TABELA DE MATERIAIS

E & P – BC / GELOG / GEINSP (CONFORME TABELA UCS-23 CÓDIGO ASME VIII - DIV. 1)

CLASSE FORMA CLASSIF. TENSÕES ADMIS. P/ TEMP. - 30 A 325 ºC


DO DE MATERIAL (PARA OUTRAS FAIXA DE TEMP. DE PROJ. VERIFICAR VALORES)

MAT. APRESENT. ASTM KPa Kgf / cm2 PSI


AÇO CHAPA A-285-C 95,000 968.71 13,775.00
TUBO COND. A-53-A 83,000 846.35 12,035.00
TUBO COND. A-53-B 103,000 1,050.29 14,935.00
TUBOT.C. A-179 81,000 825.96 11,745.00
CARB. FORJADO A-181-60 103,000 1,050.29 14,935.00
AÇO CHAPA A-515-55 95,000 968.71 13,775.00
CARB. CHAPA A-515-60 103,000 1,050.29 14,935.00
Si CHAPA A-515-65 112,000 1,142.06 16,240.00
CHAPA A-515-70 120,000 1,223.64 17,400.00
TUBO COND. A-106-A 83,000 846.35 12,035.00
PARA
TUBO COND. A-106-B 103,000 1,050.29 14,935.00
ALTAS TUBO T.C. A-210-A1 103,000 1,050.29 14,935.00
FORJADO A-105 120,000 1,223.64 17,400.00
TEMPER. FUNDIDO A-216-WCB 120,000 1,223.64 17,400.00
AÇO CHAPA A-516-55 95,000 968.71 13,775.00
CARB. CHAPA A-516-60 103,000 1,050.29 14,935.00
CHAPA A-516-65 112,000 1,142.06 16,240.00
Si CHAPA A-516-70 120,000 1,223.64 17,400.00
PARA TUBO COND. A-333-6 104,000 1,060.49 15,080.00
TUBO T.C. A-334-6 103,000 1,050.29 14,935.00
BAIXAS FORJADO A-350-LF1 104,000 1,060.49 15,080.00
FORJADO A-350-LF2 121,000 1,233.84 17,545.00
TEMPER. FUNDIDO A-352-LCB 112,000 1,142.06 16,240.00
AÇO CHAPA A-204-A 113,000 1,152.26 16,385.00
CHAPA A-204-B 121,000 1,233.84 17,545.00
LIGA
TUBO COND. A-335-P1 85,000 866.74 12,325.00
TUBO T.C. A-209-T1 95,000 968.71 13,775.00
FORJADO A-182-F1 121,000 1,233.84 17,545.00
1/2 Mo FUNDIDO A-217-WC1 112,000 1,142.06 16,240.00
AÇO CHAPA A-387-11 cl 1 103,000 1,050.29 14,935.00
LIGA TUBO COND. A-335-P11 103,000 1,050.29 14,935.00
TUBO T.C. A-199-T11 103,000 1,050.29 14,935.00
1 1/4
TUBO T.C. A-213-T11 103,000 1,050.29 14,935.00
Cr FORJADO A-182-F11 121,000 1,233.84 17,545.00
1/2 Mo FUNDIDO A-217-WC6 121,000 1,233.84 17,545.00
AÇO CHAPA A-387-22 cl 1 103,000 1,050.29 14,935.00
LIGA TUBO COND. A-335-P22 103,000 1,050.29 14,935.00
TUBO T.C. A-199-T22 103,000 1,050.29 14,935.00
TUBO T.C. A0213-T22 103,000 1,050.29 14,935.00
21/4 Cr FORJADO A-182-F22 (*) 119,000 1,213.44 17,255.00
1 Mo FUNDIDO A-217-WC9 (*) 114,000 1,162.46 16,530.00
AÇO CHAPA A-387-5 cl 11 (*) 94,000 958.52 13,630.00
LIGA TUBO COND. A-335-P5 (*) 94,000 958.52 13,630.00
TUBO T.C. A-199-T5 (*) 88,000 897.34 12,760.00
5 Cr
TUBO T.C. A-213-T5 (*) 94,000 958.52 13,630.00
FORJADO A-182-F5 (*) 110,000 1,121.67 15,950.00
1/2 Mo FUNDIDO A-217-C5 (*) 140,000 1,427.58 20,300.00
OBS.: 1) TUBO COND. - TUBOS PARA CONDUÇÃO; TUBO T.C. - TUBO PRA TROCA TÉMICA; TODOS OS TUBOS SEM COSTURA.
2) OS MATERIAIS ASSINALADOS COM ASTERISCO (*), OS VALORES DE TENSÃO ADMISSÍVEL SÃO PARA FAIXA DE TEMPERATURA 375 ºC.

E & P – BC / GELOG / GEINSP


TABELA MATERIAIS
TABELA DE MATERIAIS
E & P – BC / GELOG / GEINSP (CONFORME TABELA UCS-23 CÓDIGO ASME VIII - DIV. 1)

CLASSE FORMA CLASSIF. TENSÕES ADMISSÍVEIS P/ TEMP. -30 A 325 ºC


DO DE MATERIAL (PARA OUTRAS FAIXA DE TEMP. DE PROJ. VERIFICAR VALORES)

MAT. APRESENT. ASTM KPa Kgf / cm2 PSI


AÇO CHAPA A-203-B 120,000 1,223.64 17,400.00
LIGA TUBO COND. A-333-7 112,000 1,142.06 16,240.00
2 TUBO T.C. A-334-7 112,000 1,142.06 16,240.00
1/2 Ni FUNDIDO A-352-LC2 121,000 1,233.84 17,545.00
AÇO CHAPA A-203-D 112,000 1,142.06 16,240.00
LIGA TUBO COND. A-333-3 112,000 1,142.06 16,240.00
TUBO T.C. A-334-3 112,000 1,142.06 16,240.00
3 1/2 Ni FUNDIDO A-352-LC3 121,000 1,233.84 17,545.00

OBS.: 1) TUBO COND. - TUBOS PARA CONDUÇÃO; TUBO T.C. - TUBO PRA TROCA TÉMICA; TODOS OS TUBOS SEM COSTURA.
2) OS MATERIAIS ASSINALADOS COM ASTERISCO (*), OS VALORES DE TENSÃO ADMISSÍVEL SÃO PARA FAIXA DE TEMPERATURA 375 ºC.