , and complex and long calendars in more detail. And they have a technical focus principally.
1. 2. 3. 4. 5.
The right people The right skills The right motivation/incentives The right business environment The right leadership