Concreto Ponton L=5.

00 m
a = 0.95
b = 0.80
c = 0.40 a b c d e
d = 0.15
e = 0.10 f
f = 0.45
g = 3.20
hc = 0.80 g
B = 2.40
A = 1.00 1 2 3 4
br = 0.45
Ac= 5.00 5 hc
Ancho= 6.00
hzolado= 0.30 B

Pantalla
A2 = bx(g+f) = 2.92
A3 = cxg = 1.28
A4 = d*g/2 = 0.24
A5 = B*hc = 1.92
A6 = (b+c)*(f+g) = 4.38

VZolado = B*hzolado
VZolado = 4.32

Vf'c=140 kg/cm2 = B*hc*Ancho


Vf'c=140 kg/cm2 = 11.52

Vf'c=175 kg/cm2 = (A2+A3+A4)*Ac+A6*(Ancho-Ac)


Vf'c=175 kg/cm2 = 26.58

Aletas
Area Zapata = 5.76
VZolado = 1.73

Vf'c=140 kg/cm2 = 4.61

Area Aleta = (3.65+0.5)*2.44/2


Vf'c=175 kg/cm2 = 5.06

Losa
L= 5.80 m
Ac = 5.00 m
f= 0.45 m
Ver = 0.50 m
eVer = 0.25 m
hParapeto = 0.60 m
eParapeto = 0.15 m

Vlosa = L*Ac*e
Vlosa = 13.05 m3

Vver = 2*L*(2*Ver+0.05)*ever/2
Vver = 1.52 m3

VParapeto = 2*L*hParapeto*eParapeto
VParapeto = 1.04 m3

V= 15.62 m3
Concreto

PONTON L=5.00 M
Pantalla Aletas Losa
Total (m3)
Cantidad V Parcial (m3) Cantidad V Parcial (m3) V Parcial (m3)
V Zolado 2 4.32 4 1.73 15.55
Vf'c=140 kg/cm2 2 11.52 4 4.61 41.47
Vf'c=175 kg/cm2 2 26.58 4 5.06 73.41
Vf'c=210 kg/cm2 15.62 15.62
Encofrado (L=5.00 m)

a = 0.95
a b c d e
b = 0.80
c = 0.40
f
d = 0.15
e = 0.10
f = 0.45
g = 3.20 g
hc = 0.80
B = 2.40 1 2 3 4
A = 1.00
5 hc
br = 0.45
Ac= 5.00
B
Ancho= 6.00
hzolado= 0.30

Pantalla
A1 = Ancho*(f+g)
A1 = 3.47 m2

A2 = (Ancho*raiz(d^2+g^2))
A2 = 19.2211 m2

A3 = Ac*f+2c*f
A3 = 2.61 m2

Apant = 25.30 m2

Aletas
A = 5.06 m2
Aaletas = 2*A+0.3*0.5
Aaletas = 10.276 m2

Losa

L = 5.80 m
Ac = 5.00 m
f = 0.45 m
Ver = 0.50 m
eVer = 0.25 m
hParapeto = 0.60 m
eParapeto = 0.15 m

Base = (L-c)*Ac
Base = 27.00 m2

Laterales = 2*L*(e+2*ever+2*eparapeto)
Laterales = 14.5 m2

Caras = 4*(Ac*e+Ver*ever+hparapeto*eparapeto)
Caras = 9.215

A = 50.72 m2
PONTON L=5.00 m
Ø L (m) N° Piezas N° Veces Long Total Peso (Kg/m) Peso (Kg) Total
3/8" 0.85 12 2 20.4 0.58 11.83
3/8" 5.7 3 2 34.2 0.58 19.84 88.04
3/8" 2.7 18 2 97.2 0.58 56.38
1/2" 5.3 33 2 349.8 1.02 356.80
537.23
1/2" 6.1 29 1 176.9 1.02 180.44
3/4" 6.4 12 2 153.6 2.24 344.06 344.06
1" 6.1 23 1 140.3 4.04 566.81
609.23
1" 1.5 7 1 10.5 4.04 42.42
1578.57
Baranda
Tubo Ø L (m) N° Piezas N° Veces Long parcial Long Total (m)
2" 5.80 1.00 2.00 11.60
22.00
2" 0.65 8.00 2.00 10.40
08 RESUMEN PONTON L=5.00 M
08.01 MOVIMIENTO DE TIERRAS
08.01.01 Trazo Nivelacion y Replanteo

Área = ((Ancho+3.2*2)*(3.2))

Área = 39.68 m2

08.01.02 Excavación en Material Suelto

APant = Ancho*(a+b+c+d+e)
APant = 14.40

AAleta = 5.06 m2

V = Apant*4.50+Aaleta*3
V= 55.463 m3

08.01.03 Relleno con Material Propio


V = Ancho*a*3.65+2.44*a*2.50
V= 26.60 m3
08.02 CONCRETO SIMPLE
08.02.01 Concreto f'c=100 Kg/cm2 con Boloneria
V= 15.55 m3

08.02.02 Concreto f'c=140 Kg/cm2 + 30% P.G.


V= 41.47 m3

08.02.02 Concreto f'c=175 Kg/cm2 + 30% P.M.


V= 73.41 m3

08.03 CONCRETO ARMADO


08.03.01 Concreto f'c=210 Kg/cm2
V= 15.62 m3

08.04 ENCOFRADO
08.04.01 Encofrado y Desencofrado
Área = 50.72 m2

08.05 ACERO
08.05.01 Acero Ø 3/8" fy=4200 Kg/cm2
Peso = 88.04 Kg

08.05.01 Acero Ø 1/2" fy=4200 Kg/cm2


Peso = 537.23 Kg

08.05.01 Acero Ø 3/4" fy=4200 Kg/cm2


Peso = 344.06 Kg

08.05.01 Acero Ø 1" fy=4200 Kg/cm2


Peso = 609.23 Kg

08.06 VARIOS
08.06.06 Baranda Tuberia Ø = 2"
L= 22.00 ml

08.06.04 Neopreno de e= 7mm

total= 1.2 m2

Tecknoport e= 2''

total= 2.7 m2