Você está na página 1de 88

Project Preparation and Administration

Bridge Module

Why are bridges part of this training?


Big cost. Long Process Design is complicated Tough Decisions

R1 Trails Project Preparation

But they are Fun!

Proud crew!

Trails do nothing more than connect the Bridges!

R1 Trails Project Preparation

Training Focus
Bridge Design Process
 Decisions to be

made.  How to make those decisions!

R1 Trails Project Preparation

Training Focus
Northern Region Standard Trail Bridge Plans
   

Intended uses Limitations, Inappropriate Uses Costs Maintenance

Wilderness Bridges Helicopter Usage Preservative Treatments If there is time NP Wilderness Bridge Project Presentation

R1 Trails Project Preparation

Authorities
All Decisions Line Office Approval of Bridge Design Director of Engineering
 Unless using

Regional Standard Trail Bridge Designs Forest Engineer.

All Trail Bridges need to be designed!


R1 Trails Project Preparation

Bridge in Bob Marshall Wilderness

Authorities
Design Resources Available.
 Forest Engineer  Regional Bridge Group

 John Kattell  David Scovell

Our job is to provide technical assistance to Forest personnel and complete and/or approve all bridge designs.

R1 Trails Project Preparation

Bridge Design Process


Function (To bridge or not? Replace or remove?) Project Scope** Who is User? ROS? TMO? Force Account/Contract?

**Contact FE and /or RO during Project Scope

Location/Survey Where is best spot? Many decisions. Preliminary Design Project Funding and Scope finalized.

Plans, Specs, Estimates.

Final Design Construction COR

R1 Trails Project Preparation

Project Initiation and Scope


Function
 To Bridge or Not to

Bridge?  Replace or remove?  Preliminary Engineering needed?

Factors?
 TMO & ROS  User Safety  Resource Protection  Others?

Albino Trail Bridge Site - Gal


R1 Trails Project Preparation

Funding Feasibility Aesthetics Wilderness

Bridge Design Process


In general, more complicated than road bridges. Why?
 Defining the User  Location  Access  Wilderness  Size?

R1 Trails Project Preparation

Bridge Design Process


Dome Mtn. On Ktn.
 24-foot span  Wilderness  6-mile from TH but

4000 ft elevation gain.  Force Account  Dangerous work.

R1 Trails Project Preparation

Bridge Design Process


Iron Springs on D-P
 50-foot span  Easy access  Total cost -

Maah-Taah-Hey Trail

~$35,000  Contract

R1 Trails Project Preparation

Project Initiation and Scope


Define the User (TMO & ROS)
Pedestrians Stock ATVs Bicycles Administration vehicles  Outfitters / other permittees     
 User affects size, design

and cost.  Bridge many times limits the user!

R1 Trails Project Preparation

Project Initiation and Scope


Force Account or Contract? (Effects design
decisions!)

 Design (in house or A/E)  Complexity of bridge project.  Availability of Forest or RO Engineers  Funding  Typically, R1 designs are done in house.  Construction  Safety  Force Account capability, skill level, and availability.  Complexity of bridge.  Funding  Pros and Cons

R1 Trails Project Preparation

Force Account or Contract?


Goat Creek on NP
Remote site required packing all materials. Simple construction NP has trained Crews. Force Account

R1 Trails Project Preparation

Force Account or Contract?


Yellow Mule on Gallatin Bridge part of a larger trail construction project. Short distance from trailhead. Complicated construction Contract

R1 Trails Project Preparation

Force Account or Contract?


Mystic on Custer
Site at trailhead. Working over large water penstock and tracks. Needed large equipment Contract

R1 Trails Project Preparation

Project Initiation and Scope


Summary
 Function (To bridge or not to bridge)  Define Users.  Force Account versus Contract  Funding. Project a go or no go?  May need some preliminary engineering

this early.

Who makes these decisions?


R1 Trails Project Preparation

Location / Survey
Location
 Narrowest spot?  Not necessarily  Stable stream reach.  Where users want it!  Good trail

Survey - Varies
 Simple small creek

 Profile of trail and stream with few xsections.  Sketches


 Complex

approaches for user


(function for hikers vs stock vs snomobiles vs ATVs)

 Full site survey of area.  Geotechnical (drilling)


 In general, experienced

bridge engineer may get by with less.

