SURVEYING & DATA COLLECTION OF DISTRIBUTION NETWORK EQUIPMENTS

PROJECT DESCRIPTION

General Overview: Specific Overview: Detailed survey General Survey Project Goals:

General Overview:
The SEC Management has created a project for four regions to create a state of the art asset management system using advance technologies ; keeping pace with the worlds large utility companies.

Specific Overview:
The asset management data collection was designed at two levels i.e.

General Survey:

Detailed Survey:
General Survey:
Scope of work is a set of minimal data to create a geographical base map of the network.

Detailed Survey:
Scope of work is collection of comprehensive data of assets.

Project Goal:
The higher management of SEC very wisely set the goals of the project as follows:. 1. Creation of a geographical database. 2. A complete record of assets and their condition. 3. Preparation of a complete data base for integration of GIS at central level hence enhancing modern day management system.

SEC Project Procedure:

The following page describes how the SEC has set the procedure of the project and management. These procedures are presently followed.

SEC PROCEDURES
Priorities Work order Issued Survey Final Submitted Data Processing Invoice to Local Office Submitted to SEC local office Signed by Technicians Signed by Surveyor Comments by Local Office Incorporated by RGF Signed by Coordinator Signed by Manager

Invoice to SEC Project Manager


Invoice to SEC Accounts

Verified by Local Office

RGF Project : 1. Management 2. Procedures 3. Teams 4. Resources

RGF PROJECT MANAGEMENT


RGF Home Management SEC Higher Management Field Project Manager GIS Manager

SEC Project Manager


Field Supervisor SEC Local office Coordinator 16 Survey teams
GIS /QC
Quality Control

GIS Technicians
Data Processing

PROJECT PROCEDURE
work order Project Manager Final Submitted SEC

Verification Crews

SECChecking

Survey Teams

Punch List

SECRemarks

Invoice to Local Office

Surveying

Data Processing

RGFSupervisor

Signed by technician Signed by Surveyor

Riyadh Office

Quality Control

Supervisor Punch list

Signed by Coordinator
Data Processing

Data Processing

Re-Plotting Quality Control

Signed by Manager

Plotting

SEC-Local

SECAccounts

PROJECT RESOURCE MOBILIZED


Home Office:
Management and data Processing Based in Riyadh headed by GIS Manager with five GIS technicians equipped with computers, software and plotting facilities.

Field Office Data Update Facility A team headed by Project Manager, supervisors, GIS/CAD technicians with Data processing and plotting facilities based at Khamismushayet.

FIELD TEAMS:
Human Resources:
Human resource Supervisors no. Description 4 well experienced and trained in data collection, verification and troubleshooting. 16 well trained and project specific data collection, trained and qualified in use of GPS and data collectors, data downloading. Driving license holders or helping the surveyors for carrying equipment and for safety and security of survey equipment

Surveyors

Drivers/ Helpers

16

Note: In difficult terrain in some cases one more labor is added to few teams specifically for security of the team.

Other Resources:
Resource Vehicles no. 20 Description

Field Data Equipment:


GPS Data Collectors Field Laptops UG cable Locator 17 17 16 4 Subscribed to Omnistar With Arc Pad 8.0 Software

Office Computers:
Riyadh Khamis mushayet 7 3 2 1

Plotters:
Riyadh Khamis mushayet

DATA QUALITY
GPS subscribed to Omnistar for data correction which meets or exceeds the accuracy specifications

SEC QUALITY CHECK TECHNIQUES


Rgf using Trimble proxrt specialized GIS GPS system. RGF is using omnistar data correction as additional for data quality on annual subscription basis to guarantee the data quality. Rgf submitted files in Google earth format for checking Rgf provided training to SEC to convert any data to Google earth format to check its quality before going to field. Rgf has deployed extra verification crews for checking data prior to first submission.

TRAINING FOR SEC


Rgf provided training to 50-100 SEC persons Rgf arranged training for SEC twice since beginning of this project How to build data bases How to make esri drawing from scratch How to update existing drawings How to view and edit drawings How to find required meters transformers from database etc. How to join multiple feeders for analysis How to edit data fields and update databases.

WORK PROGRESS
Asir
Total Work orders Surveyed Work orders Processed Submitted Total Length Approved /number/length Shortest Feeder Length/time Longest Feeder Length/time 22 22 22 22 8860Km

Najran
27 27 27 27 2508Km

Jizan
34 34 34 34 2751Km

Baha
16 16 16 16 3237Km

Total
99 98 98 98 16921Km

9/3927Km
159Km/23days

12/477Km
3Km/20Days

12/470Km
1Km/12Days

6/986Km
7/37Days

39/5860Km

832Km/22days

561Km/16Days

488Km/28Days

464Km/16Days

RGF DIFFICULTIES
There are two types of difficulties. 1. Head Office 2. Local Offices 1. Head Office
I.

I. II. III. IV. V.

Work order Duration is not justified - Feeder Length vs. survey time Area Difficulty vs. survey time Time lost during crew shifting after every feeder. Resource deployment restrictions result time loss. Delays in every new work order 4-5 days. Relocation and adjustment to local area vs work order duration. After all delays from local offices , deduction from final payment.

2. Local Offices
I. II. III.

IV. V.

VI.
VII. VIII. IX.

Very poor response from local offices. Data receiving delays and signing hesitation. Lack of project awareness from local offices like General survey/Detailed Survey. Local office unlimited delays in verification. Local area undue demands like vehicle, surveyors for verification. Local area undue demand for provision of verification resources. Undue delays for signing approved work orders invoices. No dedicated Surveyors assigned from local offices. Local office verification give us just 2-4 hours in a week and often occasionally.

PROJECT HINDRANCES:
1. Lack of understanding of the importance of this project by local offices 2. Lack of local offices awareness of the requirements of this project in a big picture. 3. Lack of ownership of the project by local offices. 4. Failure of local offices to provide adequate human resources. 5. Lack of the local offices trained persons to see the data-base electronically. 6. Disinterest of the local offices in getting their people trained. 7. Lack of understanding of local offices of the bigger goals of the project and not understanding the vision of the top management of SEC.

RGF SUGGESTIONS
1. Project control should be centralized to SEC-abha. 2. SEC has allocated very limited human resources to this project. As this project is the baby of SEC South Central, we suggest that verification Surveyors Should be assigned by center and reporting to the center. 3. Centralized contact point should receive all our data conforming to standardization of scope of work.

4. It is goal of the project that all the assets of SEC south are to be mapped Therefore we suggest that one S/S should be assigned in each area for survey before moving to other area.
5. One person should be appointed at the central abha office to receive the softcopy of the data..

SUGGESTED SEC-ORGANIZATION CHART


SEC Area Manager

SEC-Local Offices

SEC-Coordinator

RGF

SEC-Surveyor-1 SEC-Surveyor-2 SEC GIS Technician

SEC-Surveyor-3
SEC-Surveyor-4

IN A NUT SHELL:
RGF shares with the SEC higher management, the common goals of success of the project. RGF played its part:. Work orders were issued only for six months: Feb.2010---Aug.2010

RGF surveyed 17000Km


SEC took one year to check 6000Km RGF was set to complete the survey of 66000Km in 3 Years.

We believe SEC should shoulder their part of the success of the project.