AVANCE DE OBRA
PRESUPUESTO SALDO REAL
ANTERIOR ACTUAL REAL ACUMULADO REAL
Item Descripción Und
Metrado P. Unitario S/. Total S/. Metrado Valorizado S/. % Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. %
1.00 SECUNDARIA
1.01 TRABAJOS PRELIMINARES
FLETE PARA EL TRASLADO DE MADERA Y TRIPLAY glb 1.00 1,500.00 1,500.00 - - 0.00% 1.00 1,500.00 100.00% 1.00 1,500.000 100.00% - - 0.00%
1.02 AREAS DE CIRCULACION
1.02.01 CERCO PROVISIONAL DE TRYPLAY m 92.80 140.12 13,003.14 - - 0.00% 92.80 13,003.14 100.00% 92.80 13,003.136 100.00% - - 0.00%
1.02.02 DESBROCE DE VEGETACION m2 37.50 5.50 206.25 - - 0.00% 37.50 206.25 100.00% 37.50 206.250 100.00% - - 0.00%
DESMONTAJE Y MONTAJE DE CERCO PERIMETRICO DE MALLA
und 1.00 175.80 175.80 - - 0.00% 1.00 175.80 100.00% 1.00 175.800 100.00% - - 0.00%
1.02.03 OLIMPICA
1.02.04 TRABAJOS MANUALES EN TERRENO NATURAL PARA ESCALINA m2 36.00 47.52 1,710.72 - - 0.00% 36.00 1,710.72 100.00% 36.00 1,710.720 100.00% - - 0.00%
1.02.05 BARANDAS DE MADERA TEMPORALES Y REUBICACION m 5.00 49.64 248.20 - - 0.00% 5.00 248.20 100.00% 5.00 248.200 100.00% - - 0.00%
1.02.06 SEÑALIZACION TEMPORAL CON BASE DE PVC und 20.00 25 500.00 - - 0.00% 20.00 500.00 100.00% 20.00 500.000 100.00% - - 0.00%
1.03 TRABAJOS ADICIONALES POR ALTA TEMPERATURA
1.03.01 MODULO CONTIGENTE S-4
1.03.01.01 COLOCACION DE VENTILADOR EN PISO und 2.00 224.00 448.00 - - 0.00% 2.00 448.00 100.00% 2.00 448.000 100.00% - - 0.00%
1.03.02 MODULO CONTIGENTE S-1 - -
1.03.02.01 COLOCACION DE VENTILADOR EN PISO und 2.00 224.00 448.00 - 0.00% 2.00 448.00 100.00% 2.00 448.000 100.00% - 0.00%
COSTO DIRECTO 18,240.11 0.00 0.00% S/18,240.11 100.00% S/18,240.11 100.00% 0.00 0.00%
0.099231879 GASTOS GENERALES (15.00%) 0.09 S/ 1,810.00 S/ - 0.00% S/ 1,810.00 100.00% S/ 1,810.00 100.00% S/ - 0.00%
0.115000000 UTILIDAD (11.50%) 0.12 S/ 2,097.61 S/ - 0.00% S/ 2,097.61 100.00% S/ 2,097.61 100.00% S/ - 0.00%
SUBTOTAL S/ 22,147.72 S/ - 0.00% S/22,147.72 100.00% S/22,147.72 100.00% S/ - 0.00%
IGV(18%) 0.18 S/ 3,986.59 S/ - 0.00% 3,986.59 100.00% 3,986.59 100.00% S/ - 0.00%
PRESUPUESTO TOTAL S/ 26,134.31 0.00 0.00% S/26,134.31 100.00% S/26,134.31 100.00% 0.00 0.00%
MEDIDAS RESULTADOS
DESCRIPCION UND
N° CANT LARGO ANCHO ALTO PARCIAL TOTAL
