Metrado Ponton L 5.00m
Metrado Ponton L 5.00m
00 m
a = 0.95
b = 0.80
c = 0.40 a b c d e
d = 0.15
e = 0.10 f
f = 0.45
g = 3.20
hc = 0.80 g
B = 2.40
A = 1.00 1 2 3 4
br = 0.45
Ac= 5.00 5 hc
Ancho= 6.00
hzolado= 0.30 B
Pantalla
A2 = bx(g+f) = 2.92
A3 = cxg = 1.28
A4 = d*g/2 = 0.24
A5 = B*hc = 1.92
A6 = (b+c)*(f+g) = 4.38
VZolado = B*hzolado
VZolado = 4.32
Aletas
Area Zapata = 5.76
VZolado = 1.73
Losa
L= 5.80 m
Ac = 5.00 m
f= 0.45 m
Ver = 0.50 m
eVer = 0.25 m
hParapeto = 0.60 m
eParapeto = 0.15 m
Vlosa = L*Ac*e
Vlosa = 13.05 m3
Vver = 2*L*(2*Ver+0.05)*ever/2
Vver = 1.52 m3
VParapeto = 2*L*hParapeto*eParapeto
VParapeto = 1.04 m3
V= 15.62 m3
Concreto
PONTON L=5.00 M
Pantalla Aletas Losa
Total (m3)
Cantidad V Parcial (m3) Cantidad V Parcial (m3) V Parcial (m3)
V Zolado 2 4.32 4 1.73 15.55
Vf'c=140 kg/cm2 2 11.52 4 4.61 41.47
Vf'c=175 kg/cm2 2 26.58 4 5.06 73.41
Vf'c=210 kg/cm2 15.62 15.62
Encofrado (L=5.00 m)
a = 0.95
a b c d e
b = 0.80
c = 0.40
f
d = 0.15
e = 0.10
f = 0.45
g = 3.20 g
hc = 0.80
B = 2.40 1 2 3 4
A = 1.00
5 hc
br = 0.45
Ac= 5.00
B
Ancho= 6.00
hzolado= 0.30
Pantalla
A1 = Ancho*(f+g)
A1 = 3.47 m2
A2 = (Ancho*raiz(d^2+g^2))
A2 = 19.2211 m2
A3 = Ac*f+2c*f
A3 = 2.61 m2
Apant = 25.30 m2
Aletas
A = 5.06 m2
Aaletas = 2*A+0.3*0.5
Aaletas = 10.276 m2
Losa
L = 5.80 m
Ac = 5.00 m
f = 0.45 m
Ver = 0.50 m
eVer = 0.25 m
hParapeto = 0.60 m
eParapeto = 0.15 m
Base = (L-c)*Ac
Base = 27.00 m2
Laterales = 2*L*(e+2*ever+2*eparapeto)
Laterales = 14.5 m2
Caras = 4*(Ac*e+Ver*ever+hparapeto*eparapeto)
Caras = 9.215
A = 50.72 m2
PONTON L=5.00 m
Ø L (m) N° Piezas N° Veces Long Total Peso (Kg/m) Peso (Kg) Total
3/8" 0.85 12 2 20.4 0.58 11.83
3/8" 5.7 3 2 34.2 0.58 19.84 88.04
3/8" 2.7 18 2 97.2 0.58 56.38
1/2" 5.3 33 2 349.8 1.02 356.80
537.23
1/2" 6.1 29 1 176.9 1.02 180.44
3/4" 6.4 12 2 153.6 2.24 344.06 344.06
1" 6.1 23 1 140.3 4.04 566.81
609.23
1" 1.5 7 1 10.5 4.04 42.42
1578.57
Baranda
Tubo Ø L (m) N° Piezas N° Veces Long parcial Long Total (m)
2" 5.80 1.00 2.00 11.60
22.00
2" 0.65 8.00 2.00 10.40
08 RESUMEN PONTON L=5.00 M
08.01 MOVIMIENTO DE TIERRAS
08.01.01 Trazo Nivelacion y Replanteo
Área = ((Ancho+3.2*2)*(3.2))
Área = 39.68 m2
APant = Ancho*(a+b+c+d+e)
APant = 14.40
AAleta = 5.06 m2
V = Apant*4.50+Aaleta*3
V= 55.463 m3
08.04 ENCOFRADO
08.04.01 Encofrado y Desencofrado
Área = 50.72 m2
08.05 ACERO
08.05.01 Acero Ø 3/8" fy=4200 Kg/cm2
Peso = 88.04 Kg
08.06 VARIOS
08.06.06 Baranda Tuberia Ø = 2"
L= 22.00 ml
total= 1.2 m2
Tecknoport e= 2''
total= 2.7 m2