R1 Trails Project Preparation

Location / Survey
Holter Cut on Btr. No survey done.

R1 Trails Project Preparation

Location / Survey
Little Salmon on Flathead in Bob Marshall. Full site survey completed. Needed for hydraulic analysis.

R1 Trails Project Preparation

Preliminary Design
Determine
 Span  Height  Width  Bridge Type  Foundations  FA or Contract  Cost

Factors
Crossing and height Flood waters, Clearance User Span, location, aesthetics Site geology See earlier slide All of the above.

R1 Trails Project Preparation

Preliminary Design
Two biggest problems in R1

Bridges too short.


Abutments scour and fail Resource damage

R1 Trails Project Preparation

Preliminary Design
Bridges are too low!

R1 Trails Project Preparation

Preliminary Design
Sill-Thru Configuration  Little work in water.  Hydraulically efficient. (less susceptible to scour).  More $ in superstructure, less in abutments.  No wingwalls needed.

R1 Trails Project Preparation

Preliminary Design
Vertical Wall Configuration  More work in water.  Hydraulically less efficient. (more susceptible to scour).  Less $ in superstructure, more in abutments.  Need wingwalls

R1 Trails Project Preparation

Preliminary Design
Span Length
 Field Estimate (Rule of Thumb) typical spill-thru bridge.

BH

Span Length (L)

Estimated Span Length (L) = BW + 3 x BH  BW Channel bottom width  BH Bridge height from channel bottom to trail tread.

R1 Trails Project Preparation

Preliminary Design
Span Length
 Field estimate must be verified on paper.  Do not undersize.  Better to spend more on span than abutments.  Evaluate existing bridge (did it function OK)  Iterative process with what?  Bridge height
 What controls bridge height?

R1 Trails Project Preparation

Preliminary Design
What controls bridge height?
 Trail height  Bridge structure

depth
 Rule of thumb 1/20 x span
 Clearance for debris

 Minimum 2 feet above high water (100 yr flood) to bottom of bridge.

Little Salmon on Flathead

R1 Trails Project Preparation

Preliminary Design
Span Length Vertical Wall abutment

BH

Span Length (L)

 Span Length = Bankfull +. Must be able to pass

flood without damage to bridge or stream.  Footings must be below stream bed as minimum unless on bedrock.
R1 Trails Project Preparation

Preliminary Design
Factors for Bridge Width - Users - Railing

Bridge w/o railing

R1 Trails Project Preparation

Preliminary Design
Variable widths
Single log 14 Stock w/railing 8 Snowmobile 16+ Manual guidance but can be anything.

Bridge with railing


R1 Trails Project Preparation

Preliminary Design
Bridge Types
 Single Log  Timber stringer  Glu-lam stringer  Truss  Suspension  Packable

Factors
Span Access Aesthetics Materials

R1 Trails Project Preparation

Preliminary Design
Foundations
 Spread footings  Gabions  Geocell  Walls

Factors
 Site geology  Site materials  Access  Scour Potential

Generally we use spill-thru configuration with timber sill on gabion or geocell.

R1 Trails Project Preparation

Preliminary Design
Costs
 Very difficult to estimate.  No rules of thumb.  Procedure  Take off and price materials (variable)  Crew up labor.
 $2500/day for crew of 4 with misc.tools/equipment  Or use Davis Bacon rates

 Estimate Equipment needed (cranes, backhoe, helicopter)

R1 Trails Project Preparation

Preliminary Design
Costs - continued
 Materials  Sawn Timber  GL timber  Bolts/hardware  Concrete  Reinforcing Steel  Gabions  Geocell  Geocell fill
R1 Trails Project Preparation

$1350/mfbf $2500/mfbf $3.00/lbs. $600 - $1000/cy $1.25/lb $125/cy $15/cy $25-$75/cy

Preliminary Design
Costs - continued
 Equipment  Excavator  Backhoe  Dump Truck  Crane (Light)  Crane (medium)  Helicopters  Packing
$130/hr $80/hr $75/hr $350/hr $650/hr See later slides

$225/mule trip (180 lbs per mule)

R1 Trails Project Preparation

Preliminary Design

Typical work items to accomplish for labor.


