Você está na página 1de 26

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Management: An Introduction and Short Tutorial


Wayne Baggett

November 21, 2005

Space Telescope Science Institute

GSET Technical Seminar Series

Outline
What is Earned Value? Government Requirements Small Project Usage Why Use Earned Value? Earned Value in a Nutshell Conclusions
November 21, 2005 2

Space Telescope Science Institute

GSET Technical Seminar Series

What is Earned Value?


How does Dilbert know this?

November 21, 2005

Space Telescope Science Institute

GSET Technical Seminar Series

What is Earned Value?


Project Management Technique
Integrates technical performance requirements, resource planning, and cost accounting with schedule Provides insight into project status Provides early warning signals for problems

Provides a disciplined means of managing the project


November 21, 2005 4

Space Telescope Science Institute

GSET Technical Seminar Series

Government Requirements
OMB Circular A-11, Exhibit 300 (2004)
Requires EVMS for all major acquisitions Agencies must have ANSI-compliant EVMS in place by December 31, 2005 EVMS data must be used to identify problems and provide realistic final cost estimates as a part of decision packages

Federal Acquisition Regulations (2005) amended to require contractor-maintained EVMS


November 21, 2005 5

Space Telescope Science Institute

GSET Technical Seminar Series

Government Requirements
These requirements apply to large projects or programs; DOD requires
Contract Value $50M: validated ANSI-compliant EVMS, structured reports and reviews, ongoing surveillance $50M > Contract Value $20M: ANSI-compliant EVMS (validation not required), tailored reports and reviews, ongoing surveillance Contract Value < $20M: EVMS optional, ongoing surveillance

Very rigid, heavily constrained system at this level


November 21, 2005 6

Space Telescope Science Institute

GSET Technical Seminar Series

Small Project Usage


Small projects provide the best opportunities for earned-value employment
Consider its use for all in-house funded developmental projects where a firm commitment is made to management. Software projects can especially benefit from the employment of a simple earned-value approach.
(Fleming and Koppelman, Earned Value Project Management: A Powerful Tool for Software Projects, Crosstalk, July, 1998, p. 19.)
November 21, 2005 7

Space Telescope Science Institute

GSET Technical Seminar Series

Small Project Usage


The Personal Software Process (PSPSM) and Team Software Process (TSPSM) use EVM
PSP has practitioners estimate task efforts and track their actual efforts
Tasks estimated are very small about 10 hours each
Data are used to improve future estimates

TSP expands the use of EVM to the project level Use of PSP and TSP helps projects meet their commitments (Tuma, D. and Webb, D., Personal Earned Value:
Why Projects Using the Team Software Process Consistently Meet Schedule Commitments, Crosstalk, March 2005, p. 17.)
PSP and TSP are registered service marks of Carnegie Mellon University
November 21, 2005 8

Space Telescope Science Institute

GSET Technical Seminar Series

Small Project Usage


Several projects at STScI have used EVM:
Most used a tailored version of EVM JWST S&OC development
FOS, PPS, PRDS

JWST FITS Writer development INS Master Schedule development DMS Automated Test System development
November 21, 2005 9

Space Telescope Science Institute

GSET Technical Seminar Series

Why Use Earned Value?


Obligates planning to the level of task management
Less likely to overlook work

Provides objective measures of progress Allows early detection of budget and schedule problems Allows an objective projection of eventual project cost and schedule
November 21, 2005 10

Space Telescope Science Institute

GSET Technical Seminar Series

Key to Earned Value


Determine the value for every task prior to starting work!

November 21, 2005

11

Space Telescope Science Institute

GSET Technical Seminar Series

Guidelines for Setting/Earning Value


Use a consistent unit of measurement that makes sense for the project
Dollars required for large govt projects Hours useful on small projects; PSPSM Arbitrary number not recommended, but still used

Consider task duration Select Earned Value Methods that are as objective as possible

November 21, 2005

12

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Methods


Method Equivalent Units 0-100 50-50 Usage Value based on completed portion of a large number of completed activities Value earned upon completing work that starts and ends within one status period Part of value earned when work starts and remainder when it ends, usually when work straddles two reporting periods; percentages are determined by the manager Value earned at the completion of objective milestones; usually for work that straddles several consecutive status periods Value earned is prorated based on a portion earned for another unit of work Value earned based on subjective estimate; usually for work that has no objective measure of completeness Value based on passage of time; usually for work that cannot be defined or measured Examples S/W Implementation, H/W Production Outlines, Document Preparation, Formal Reviews Short Engineering Analyses, System Design, Build and Acceptance Tests Long-Term Analyses, System Design, Requirements Definition QA, Configuration Management, Database Management Long-Term Studies, Maintenance and Operations Project Management, Receptionist, Help Desk 13

Interim Milestones Apportioned Effort Percent Complete Level of Effort

November 21, 2005

Objectivity

Space Telescope Science Institute

GSET Technical Seminar Series

Example: Planned vs. Actuals


$250 $200

Current Date

Value ($1000s)

$150 Planned Actual $100

$50

$13,000 under budget!