1.00 SECUNDARIA
1.01 AREAS DE CIRCULACION
1.01.01 CERCO PROVISIONAL 92.80
ZONA 01 - COLINDA CON MOD. CONTINGENTE M 1.00 48.50 48.50
ZONA 02 - COLINDA CON PATIO M 1.00 49.30 49.30
ZONA
CERCO03PROVISIONAL
- COLINDA CON
ENBLOQUE COMEDOR M 1.00 23.00 23.00
PRIMARIA(DESCONTAR) M 1.00 -28.00 -28.00
N
RESUMEN DE PLANILLA DE METRADOS SEGÚN PARTIDAS EJECUTADAS
°
PRESUPUESTO BASE Total % de EJEC. EN
METRADO EJECUTADO
Metrado Metrado % Saldo de
FECHA Metrado saldo
ÍTEMS DESCRIPCIÓN PARTIDA UND Metrado Avance VEL MES Anterior Acumulado Avance
e
SECUNDARIA c
01 TRABAJOS PRELIMINARES e
s
01.02 FLETE PARA EL TRASLADO DE MADERA Y TRIPLAY glb 1.00 100.00% 1.00 0.00 1.00 0.00 0.00%
01.05.01 AREAS DE CIRCULACION
CERCO PROVISIONAL DE TRYPLAY m 92.8 100.00% 92.80 0.00 92.80 0.00 0.00%
DESBROCE DE VEGETACION m2 37.50 100.00% 37.50 0.00 37.50 0.00 0.00%
DESMONTAJE Y MONTAJE DE CERCO PERIMETRICO DE MALLA OLIMPICA und 1.00 100.00% 1.00 0.00 1.00 0.00 0.00%
TRABAJOS MANUALES EN TERRENO NATURAL PARA ESCALINATAS m2 36.00 100.00% 36.00 0.00 36.00 0.00 0.00%
TEMPORALES
04.01.02.01 BARANDAS DE MADERA TEMPORALES Y REUBICACION m 5.00 100.00% 5.00 0.00 5.00 0.00 0.00%
SEÑALIZACION TEMPORAL CON BASE DE PVC und 20 100.00% 20.00 0.00 20.00 0.00 0.00%
TRABAJOS ADICIONALES POR ALTA TEMPERATURA
MODULO CONTIGENTE S-4
COLOCACION DE VENTILADOR EN PISO und 2.00 100.00% 2.00 0.00 2.00 0.00 0.00%
MODULO CONTIGENTE S-1
COLOCACION DE VENTILADOR EN PISO und 2.00 100.00% 2.00
: INTERVENCION DE LA INFRAESTRUCTURA DEL PROYECTO MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E COSTO DIRECTO S/18,240.11
501138 JAVIER PEREZ DE CUELLAR KEPASHIATO – ECHARATI – LA CONVENCION - CUSCO
SERVICIO
PRESUPUESTO TOTAL S/26,134.31
RESIDENTE DE OBRA : ING. WILLIANS ALFREDO LIMACHI AVANCE FISICO ACTUAL S/26,134.31
SUPERVISOR : ING. JULIO CESAR CRUZ HEREDIA AVANCE FISICO ACUMULADO S/26,134.31
EJECUTOR : BANCO DE CREDITO DEL PERU - BCP
PRESUPUESTO PRESUPUESTO AVANCES
SALDOS
PART. DESCRIPCION EXPEDIENTE PROGRAMADO ANTERIOR ACTUAL ACUMULADO
S/. S/. VALORIZ. VALORIZ. VALORIZ. % VALORIZ. %
CURVA "S"
160.00%
143.83%
140.00% 135.16%
126.66%
120.00%
%AVANCE
112.46%
100.00%
100.00%
100.00% 91.04%
84.58%
80.00% 75.94%
65.83%
60.00% 55.67%