 Project Management  Mobilization  Excavation  Build Abutments  Install Superstructure  Build Approach walls  Build Approach fills

Less Common Work Items


 Helicopter use.  Packing Materials  Supply Camp  Install Falsework.

R1 Trails Project Preparation

Preliminary Design
Nail Lam built 15 years ago. Replace with glulam stringer bridge. On sills. Wilderness Use Helicopter to fly in stringers. Estimate based on Contract Construction Flood Creek Custer

R1 Trails Project Preparation

R1 Trails Project Preparation

Preliminary Design
Whose Responsibility / Authority for preliminary decisions?

Forest!
However, Engineering must assist! Why? Call FE and or RO during Project Scope for assistance with alternatives and options.  Meet with Rec staff and Ranger to discuss preliminary design options and alternatives.

R1 Trails Project Preparation

Preliminary Design
At this point
 Re-evaluate Project Scope!  Re-evaluate Funding!

Why?
 Many times each site has several

alternatives being evaluated.  Must select Final Design Alternative.

R1 Trails Project Preparation

Final Design, PS&E


Typically done by Engineering Plans (as a minimum)
 Title Sheet (signatures)  Bridge Layout (Plan and Elevation)  On site plan from survey.  Abutment/foundation details  Superstructure details  Miscellaneous details

R1 Trails Project Preparation

Final Design, PS&E


Specifications
 FP-03, Standard Specifications for

Construction of Roads and Bridges on federal Highway Projects.  Special Project Specifications as needed.

R1 Trails Project Preparation

Final Design, PS&E


Estimates
 Estimated Construction Costs  Update of preliminary estimate  Estimated Schedule for Construction

R1 Trails Project Preparation

Final Design, PS&E


Plans, Specs and Estimates
 All 3 required.  Any difference for Force Account vs

Contract?
 Shouldnt be!
 Authorities  Regional Engineer must approve PS&E package, UNLESS  Using Standard Plans, then FE has authority to approve PS&E package.

R1 Trails Project Preparation

Construction
All Trail Bridge Construction is to be administered and inspected by
 Certified COR, Level III  With appropriate technical endorsements.  Any difference for Force Account vs

Contract?
 NO!
 RO will assist as needed or requested.

R1 Trails Project Preparation

Trail Bridge Standard Plans


Pre-designed and detailed drawings for:
 Typical Trail
Iron Springs on Maay-Daay-Hey Trail

Bridge Superstructures  Typical simple substructures (sills).

R1 Trails Project Preparation

Trail Bridge Standard Plans


Intended Uses
 Simple, single spans  Spans less than 60 feet  Adapted for each site.  FE can approve.

Limitations
 At discretion of FE only.  Not for complex bridges.  Not for difficult

abutments.  Still requires, survey, hydraulic analysis, soils, etc.

R1 Trails Project Preparation

Trail Bridge Standard Plans


Typical Superstructures:
 Solid Sawn Timber Stringer  Log Stringer  Glu-lam timber stringer  Glu-lam longitudinal slab  Single log  Nail-lam longitudinal slab  Prefabricated steel truss  Packable spliced stringer

Drawing #
R1920 R1921 R1922 R1923 R1924 R1925 R1926 R1927

R1 Trails Project Preparation

Trail Bridge Standard Plans


Typical abutment details
Various types of sills used

Drawing #
R1930-34

Will need to be customized for each site.

R1 Trails Project Preparation

Trail Bridge Standard Plans


Sawn Timber Stringer
 Spans 10 to 40 feet  Any width  Stringers 3x10 to 8x24  ROS - ???  Economical if you have

used stringers.  But stringer quality large than 4x10 gets iffy.  Costs increase significantly with larger stringers.

