Você está na página 1de 19

OUR EXPERIENCE

Client Location Duration Water depth

: Oil & Natural Gas Corporation (ONGC) / INTEC SEA : Bay of Bengal, East Coast of India : 2003 : 20 Meters

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

OUR EXPERIENCE

Client

: Petronas Carigali Sdn Bhd (PCSB) / Sime Darby Engineering Sdn Bhd / Ramunia Fabricator Sdn Bhd : Sumandak Field located at offshore Sabah, Malaysia : March 2005 October 2007 :
Platform Name SUPG-B SUJT-C Water Depth (M) 43 37

Location Duration Weight & Water Depth

Dry Weight (M)


Topside 8,300 570 Jacket 3,000 800

Scope of work : Pre-Conceptual Study Detailed Design Project Management Procurement Support Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

Client

Petronas Carigali Sdn Bhd (PCSB) / Newfield Peninsula Sdn Bhd / Ramunia Fabricator Sdn Bhd 320km offshore Terengganu in block PM318, Malaysia October 2005 May 2006
Water Depth (M) 61 Dry Weight (MT) Topside 2,200 Jacket 1,200

Location Duration Weight & Water Depth

: : :

Scope of work : Pre-Conceptual Study Detailed Design Project Management Procurement Support Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

Client Location

: Talisman Malaysia Limited (TML) : Southern Part of PM3 Commercial Arrangement Area (CAA), Malaysia / Vietnam Border : March 2005 July 2005 :
Water Depth (M) 57 Dry Weight (MT) Topside 350 Jacket 600

Duration Weight & Water Depth

Scope of work : Detailed Design Pre-Conceptual Study Procurement Project Management Follow on Engineering Conceptual Design Front End Engineering Design

OUR EXPERIENCE

Client Location

: Petronas Carigali Sdn Bhd (PCSB) : Block PM12 within the existing MASA field, offshore Terengganu, Malaysia : February 2006 - June 2006 : 75 Meters

Duration Water Depth

Scope of work : Pre-Conceptual Study Detailed Design Procurement Support Project Management Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

Client Location Duration

: Petronas Carigali Sdn Bhd (PCSB) : Dulang field, offshore Terengganu, Malaysia : July 2006 June 2007
Water Depth 70 Dry Weight Topside 1,034 Jacket N/A

Weight & Water : Depth

Scope of work : Pre-Conceptual Study Detailed Design Project Management Procurement Support Follow on Engineering Conceptual Design Front End Engineering Design

OUR EXPERIENCE

Client Location Duration

: Petronas Carigali Sdn Bhd (PCSB) : 185 km offshore Terengganu, Block PM313, Malaysia : July 2006 October 2010
Platform Name TBCP-A TBDR-A TBFP-A LHDP-A MLDP-A Water Depth (M) 73 73 73 71 77 Dry Weight (MT) Topside 14,000 2,530 450 1,500 1,520 Jacket 8,760 5,140 542 3,410 3,650

Weight & Water : Depth

Scope of work

: Detailed Design Pre-Conceptual Study Procurement Support Project Management Follow on Engineering Conceptual Design Front End Engineering Design

OUR EXPERIENCE

Client Location

: Petronas Carigali Vietnam Limited (PCVL) : 155km offshore Vung Tau, in Blocks 01 & 02 S.R. of Vietnam : February 2007 May 2007 :
Water Depth (M) 50 Dry Weight (MT) Topside 1,280 Jacket N/A

Duration Weight & Water Depth

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

OUR EXPERIENCE

9 14

JK-A

MD-A

Location Duration Client Client Weight & Location Water Depth Duration Weight & Water Depth

: 268km East of Songkhla, Thailand : July 2007 March 2008 : Carigali-PTTEPI Operating Company (CPOC) : Carigali-PTTEPI Operating Company (CPOC) Water Dry Weight (MT) : Platform Depth : 268km East of Songkhla, Thailand Name : July 2007 March 2009
MD-A (M) Topside 760 Jacket

Platform MD-B Name MD-C MD-A JK-A MD-B MDD MD-C JK-A

60 Water 60 Depth (M) 60 60 60 60 60 60 60

540 Dry Weight (MT) 620 530 Topside Jacket 610 510 760 870 620 726 610 870 540 980 530 510 510 980

Scope of work :