40.00%
30.57%
17.63%
20.00%
8.73%
0.00%
INTERVENCION DE LA INFRAESTRUCTURA DEL PROYECTO MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E 501138 JAVIER PEREZ DE
CUELLAR KEPASHIATO – ECHARATI – LA CONVENCION - CUSCO1
QUINCENA 1 (17- QUINCENA 2(1- QUINCENA 3 (16- QUINCENA 4(1- QUINCENA 5(16- QUINCENA 6 (1- QUINCENA 7(16- QUINCENA QUINCENA
30) 15) 31) 15) 30) 15) 31) 8(1-15) 9(16-31)
PARTIDAS Sep-09 Oct-10 Oct-10 Nov-11 Nov-11 Dec-12 Dec-12 Jan-01 Jan-01
S/63,188.73 S/64,414.12 S/93,669.72 S/181,730.06 S/73,520.66 S/73,186.50 S/62,560.29 S/46,772.60 S/64,850.81
01 OBRAS PRELIMINARES
01.01.01 FLETE/ TRASLADO DE MATERIALES CUSCO - KEPASHIATO S/ 31,500.00 S/ 3,500.00 S/ 3,500.00 3500 3500 3500 7000 3500 S/ 3,500.00
01.01.03 FLETE/ TRASLADO DE MATERIALES QUILLABAMBA - KEPASHIATO S/ 2,000.00 S/ 500.00 S/ 500.00 1000
01.02 ENERERGIA ELECTRICA PARA LA CONSTRUCCION S/ 2,000.00 S/ 500.00 500 500 S/ 500.00
01.03 SEGURIDAD Y SALUD
01.04 EQUIPOS DE PROTECCION INDIVIDUAL S/ 6,250.00 S/ 6,250.00
01.04.02 EQUIPOS DE PROTECCION COLECTIVA S/ 2,000.00 S/ 2,000.00
01.04.04 SEÑALIZACION TEMPORAL DE SEGURIDAD S/ 1,200.00 S/ 1,200.00
01.04.06 EXAMEN MEDICO S/ 1,200.00 S/ 1,200.00
01.05.01 INTERVENCION ESTRUCTURAL
INCREMENTO DE SECCION EN ZAPATAS Y NUEVA VIGA DE CONEXION
02.01.01 OBRAS PRELIMINARES S/ -
02.01.01.02RETIRO DE MURO TARRAJEADO S/ 2,101.44 S/ 1,786.23 S/ 315.22
02.01.01.04RETIRO DE COLUMNETA S/ 1,992.25 S/ 1,693.41 S/ 298.84
02.01.02.01RETIRO DE VIGUETA S/ 1,241.74 S/ 1,055.48 S/ 186.26
02.02.02 RETIRO DE CIMIENTO CORRIDO S/ 1,144.93 S/ 973.19 S/ 171.74
02.01.03 RETIRO DE SOBRECIMIENTO S/ 858.85 S/ 730.02 S/ 128.83
RETIRO DE CONTRAPISO Y PISO PULIDO S/ 3,339.08 S/ 2,838.22 S/ 500.86
02.01.05 ACOPIO DE RESTOS DE CONCRETO S/ 946.00 S/ 804.10 S/ 141.90
02.01.05.02DESMONTAJE Y MONTAJE DE VENTANA S/ 1,980.88 S/ 1,683.75 S/ 297.13
02.01.06.01DESMONTAJE Y MONTAJE DE PIZARRA S/ 376.95 S/ 320.41 S/ 56.54
02.01.06.01EXCAVACION DE MANUAL DE TERRENO COMPACTO S/ 8,870.69 S/ 7,540.08 S/ 1,330.60
02.01.07 APUNTALAMIENTO TEMPORAL S/ 775.20 S/ 658.92 S/ 116.28
02.01.07.02MOVIMIENTO DE TIERRAS
02.01.08.01RELLENO COMPACTADO CON MATERIAL DE PRESTAMO S/ 6,318.23 S/ 947.74 S/ 3,790.94 S/ 631.82 947.74