R1 Trails Project Preparation

Trail Bridge Standard Plans Sawn Stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


Log Stringer
 Spans 10 to 45 feet.  Any width.  Diameter from 8 to

22  ROS ???  Costs are higher Than other types for similar spans.  More difficult to build and maintain.

R1 Trails Project Preparation

Trail Bridge Standard Plans Log Stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


Glu-laminated Stringer
 Spans 25 to 60 feet.  Any width.  Stringers 3.125 x 15 to     

8.75 x 39. Requires diaphragms. ROS - ???? Most ecomomical for spans 40 feet or longer. Easy construction but requires larger equipment. Low maintenance.

R1 Trails Project Preparation

Trail Bridge Standard Plans GL Stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


GL Longitudinal Slab
 Spans 10 to 35 feet.  Best for widths < 8.  Come in panels, max     

4 width. ROS - ??? Very ecomomical Easy to build. Low maintenance Handrail more difficult to attach.

R1 Trails Project Preparation

Trail Bridge Standard Plans GL Longitudinal Slab

R1 Trails Project Preparation

Trail Bridge Standard Plans


Single Log Stringer
 User is hiker only.  Spans 10 to 45 feet.  Diameters 16 to 24  ROS ???.  Handrail is hard to

attach and align.  Handrail may be maintenance problem.

R1 Trails Project Preparation

Trail Bridge Standard Plans Single Log

R1 Trails Project Preparation

Trail Bridge Standard Plans


Nail-Lam Longitudinal Slab
 Spans 12 to 30 feet.  Best for widths < 8.  Materials 2x6 to 2x14.  ROS - ???  Labor intensive.  Materials less expensive but

labor is higher.  Good for sites short distance from trailhead but not accessible for equipment  Moderate maintenance.  Handrail difficult to attach.

R1 Trails Project Preparation

Trail Bridge Standard Plans Nail Laminated Slab

R1 Trails Project Preparation

Trail Bridge Standard Plans


Prefabricated Steel Truss
 Spans > 60 (Standard    

Plans limited to 100) Any width. ROS ??? Requires heavy equipment. Too heavy for economical use of helicopters. Requires manufacturer design and shop drawings. Low maintenance.

R1 Trails Project Preparation

Trail Bridge Standard Plans Prefabricated Truss

R1 Trails Project Preparation

Trail Bridge Standard Plans


Packable Bridge
 Span 36 feet or less.  Any width.  ROS - ???  Alternative to

helicopter use.  Expensive materials.  Labor intensive.  More difficult to build.  Increased maintenance.
R1 Trails Project Preparation

Trail Bridge Standard Plans Packable Bridge

R1 Trails Project Preparation

Trail Bridge Standard Plans


Abutment Details
 Sill designs - Spill-thru  Keep away from stream    

edge. Not applicable if scour issues. Do not stack sills to gain height. Place on geocell, gabion, or concrete pad. Need to be site adapted.

R1 Trails Project Preparation

Timber Cribbing & Rock Gabions

Sill on Gabion Sill on Timber crib on geocell

R1 Trails Project Preparation

Others Trail Bridge Types


Timber Truss
 Spans 50 to 100+

feet.  Any width  ROS ???  Labor intensive.  Difficult to build  Moderate maintenance.  Can be built with semi- primitive tools or heavy equipment.
R1 Trails Project Preparation

Others Trail Bridge Types Timber Truss

R1 Trails Project Preparation

Others Trail Bridge Types


Suspension Bridges
 Spans > 100 feet  Up to 8 feet.  ROS ???  Very difficult to

build.  Very high maintenance.  Very high cost

R1 Trails Project Preparation

General Guidance
Trail Types
Hiking Mountain Biking Pack and Saddle
Cross Country Skiing

Clear width
4 4
5 w/o rail 6 w/rail

Rail Height
42 54 54 42 Site specific 42 27

6 6 42 50

Snowmobile Motorcycle ATV


R1 Trails Project Preparation

General Guidance
Railing Are they needed?
Proposed manual direction says:
In general, rails shall be required for all trail and pedestrian bridges. However, railings may be eliminated and potentially curbs substituted for rails when an appropriate analysis as described below has been completed: An analysis has identified and evaluated the potential users and determined that the potential hazards along the trail are the same or greater than that of a bridge without a rail. The analysis shall include the possibility of using a rail on only one side of the bridge. In general, rural and urban ROS settings are likely to have small children and less experienced users. Thus, a railing is warranted in most instances. In backcountry or wilderness settings, where users are normally more experienced, rails may not be needed.

