Escolar Documentos
Profissional Documentos
Cultura Documentos
CPM / PERT
1
Introduction
projects is a combination of various activities. PERT and CPM are two techniques that are widely used in planning and scheduling the large projects. These two technique are used to estimate and evaluate the project completion time and control the resources to see that the project is completed within the stipulated time and at minimum possible cost
2
PERT Meaning-
It is a planning and control technique which uses the a network to complete a predetermine project on schedule
CPM Meaning-
it attempts to complete the given project as quickly as possible with minimum possible cost
Analysis-
Analysis-
Useful-
Useful-
BasisUtility-
BasisUtility-
Its network is EVENT based. It is used where the emphasise is on shortning the projectexecution time without time without much concern for cost of the project.
Its network is ACTIVITY based. It is used where the emphasise is on optimising resource allocation and minimising overall cost for given execution time.
Time Estimates
Time Estimates
In this three time estimates i.e. Optimistic , most likely, and pessimistic, of completion for each activity. Here time estimates are uncertain.
In this one time estimates i.e. most likely time of completion for each activity. Here time estimates are certain.
Introduction
A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling
Completing the project as early as possible by determining the earliest start and finish of each activity. Calculating the likelihood a project will be completed within a certain time period. Finding the minimum cost schedule 5
Introduction
A project is a collection of tasks that must be completed in minimum time or at minimal cost. Investigating the results of possible Objectives of Project Scheduling delays in activitys completion time.
Progress control. Smoothing out resource allocation over the duration of the project.
Task Designate
Tasks are called activities.
Estimated completion time (and sometimes costs) are associated with each activity. Activity completion time is related to the amount of resources committed to it. The degree of activity details depends on the application and the level of specificity of data. 7
Based on this information we can develop managerial tools for project control.
8
KLONE needs to develop a precedence relations chart. The chart gives a concise set of tasks and their immediate predecessors.
10
Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects
Use of nodes and arrows Arrows An arrow leads from tail to head directionally Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. Activity A task or a certain amount of work required in the project Requires time to complete Represented by an arrow Dummy Activity Indicates only precedence relationships Does not require any time of effort
Project Network
11
Project Network
Event Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node) Network Shows the sequential relationships among activities using nodes and arrows
12
Project Network Activity An activity is an element of a project which must be carried out to complete the project. The activity denoted by an arrow. The tail end of an arrow represents
13
Types of Activity
Predecessor Activity Successor Activity Concurrent Activity Dummy Activity
14
completed immediately prior to the start of another activity Successor Activity- the activity cannot be started until one or more activities are completed Concurrent Activity- that activity which can be accomplished simultaneously Dummy Activity- which only determines the dependencyof one activity over the other, but does't consume any time.
15
Event
The beginning and end of activity are called events or nodes. Event is a point of time does't consume any resources. Event are represented by which are called nodes.
16
Types of Events
Merge Event- when one or more activity join an event
17
18
A must finish before B can start both A and C must finish before D can start
19
Concurrent Activities
Lay foundation Lay foundation
3
Dummy 2 1 0
3 2
Order material
20
KLONE COMPUTERS, INC From the activity description chart, we can determine immediate predecessors for each activity.
A
Activity A is an immediate predecessor Bof activity B, because it must be competed just prior to the commencement of B.
21
22
Network
D G
23
A B C D E F G H I J
90 15 5 20 21 25 14 28 30 45
24
PERT/CPM is used for scheduling activities such that the projects completion time is minimized.
25
CPM
27
Evaluate the ES of all the nodes for which EF of all the immediate predecessor has been determined.
ES = Max EF of all its immediate predecessors. EF = ES + Activity duration.
28
0,90 A A 90
90,115 F F 25
29
5,95 A A 90
0,90 0,90
29,119
149,177 115,129 129,149 129,149 129,149 115,129 153,173 166,194 146,166 H D G D H G 20 28 14 129,149 149,194 149,194
194
J 45
31
Slack Times
Activity start time and completion time may be delayed by planned reasons as well as by unforeseen reasons. Some of these delays may affect the overall completion date. To learn about the effects of these delays, we calculate the slack time, and form the critical path.
32
Slack Times
Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project.
Slack Time = LS - ES = LF - EF
33
Activity
A
B C D E F G H I
J
0 5 5 0 24 0 0 17 29 0
Critical activities Critical activities must be rigidly must be rigidly scheduled scheduled
34
J 45
36
38
39
Assumption 2
Assumption 3
Cost Crashing
44
The maximum crashing of activity completion time is TC TN. This can be achieved when spending CN CC. Any percentage of the maximum extra cost (CN CC) spent to crash an activity, yields the same percentage reduction of the maximum time 47
A demonstratio Total Cost = $2600 Time Job time = 18 days n 20 and save on completion time 18 of the and save 16 more on Linearity Add 25% of the ext completion 14 cost... Add Add to to the Assumption more the time
Normal CN = $2000 TN = 20 days
12 normal cost... normal cost... 10 to save 25% of the max. time reduction 8 6 4 2
10
15
20
25
30
35
Cost ($100) 48 40 45