02.01.04 CONCRETO SIMPLE
02.01.04.02ZAPATAS Y V.C
02.01.04.05SOLADO DE CONCRETO E=0.05CM S/ 4,116.45 S/ 374.22 S/ 2,806.67 S/ 935.56
CIMIENTO CORRIDO
ENCOFRADO Y DESENCOFRADO S/ 5,800.18 S/ 527.29 S/ 1,977.34 S/ 1,318.22 1977.34
CONCRETO f'c=140 kg/cm2 S/ 4,313.66 S/ 392.15 S/ 1,470.57 S/ 980.38 1470.57
SOBRECIMIENTO
04.03.01 ENCOFRADO Y DESENCOFRADO S/ 654.16 S/ 59.47 S/ 223.01 S/ 148.67 223.01
CONCRETO f'c=175 kg/cm2 S/ 735.93 S/ 66.90 S/ 250.89 S/ 167.26 250.89
CONCRETO ARMADO
2.02 ZAPATAS Y V.C
02.02.01.01RETIRO DE RECUBRIMIENTO DE CONCRETO S/ 1,583.04 S/ 150.77 S/ 565.37 S/ 301.53 565.37
02.02.01.02ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 9,158.21 S/ 872.21 S/ 4,579.10 S/ 1,744.42 1962.47
ADITIVO HIT RE - 500 V3 PARA ANCLAJES S/ 14,445.24 S/ 1,375.74 S/ 7,222.62 S/ 2,751.47 3095.41
ENCOFRADO Y DESENCOFRADO S/ 2,835.89 S/ 270.08 S/ 1,417.94 S/ 540.17 607.69
CONCRETO f'c=210 kg/cm2 S/ 6,671.68 S/ 635.40 S/ 3,335.84 S/ 1,270.80 1429.65
PUENTE ADHERENTE PARA CONCRETO S/ 1,823.60 S/ 173.68 S/ 911.80 S/ 347.35 390.77
COLUMNETAS
ENCOFRADO Y DESENCOFRADO S/ 10,152.14 S/ 966.87 S/ 7,251.53 S/ 966.87 966.87
CONCRETO f'c=175 kg/cm2 S/ 8,050.48 S/ 766.71 S/ 5,750.34 S/ 766.71 766.71
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 5,321.76 S/ 506.83 S/ 3,801.26 S/ 506.83 506.83
REPOSICION DE DADO DE CONCRETO EN MONTANTES DE AGUAS PLUVIALES S/ 720.00 S/ 68.57 S/ 514.29 S/ 68.57 68.57
2.02 VIGUETAS
02.02.01.01ENCOFRADO Y DESENCOFRADO S/ 2,069.68 S/ 197.11 S/ 739.17 S/ 394.22 739.17
02.02.01.03CONCRETO f'c=175 kg/cm2 S/ 1,103.90 S/ 105.13 S/ 394.25 S/ 210.27 394.25
02.02.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 3,357.04 S/ 319.72 S/ 1,198.94 S/ 639.44 1198.94
02.01.02.02ARQUITECTURA Y ACABADOS
FALSO PISO Y CONTRAPISO PULIDO EN EXTERIORES AULA S/ 5,911.77 S/ 4,138.24S/ 886.77 S/ 886.77
02.02.06 FALSO PISO Y CONTRAPISO EN AULAS S/ 4,220.32 S/ 2,954.23S/ 633.05 S/ 633.05
02.01.06.01ENCHAPE DE CERAMICO EN ZONAS INTERVENIDAS S/ 3,538.67 S/ 2,477.07S/ 530.80 S/ 530.80
02.02.06 CONTRAZOCALO DE CERAMICO EN ZONAS INTERVENIDAS S/ 835.92 S/ 585.15S/ 125.39 S/ 125.39
MURO DE LADRILLO K.K.MACIZO 9x13x24 cm. S/ 12,176.34 S/ 7,305.80S/ 2,435.27 S/ 2,435.27
