Escolar Documentos
Profissional Documentos
Cultura Documentos
A Global Company
Eastern Europe, Middle East, & Africa
North America
#1
#1
Asia
#2
Latin America
#1
Asia one of the fastest growing markets. Goodyear holds a # 2 position in market
Regional Rank
Goodyear Ballabhgarh
Plant Location : 28 km South of Delhi in Haryana state on National Highway No.2. Escorts, Maruti (Gurgaon), JCB, Yamaha, Honda (Greater Noida) 67 acre with 654,000 sq.ft of floor space Automotive tires started in 1961, presently producing 4100 Tires per day. Farm, Truck, LCV tires.
Area Manufacturing
: :
Products
Banbury - Mixer
Curing
OEM Retail
Tire Building
Natural Rubber
Extrusion
Inspection Dispatch
Plant Layout
Project Approach
Project Definition Data collection Root Cause Analysis Actions suggested based on identified root causes Cost Benefit Analysis Key Learnings
Project Objective
DEFINITION The main objective of doing the project is to reduce the waste from extruder machine which produces tire treads so as to reduce scrap/rework costs and improve the productivity of the plant. SCOPE The scope of the project includes study of extrusion waste that occurs in different processes during tire making. Reduction of waste in other processes(particularly curing) was beyond the scope. The scope is limited till the recommendation phase. The actual implementations of the recommendations are under the purview of the organization.
ASSUMPTION The waste reduction was limited to material waste because the extrusion process bears slack. The bottleneck lies at the curing process so extrusion doesnt work at full capacity. The defect data collected was only limited to 7 days in Shift A. The defects in other shifts are expected to be of same pattern.
Extrusion Process
EXTRUDER
Skiver
Weighin g Convey or
Gravity rollers
Declining Conveyo r
Scrap Marker
Inclined convey or
Cooling Convey or
Cement Station
Defect Data
Types of defects in treads
54, 3% 7.8% 16% 51.3%
HIGH WEIGHT
LOW WEIGHT
Treads produced-12207 Treads rejected-1674
22.5%
LUMPS
TORNEDGE
OTHERS
Pareto Analysis
FINDINGS
More than 50% of the rejections are caused to low weight. High weight and lumps add up to almost 90% of the
MATERIAL
Low Viscosity (M)
Low specific gravity (M) Running weight not properly set
Low weight
Line synchronization not proper Mechanical/Electrical stoppage (M) Waiting for compound Operating skills
MACHINE
METHOD
Low weight
Low viscosity
Compound milled for a long time at B.D. mill. Temperature at extruder head increased
No water circulation at extruder head
Why #2
Electrical stoppage s
Feedbrea k
Why #3
Why #4
Why #5
Operator negligence
Why #6
Root Causes
Nonconformanc e of procedure
High weight
Line synchronization not proper Improper breakdown of compound at B.D. Mill (M) Wrong die tuning
MACHINE
METHOD
Why #2
High viscosity
Compound from Banbury was hard
Why #3
Why #4
Compound urgently needed at feed mill Feed mill running short of compound at extruder. Shortage of material. Planning improper.
Why #5
Why #6
Lumps
Temp/TCU Line stoppage (M) Waiting for compound Operating skills
MACHINE
METHOD
Lumps
Why #2
Lumpy treads mixed at Banbury
Viscosity variation
Lumps formed at Banbury mixer
Line Stoppage
Why #3
Why #4
Compound processed for a long time Orbit conveyor not used in cap side Operator not trained in orbit conveyor usage
Why #5
Why #6
Actions / Opportunities
Ensure Ok compound loaded on B.D. mill free from lumps
Root Cause - Operator negligence
Censor installed at declining conveyor so that operator loads tread to roller on time
Root Cause Less visibility for operator
Automated entry of lumpy treads count by operator at cementing station through push button
Root Cause Lumpy treads not recorded
Actions / Opportunities
Implementation of Orbit conveyor at the cap & the base feed mills and train operator its function and usage.
Root Cause Lumps formed due to overheating as operator is not trained on its usage
Segregate lumps from lumpy treads before sending back to Banbury mixer
Root Cause Improper disposal of lumpy treads
Scheduling of preventive maintenance at conveyor belt, skiver, motor to prevent untimely breakdown during running of batch
Root Cause Non conformance to procedure(maintenance)
Proper scheduling at Banbury to ensure there is enough compound. If not operator should inform supervisor at the starting of batch
Root Cause Shortage of material at B.D. mill
Actions / Opportunities
Censor installed at cap feed mill to indicate accumulation of material at cap feed mill guard
Root Cause Less visibility for mill man
Operator counseling to make them aware and responsible towards the job they are doing & adhere to SOPs/specifications.
Root Cause Standard procedures not followed
Proper distance between the bite rollers should be maintained and its axis straightened so that rollers work properly.
Root Cause Safety and performance audit not conducted by plant
Total cost involved for treating one KG of tread = Cost of Banbury + Cost of extruder = 1.30+0.39=1.69 Rs/kg
Total cost of re-work per month: = 396498.85 * 1.69 = Rs. 670, 083.06
= 321,781.86 Rs/Month.
Key Learnings
Learned in detail about the steps/processes involved in tire manufacturing particularly producing treads in 10*10 extruder machine. Learned about the quality parameters which are responsible for the rejection of tire treads. Learned about the allocation of work, manpower, job scheduling & also learned that how manpower is managed & handled on the shop floor. Undertook step-by-step approach using TQM tools to address the problem. Practically saw the types of manufacturing waste being generated on the shop floor & how it impacts the productivity of the plant. Learned about the interdependencies between various processes for this project & how the impact of one process affects the output of another process.
Thank you