$-

11/26/2005

10/28/2006

12/23/2006

11/24/2007

7/8/2006

9/2/2006

6/9/2007

10/1/2005

1/21/2006

3/18/2006

5/13/2006

2/17/2007

4/14/2007

8/4/2007

9/29/2007

1/19/2008

3/15/2008

Date
November 21, 2005 14

5/10/2008

Space Telescope Science Institute

GSET Technical Seminar Series

Example: Earned Value


$250

PV
$200

BAC=$200

Value ($1000s)

$150

PMB
$100

PV EV AC

SV=EV-PV=($30)
$50

CV=EV-AC=($17)

AC
$11/26/2005 10/28/2006 7/8/2006 9/2/2006 10/1/2005 1/21/2006 3/18/2006 5/13/2006

EV
12/23/2006 11/24/2007 6/9/2007 2/17/2007 4/14/2007 8/4/2007 9/29/2007 1/19/2008 3/15/2008 5/10/2008

Date
November 21, 2005 15

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Concepts


Planned Value (PV) planned cost of doing the scheduled work (formerly BCWS) Earned Value (EV) planned cost of the work completed (formerly BCWP) Actual Cost (AC) actual cost of the work completed (formerly ACWP) Performance Measurement Baseline (PMB) the time-phased budget plan against which performance is measured
November 21, 2005 16

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Concepts (cont.)


Schedule Variance (SV) measures how project is doing relative to the schedule SV = EV PV
Positive Ahead of Sched., Negative Behind Sched.

Cost Variance (CV) measures how project is performing; productivity measure CV = EV AC


Positive Efficient, Negative Inefficient
November 21, 2005 17

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Concepts (cont.)


Budget Variance (BV) measures how project is doing against the budget BV = PV AC
Positive Under Budget, Negative Over Budget

Budget At Completion (BAC) sum of the planned value plus the Undistributed Budget
November 21, 2005 18

Space Telescope Science Institute

GSET Technical Seminar Series

Example: Earned Value


$250

EAC=AC + ETC=$233 SPI=EV/PV=0.70

$200

Value ($1000s)

CPI=EV/AC=0.81
$150

PV EV AC

$100

VAC=BAC-EAC=($33)
ETC=(BAC-EV)/CPI=$146
11/26/2005 10/28/2006 12/23/2006 11/24/2007 10/1/2005 1/21/2006 3/18/2006 5/13/2006 2/17/2007 4/14/2007 9/29/2007 1/19/2008 3/15/2008 5/10/2008 7/8/2006 9/2/2006 6/9/2007 8/4/2007

ETC

$50

$-

Date
November 21, 2005 19

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Concepts (cont.)


Schedule Performance Index (SPI) measure of schedule compliance: is work being done at the planned rate? SPI = EV/PV
<1 Slower than planned, >1 Faster than planned

Cost Performance Index (CPI) productivity measure: is the work costing what was expected? CPI = EV/AC
< 1 Inefficient, > 1 Efficient
November 21, 2005 20

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Concepts (cont.)


Estimate To Complete (ETC) estimate of the effort required to complete the project from the current date ETC = (BAC EV)/CPI Estimate At Completion (EAC) the estimated total cost of the project EAC = AC + ETC
November 21, 2005 21

Space Telescope Science Institute

GSET Technical Seminar Series

Earned Value Concept Summary


Acronym PV Definition Budgeted cost of task Equation (none) Interpretation

EV
AC SV BV CV BAC SPI CPI ETC EAC VAC

Earned value for task


Actual cost of task Schedule Variance Budget Variance Cost Variance Budget At Completion Schedule Perf. Index Cost Perf. Index Estimate to Complete Estimate At Completion Variance at Completion

(none)
(none) SV=EV - PV BV=PV - AC CV=EV - AC BAC= UB + S PV SPI=EV/PV CPI=EV/AC ETC=(BAC-EV) /CPI EAC=AC+ETC VAC = BAC - EAC
>0 = Under, <0 = Over >0 = Ahead, <0 = Behind >0 = Under, <0 = Over >0 = Productive, <0 = Unproductive UB=Undistributed Budget >1 = Faster, <1 = Slower >1 = Efficient, < 1 = Inefficient

November 21, 2005

22

Space Telescope Science Institute

GSET Technical Seminar Series

Costs of EVMS
Marginal cost of using EVMS is estimated at less than 1% to a few% of total contract cost
Based mainly on large DOD contracts with experienced EVMS users Some costs are unnecessary according to EVMS criteria, but effort is put into those activities anyway

Expect costs to be higher at STScI due to inexperience in using EVM and our culture
Mitigated by our implementation
Christensen, David S., The Costs and Benefits of the Earned Value Management Process, Acquisition review Quarterly, Fall, 1998, p. 373.

November 21, 2005

23

Space Telescope Science Institute

GSET Technical Seminar Series

Benefits of Earned Value


It is a single management control system that provides reliable data. It integrates work, schedule, and cost using a work breakdown structure. The associated database of completed projects is useful for comparative analysis. The cumulative cost performance index (CPI) provides an early warning signal. The schedule performance index provides an early warning signal.
Christensen, David S., The Costs and Benefits of the Earned Value Management Process, Acquisition review Quarterly, Fall, 1998, p. 373.
November 21, 2005 24

Space Telescope Science Institute

GSET Technical Seminar Series

Benefits of Earned Value


The CPI is a predictor for the final cost of the project. It uses an index-based method to forecast the final cost of the project. The to-complete performance index allows evaluation of the forecasted final cost. The periodic (e.g., weekly or monthly) CPI is a benchmark. The management by exception principle can reduce information overload.
Christensen, David S., The Costs and Benefits of the Earned Value Management Process, Acquisition Review Quarterly, Fall, 1998, p. 373.
November 21, 2005 25

Space Telescope Science Institute

GSET Technical Seminar Series

The most common problem product teams face is unreasonable schedule pressure. When teams are forced to work to unreasonable schedules, they are unable to make useful plans. Every plan they produce misses managements edicted schedule and is therefore unacceptable. As a result, they must work without the guidance of an orderly plan. Under these conditions, the team will generally take much longer to complete the project than they otherwise would.
Watts Humphrey, Pathways to Process Maturity: The Personal Software Process and Team Software Process, SEI Interactive, June 1999.

November 21, 2005

26

Você também pode gostar