R1 Trails Project Preparation

General Guidance
Pettibone to left, Goat to below on NP. Selway wilderness.

R1 Trails Project Preparation

General Guidance
Dome Mtn. Kootenai. Cabinet Wilderness No Handrail!

R1 Trails Project Preparation

General Guidance
Type Sawn Stgr. Log Stgr. GL Stgr. GL Slab Single Log NL Slab Steel Truss Packable Tbr. Truss Suspension ROS Spans 10 to 40 10 to 45 25 to 60 10 to 35 10 to 45 12 to 30 > 60 < 36 > 60 > 100 Equipment Light Light/Med Medium Light Primitive/Light Primitive/Light Heavy Primitive/Light Light/Heavy Medium Maint. Low Low Low Low Low Moderate Low Moderate Moderate High Cost Low/Med Low/Med Low/Med Low Low Medium High High High High

R1 Trails Project Preparation

Wilderness Trail Bridges


Unique
 What is

appropriate?  What can you build?  Is a bridge needed? Bob Marshall Wilderness

R1 Trails Project Preparation

Wilderness Trail Bridges


Design Process Add conceptual design before Project Scope Need alternatives
 Bridge Type  Construction methods  Materials  Costs
Location/Survey

Conceptual Design

Project Scope

R1 Trails Project Preparation

Wilderness Trail Bridges


Minimum Tool analysis. Use of helicopters Force Account or Contract. Logistics!!

Wilderness bridges are the most complicated and expensive. Need special attention.

R1 Trails Project Preparation

Helicopter Usage
Helicopter contracts
 Type I (Heavy) Sky cranes, etc  Can pick up to 25,000 lbs.  On call contract $9000/hour  Must come out of West Coast.  Mob costs prohibitive.  Type II (Medium)  5000 to 12,000 lbs.  On call contract $4500/hour  Several in Montana, but not readily available.
R1 Trails Project Preparation

Helicopter Usage
Helicopter contracts
 Type III ( Light)  Can pick up to 5000lbs.  On call contract $1800/hour  For up to 3000 lbs, readily available.  Need to plan ahead and try to coordinate

with other work in the area to lower costs.

R1 Trails Project Preparation

Helicopter Usage
Helicopter Use - best value?
 Small helicopter  More trips  More on-site labor (fly one stringer at a time)  Big Helicopter  Less trips.  Less on site labor (fly in entire bridge superstructure)

R1 Trails Project Preparation

Preservative Treatments
What is life expectancy of permanent bridge? Life of untreated material?  15 to 20 years Life of treated material?  50 + years

R1 Trails Project Preparation

Preservative Treatments
Treated vs Untreated.
 Manual Direction fpr

permanent structures
 design life of 50 yrs
 However, exceptions are

made.  Who decides?


 Forest
 Treated material is

strongly recommended. Papoose Creek on Clwt NF

R1 Trails Project Preparation

Preservative Treatments
Protect the integrity of Treatment.
 Cutting ends, drilling

holes, all ruins treatment.

Blue Sky Bridge on Ktn NF

Field treatments have limited success. To apply field treatments, person needs training and certification. Hassle!

R1 Trails Project Preparation

Preservative Treatment
Any laws against Treatment?
 Only 1 by EPA  Can not use CCA in

members in direct contact with peoples skin.  No others.

However, do we want oily treatment on handrails?

R1 Trails Project Preparation

Preservative Treatment
Options
 Substructure,

stringers, deck, curbs


 Penta, Copper Naphthenate

 Handrail  Treated many choices  Untreated redwood or Red Cedar


Iron Springs - DPGL

Changing constantly

R1 Trails Project Preparation

Você também pode gostar