22 16/Out/22 23/Out/22 30/Out/22 06/Nov/22 13/Nov/22 20/Nov/22 27/Nov/22 04/Dez/22 11/Dez/22 18/Dez/22 25/Dez/22 01/Jan/23 08/Jan/23 15/Jan/23 22/Jan/23 29/Jan/23 05/Fev/23 12/Fev/23 19/Fev/23 26/Fev/23 05/Mar/23 12/Mar/23 19/Mar/23 26/Mar/23 02/Abr/23 09/Abr/23 16/Abr/23 23/Abr/23 30/Abr/23 07/Maio/23 14/Maio/23 21/Maio/23 28/Maio/23
Tarefa S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S D S T QQ S S
0 0 Projeto 163,75 dias?Seg 03/10/22 Qui 27/04/23
5 5 5 Concretagem 5 dias Qua 16/11/22 Ter 22/11/22 3;4 Concretagem[150 M³];Pedreiro[200%];Servente de Obras[200%]
7 7 7 Instalações Elé. 15 dias Seg 12/12/22 Sex 30/12/22 Instalações Elét. E Hidr.[450 M²];Encanador;Eletricista
E Hidr
8 8 8 Chapisco 20 dias Sex 30/12/22 Qua 25/01/23 6;7 Chapisco[800 M²];Pedreiro[200%];Servente de Obras[200%]
9 9 9 Emboço Interno 15 dias Qua 25/01/23 Seg 13/02/23 8 Emboço Interno[600 M²];Pedreiro[200%];Servente de Obras[200%]
10 10 10 Emboço 5 dias Seg 12/12/22 Sex 16/12/22 6 Emboço Externo[150 M²];Pedreiro[200%];Servente de Obras[200%]
Externo
12 12 12 Cerâmica Piso 30 dias Sex 03/03/23 Seg 10/04/23 11 Cerâmica Piso[200 M²];Pedreiro[200%];Servente de Obras[200%]
13 13 13 Azulejo Parede 5 dias Seg 10/04/23 Seg 17/04/23 12 Azulejo Paredes[100 M²];Pedreiro[200%];Servente de Obras[200%]
14 14 14 Esquadrias 10 dias Sex 03/03/23 Qui 16/03/23 10;11 Esquadrias[20 UNID];Pedreiro[200%];Servente de Obras[200%]
15 15 15 Louças e 5 dias Seg 17/04/23 Sáb 22/04/23 12;13 Louças e Metais[1 UNID];Pedreiro;Servente de Obras
Metais
16 16 16 Pintura Interna 20 dias Qui 16/03/23 Seg 10/04/23 14 Pintura Interna[600 M²];Pintor[200%];Ajudante de Pintor[200%]
17 17 17 Pintura Externa 10 dias Seg 10/04/23 Sáb 22/04/23 16 Pintura Fachada[300 M²];Pintor[200%];Ajudante de Pintor[200%]
Projeto: Projeto Tarefa Marco Resumo do projeto Marco Inativo Tarefa Manual Acúmulo de Resumo Manual Somente início Tarefas externas Data limite Marco de Linha de Base Andamento
Data: Qui 29/09/22 Divisão Resumo Tarefa Inativa Resumo Inativo Somente duração Resumo Manual Somente término Marco externo Linha de Base Resumo da Linha de Base Progresso manual