TARRAJEO DE MUROS INTERIORES/EXTERIORES S/ 16,793.80 S/ 10,076.28S/ 3,358.76 S/ 3,358.76
JUNTA DE TECNOPORT INCL SIKAFLEX S/ 2,501.41 S/ 1,500.85 S/ 500.28 S/ 500.28
BRUÑAS S/ 1,662.88 S/ 997.73 S/ 332.58 S/ 332.58
04.01.01 INSTALACIONES ELECTRICAS
04.01.01.02REPOSICION DE TOMACORRIENTES,INTERRUPTORES Y OTROS S/ 300.60 S/ 150.30 S/ 150.30
04.01.01.04REPOSICION DE TALEROS DE DISTRIBUCION S/ 521.58 S/ 260.79 S/ 260.79
04.01.02.01INTERVENCION EN VIGAS PERALTADAS
OBRAS PRELIMINARES
RETIRO DE MURO TARRAJEADO S/ 6,425.00 S/ 3,212.50 S/ 2,570.00 S/ 642.50
RETIRO DE COLUMNETA S/ 3,384.45 S/ 1,692.23 S/ 1,353.78 S/ 338.45
RETIRO DE VIGUETA S/ 1,896.77 S/ 948.38 S/ 758.71 S/ 189.68
ACOPIO DE RESTOS DE CONCRETO S/ 1,118.00 S/ 559.00 S/ 447.20 S/ 111.80
RETIRO DE SOBRECIMIENTO S/ 423.33 S/ 211.66 S/ 169.33 S/ 42.33
DESMONTAJE Y MONTAJE DE VENTANA S/ 2,160.96 S/ 1,080.48 S/ 864.38 S/ 216.10
04.05.01 DESMONTAJE Y MONTAJE DE PIZARRA S/ 829.29 S/ 414.65 S/ 331.72 S/ 82.93
APUNTALAMIENTO TEMPORAL S/ 2,390.20 S/ 1,195.10 S/ 956.08 S/ 239.02
DESMONTAJE Y MONTAJE DE PUERTA S/ 659.70 S/ 527.76 S/ 131.94
CONCRETO SIMPLE
SOBRECIMIENTO
04.04.01 ENCOFRADO Y DESENCOFRADO S/ 857.67 S/ 686.14 S/ 171.53
04.04.04 CONCRETO f'c=175 kg/cm2 S/ 303.32 S/ 242.66 S/ 60.66
04.05.01 CONCRETO ARMADO
INTERVENCION EN VIGAS PERALTADAS
RETIRO DE RECUBRIMIENTO DE CONCRETO EN VIGAS S/ 953.12 S/ 285.94 S/ 524.22 S/ 142.97
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 3,811.69 S/ 1,143.51 S/ 2,096.43 S/ 571.75
04.02.01.06ENCOFRADO Y DESENCOFRADO S/ 1,162.94 S/ 348.88 S/ 639.62 S/ 174.44
4 ADITIVO HIT RE - 500 V3 PARA ANCLAJES S/ 1,846.88 S/ 554.06 S/ 1,015.78 S/ 277.03
04.01 CONCRETO f'c=210 kg/cm2 S/ 9,048.95 S/ 2,714.68 S/ 4,976.92 S/ 1,357.34
04.01.01.01UNION DE ACERO EN FORMA DE U EN REFURZO INFERIOR DE VIGAS PERALTADAS S/ 7,648.00 S/ 2,294.40 S/ 4,206.40 S/ 1,147.20
04.01.01.04COLUMNETAS
04.01.02.01PUENTE ADHERENTE PARA CONCRETO S/ 1,720.57 S/ 602.20 S/ 946.31 S/ 172.06
04.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 10,984.04 S/ 3,295.21 S/ 6,590.43 S/ 1,098.40
04.04.02 CONCRETO f'c=175 kg/cm2 S/ 3,361.41 S/ 1,008.42 S/ 2,016.85 S/ 336.14
04.05 ENCOFRADO Y DESENCOFRADO S/ 6,494.92 S/ 1,948.48 S/ 3,896.95 S/ 649.49
04.05.02 VIGUETAS
