EAP - ESTRUTURA ANALITICA DO PROJETO

CLIENTE ALLMONT
PROJETO CMAI III
PESO (%) Ano 2021
ID

GERAL
Mês JANEIRO FEVEREIRO MARÇO ABRIL
Semana 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Início 18/1 25/1 1/2 8/2 15/2 22/2 1/3 8/3 15/3 22/3 29/3 5/4 12/4 19/4 26/4 3/5 10/5
100,00%
Término 24/1 31/1 7/2 14/2 21/2 28/2 7/3 14/3 21/3 28/3 4/4 11/4 18/4 25/4 2/5 9/5 16/5

P 1,61% 4,04% 8,70% 14,67% 22,37% 32,17% 44,05% 57,37% 70,92% 83,10% 92,30% 97,43% 100,00%
1 1 - SERVIÇOS GERAIS 25,38%
R 2,2% 5,8% 11,9% 16,9% 29,6% 39,0% 45,0% 57,2% 68,7%

P 2% 5,60% 11,78% 20,07% 31,19% 45,21% 61,11% 76,73% 89,38% 96,85% 100,00%
2 2 - FABRICAÇÃO DE SPOOL 74,62%
R 3,8% 7,3% 16,1% 26,8% 33,7% 47,9% 62,4%

PREVISTO NA SEMANA 0,41% 0,62% 2,60% 4,27% 6,57% 8,67% 11,31% 13,85% 15,30% 14,75% 11,77% 6,88% 3,00% -100,00%
PREVISTO ACUMULADO 0,41% 1,03% 3,63% 7,90% 14,47% 23,14% 34,45% 48,30% 63,60% 78,35% 90,12% 97,00% 100,00%
REAL DA SEMANA 0,56% 0,91% 4,39% 3,88% 9,77% 10,40% 6,66% 13,68% 13,75% -64,00%
REAL ACUMULADO 0,56% 1,47% 5,86% 9,74% 19,51% 29,91% 36,57% 50,25% 64,00%
SITUAÇÃO DA OBRA 0,2% 0,4% 2,2% 1,8% 5,0% 6,8% 2,1% 2,0% 0,4% -78,4% -90,1% -97,0% -100,0%

CURVA "S"
100,00%
90,00%
80,00%
70,00%
60,00%

50,00%
40,00%
30,00%
20,00%
10,00%
0,00%
3 4 5 6 7 8 9 10 11 12 13 14 15 16

Série5 Série1