Escolar Documentos
Profissional Documentos
Cultura Documentos
OBJECTIVE
Project Management Overview MS Projects
PROJECT MANAGEMENT : Project management is the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
PROJECT MANAGEMENT
Project management is accomplished through the appropriate application and integration of the 5 Process Groups & 9 Knowledge Areas.
5 Process Groups are: Initiating Planning Executing Monitoring and Controlling Closing
9 Knowledge Areas: Integration Management Scope Management Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management
MS PROJECT BASICS
MS PROJECT TOPICS
CREATING A PROJECT PLAN
1. Getting Started
2. Calendars 3. Task Types 4. Project Information 5. WBS 6. Activity definition 7. Activity sequencing 8. Activity duration estimation 9. Project Baseline 10. Critical Path 11. Constraints
1. Planned % Complete
2. Project Plan Updation
GETTING STARTED
Before making the Project Plans the following need to be taken care of:
1. Project Scope - What has to be included in the Project Plan 2. Project Deliverable or WBS How the scope can be broken down into more manageable parts 3. Project Calendar Defining the no of working Days and hours
GETTING STARTED
STARTING MS PROJECTS
PROJECT INFORMATION
ACTIVITY DEFINITION
ACTIVITY SEQUENCING
FINISH TO START Relationship between activities in which start of an a successor activity depends on the finish of the predecessor.
START TO START Relationship between activities in which start of an a successor activity depends on the start of the predecessor.
ACTIVITY SEQUENCING
FINISH TO FINISH Relationship between activities in which finish of an a successor activity depends on the finish of the predecessor.
START TO FINISH Relationship between activities in which a successor activity cannot complete until its predecessor starts.
ACTIVITY SEQUENCING
PROJECT BASELINE
PROJECT BASELINE
CRITICAL PATH
Step1: Select Tracking Gantt from the view menu Step 2 : Format the time scale to see the entire tracking Gantt chart
CONSTRAINTS
Constraints are broadly classified as under
Flexible Constraints - They dont tie a task to a specific date - Flexible constraints in MS Projects are i. As soon as possible ii. As late as possible
Semi- Flexible constraints - They have a date associated with them but dont require the task to start or finish on the exact dates. -Semi Flexible constraints in MS Projects are i. Start no earlier than ii. Start no later than iii. Finish no earlier than iv. Finish no later than
CONSTRAINTS
Inflexible constraints -They tie the tasks start and finish date to a specific date - Inflexible constraints in MS Projects are i. Must Start on ii. Must finish on
PLANNED % COMPLETE
The planned % complete is used for the S- Curve Depending upon the frequency of updation the data dates are finalized. The project is then updated on these data dates as shown below. Tools Tracking update Project
PLANNED % COMPLETE
PLANNED % COMPLETE
Planned % complete
120 100
80 60
40 20 0 Planned % complete
Planned % Complete
Data Date
3%
11%
24%
24%
24%
26%
29%
32%
39%
53% 53%
58%
68%
92%
100%
18-Aug 22-Aug 27-Aug 1-Sep 6-Sep 11-Sep 16-Sep 21-Sep 26-Sep 1-Oct 6-Oct 11-Oct 16-Oct 21-Oct 25-Oct
60
Planned % Complete 40 20 0 Actual % Complete
0% 3% 18-Aug
8% 11% 24% 24% 1-Sep 24% 26% 29% 32% 39% 53% 53% 58% 68% 92% 100%
22-Aug 27-Aug
6-Sep 11-Sep 16-Sep 21-Sep 26-Sep 1-Oct 6-Oct 11-Oct 16-Oct 21-Oct 25-Oct
THANK YOU