ENCOFRADO Y DESENCOFRADO S/ 3,863.76 S/ 1,159.13 S/ 2,318.26 S/ 386.38
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 6,394.57 S/ 1,918.37 S/ 3,836.74 S/ 639.46
CONCRETO f'c=175 kg/cm2 S/ 2,063.59 S/ 619.08 S/ 1,238.15 S/ 206.36
ARQUITECTURA Y ACABADOS
REPOSICION DE DADO DE CONCRETO EN MONTANTES DE AGUAS PLUVIALES S/ 1,800.00 S/ 1,080.00 S/ 540.00 S/ 180.00
ENCHAPE DE CERAMICO EN ZONAS INTERVENIDAS S/ 7,485.03 S/ 5,988.02 S/ 748.50 S/ 748.50
04.03.01 MURO DE LADRILLO K.K.MACIZO 9x13x24 cm. S/ 31,475.60 S/ 18,885.36 S/ 9,442.68 S/ 3,147.56
JUNTA DE TECNOPORT INCL SIKAFLEX S/ 2,726.70 S/ 2,181.36 S/ 545.34
CONTRAZOCALO DE CERAMICO EN ZONAS INTERVENIDAS S/ 2,023.25 S/ 606.98 S/ 1,213.95 S/ 202.33
04.01.01.01TARRAJEO DE MUROS INTERIORES/EXTERIORES S/ 33,155.10 S/ 19,893.06 S/ 9,946.53 S/ 1,657.76 S/ 1,657.76
04.01.01.03BRUÑAS S/ 2,416.80 S/ 725.04 S/ 1,450.08 S/ 241.68
04.01.02 INSTALACIONES ELECTRICAS
04.01.02.02REPOSICION DE TALEROS DE DISTRIBUCION S/ 695.44 S/ 556.35 S/ 139.09
04.05.01 REPOSICION DE TOMACORRIENTES,INTERRUPTORES Y OTROS S/ 1,002.00 S/ 801.60 S/ 200.40
04.02 INTERVENCION EN ALBAÑILERIA
04.02.01.06REMPLAZO DE MUROS FISURADOS
OBRAS PRELIMINARES
RETIRO DE MURO TARRAJEADO S/ 14,440.61 S/ 5,776.25 S/ 2,888.12 S/ 5,776.25
RETIRO DE COLUMNETA S/ 2,136.95 S/ 854.78 S/ 427.39 S/ 854.78
RETIRO DE VIGUETA S/ 4,828.68 S/ 1,931.47 S/ 965.74 S/ 1,931.47
04.04 DESMONTAJE Y MONTAJE DE PIZARRA S/ 678.51 S/ 407.11 S/ 271.40
04.04.04 ACOPIO DE RESTOS DE CONCRETO S/ 1,204.00 S/ 481.60 S/ 240.80 S/ 481.60
04.03.01 DESMONTAJE Y MONTAJE DE VENTANA S/ 1,800.80 S/ 1,080.48 S/ 720.32
CONCRETO ARMADO
COLUMNETAS
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 16,392.64 S/ 3,278.53 S/ 6,557.06 S/ 3,278.53 S/ 3,278.53
CONCRETO f'c=175 kg/cm2 S/ 4,489.17 S/ 897.83 S/ 1,795.67 S/ 897.83 S/ 897.83
ENCOFRADO Y DESENCOFRADO S/ 9,981.94 S/ 1,996.39 S/ 3,992.77 S/ 1,996.39 S/ 1,996.39
VIGUETAS
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/ 13,240.85 S/ 2,648.17 S/ 5,296.34 S/ 2,648.17 S/ 2,648.17
CONCRETO f'c=175 kg/cm2 S/ 3,559.51 S/ 711.90 S/ 1,423.81 S/ 711.90 S/ 711.90
04.02.01 ENCOFRADO Y DESENCOFRADO S/ 7,122.43 S/ 1,424.49 S/ 2,848.97 S/ 1,424.49 S/ 1,424.49
ARQUITECTURA Y ACABADOS