Pre-Conceptual Study Detailed Design MDD 60 726 510 Project Management Procurement Support Conceptual Follow on Engineering Scope of work : Design Front End Engineering Design Pre-Conceptual Study Detailed Design Project Management Procurement Support Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

10

Client Location

: Petronas Carigali Sdn Bhd (PCSB) : 55 Km West North of Labuan Offshore, Sabah, Malaysia : July 2007 Present
Platform Name KNPG-B KNJT-C Water Depth (M) 60 55 Dry Weight (MT) Topside 14,782 1,319 Jacket 11,487 2,135

Duration

Weight & Water : Depth

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

OUR EXPERIENCE

11

Client Location Duration

: Mearsk Oil Qatar As (MOQ) / Sime Darby Engineering Sdn Bhd : Al Shaheen facilities, Qatar : August 2006 May 2008
Platform Name BE BG Water Depth (M) 61 60 Dry Weight (MT) Topside 9,581 9,410 Jacket 7,440 7,320

Weight & Water : Depth

Scope of work

Detailed Design Pre-Conceptual Study Procurement Support Project Management Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

12

Client Location

: Petronas Carigali Vietnam Limited (PCVL) : Block 1 & 2, 164km (Topaz) from Vung Tau Port, S.R Vietnam : October 2007 September 2010 :
Platform Name TOPAZ Water Depth (M) 41 Dry Weight (MT) Topside 1,540 Jacket 950

Duration Weight & Water Depth

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

OUR EXPERIENCE

13

Client Location

: Carigali-PTTEPI Operating Company (CPOC) : CPOC JDA Block B 17 located in the Thailand Malaysia Joint Development Area : February 2007 April 2008

Duration

Scope of work : Pre-Conceptual Study Detailed Design Project Management Procurement Support Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

14

Client Location Duration

: Petronas Carigali Sdn Bhd (PCSB) / NATCO, USA : 185 km offshore Terengganu, Block PM313, Malaysia : August 2008 October 2010

Scope of work : Detailed Design Pre-Conceptual Study Procurement Support Project Management Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

15

Client Location

: Vietsovpetro : Block 09-1, Offshore of Socialist Republic of Vietnam, approximately 125km southwest Vung Tau : October 2009 April 2010 :
Platform Name RC1 RC3 Water Depth (M) 48 48 Dry Weight (MT) Topside 350 955 Jacket N/A N/A

Duration Weight & Water Depth

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

OUR EXPERIENCE
16

Client Location Duration Weight & Water Depth

: Sarawak Shell Berhad : 50 km Offshore Miri, Sarawak, Malaysia : November 2008 August 2010 :
Platform Name LAILA Water Depth (M) 76 Dry Weight (MT) Topside 640 Jacket N/A

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

OUR EXPERIENCE

17

Client Location Duration Weight & Water Depth

: Dragon Oil Turkmenistan : 35km of Turkmenistan in the Caspian Offshore : April 2010 Present :
Platform Name LAM C Water Depth (M) 35 Dry Weight (MT) Topside 2,000 Jacket 800

Scope of work

Pre-Conceptual Study Detailed Design Project Management Procurement Support Conceptual Design Follow on Engineering Front End Engineering Design

OUR EXPERIENCE

18

Client Location Duration Weight & Water Depth

: LAM SON JOINT OPERATING COMPANY : 120 km East of Vung Tau : September 2010 January 2011
Water Depth (M) 70 Dry Weight (MT) Topside 1,482 Jacket 3,523

Platform Name THANG LONG

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering

19

OUR EXPERIENCE

Client Location Duration Weight & Water Depth

: Pars Oil & Gas Company / PIRE Co. : 100km South East of Akhtar in the Persian Gulf : November 2010 Present
Dry Weight (MT) Topside 2,470 2,470 2,380 2,380 Jacket 1,997 1,986 2,025 2,044

Platform Name SPD22 SPD23 SPD24A SPD24B

Water Depth (M) 65.60 64.60 66.80 67.90

Scope of work : Pre-Conceptual Study Project Management Conceptual Design Front End Engineering Design Detailed Design Procurement Support Follow on Engineering