04.02.01.06MURO DE LADRILLO K.K.MACIZO 9x13x24 cm. S/ 83,672.93 S/ 16,734.59 S/ 33,469.17 S/ 16,734.59 S/ 16,734.59
6 TARRAJEO DE MUROS INTERIORES/EXTERIORES S/ 84,697.39 S/ 33,878.96 S/ 16,939.48 S/ 16,939.48 S/ 8,469.74 S/ 8,469.74
04.01.02 CONTRAZOCALO DE CERAMICO EN ZONAS INTERVENIDAS S/ 521.15 S/ 104.23 S/ 208.46 S/ 208.46
04.01.02.02BRUÑAS S/ 516.80 S/ 206.72 S/ 103.36 S/ 103.36 S/ 103.36
04.04.01 JUNTA DE TECNOPORT INCL SIKAFLEX S/ 4,030.15 S/ 2,418.09 S/ 1,612.06
04.01 INSTALACIONES ELECTRICAS
04.01.01.01REPOSICION DE TALEROS DE DISTRIBUCION S/ 608.51 S/ 365.11 S/ 243.40
04.01.01.03REPOSICION DE TOMACORRIENTES,INTERRUPTORES Y OTROS S/ 1,127.25 S/ 676.35 S/ 450.90
04.04.04 ENSAYOS DE CONTROL/CALIDAD
04.05.01 ROPTURA DE TESTIGOS DE CONCRETO S/ 2,700.00 S/ 2,700.00
04.02 ENSAYOS DE DENSIDAD DE CAMPO S/ 1,200.00 S/ 960.00 S/ 240.00
04.02.01.06TRABAJOS FINALES
RETIRO MANUAL DE PINTURA ANTERIOR S/ 825.00 S/ 495.00 S/ 330.00
PINTURA EN ZONAS EXTERIORES S/ 51,649.00 S/ 10,329.80 S/ 15,494.70 S/ 25,824.50
7 PINTURA EN ZONAS INTERIORES S/ 38,817.80 S/ 7,763.56 S/ 11,645.34 S/ 19,408.90
ELIMINACION DE MATERIAL DE DEMOLICIONES S/ 2,095.80 S/ 1,047.90 S/ 1,047.90
LIMPIEZA FINAL DE OBRA S/ 1,500.00 S/ 750.00 S/ 750.00
COSTO DIRECTO 723,893.48 63,188.73 64,414.12 93,669.72 181,730.06 73,520.66 73,186.50 62,560.29 46,772.60 64,850.81
#REF! GASTOS GENERALES (15.00%) S/ 91,653.13 S/ 8,000.41 S/ 8,155.56 S/ 11,859.65 S/ 23,009.09 S/ 9,308.55 S/ 9,266.24 S/ 7,920.84 S/ 5,921.94 S/ 8,210.85
#REF! UTILIDAD (11.50%) S/ 83,247.75 S/ 7,266.70 S/ 7,407.62 S/ 10,772.02 S/ 20,898.96 S/ 8,454.88 S/ 8,416.45 S/ 7,194.43 S/ 5,378.85 S/ 7,457.84
COVID BCP S/ 20,178.33 S/ 1,761.37 S/ 1,795.53 S/ 2,611.02 S/ 5,065.68 S/ 2,049.37 S/ 2,040.05 S/ 1,743.85 S/ 1,303.77 S/ 1,807.70
#REF! SUBTOTAL S/ 918,972.70 S/ 80,217.21 S/ 81,772.83 S/ 118,912.41 S/ 230,703.77 S/ 93,333.45 S/ 92,909.25 S/ 79,419.42 S/ 59,377.17 S/ 82,327.20
IGV(18%) S/ 165,415.09 S/ 14,439.10 S/ 14,719.11 S/ 21,404.23 S/ 41,526.68 S/ 16,800.02 S/ 16,723.66 S/ 14,295.49 S/ 10,687.89 S/ 14,818.90
PRESUPUESTO TOTAL 1,084,387.79 94,656.31 96,491.94 140,316.64 272,230.45 110,133.47 109,632.91 93,714.91 70,065.06 97,146.09
% QUINCENAL 8.73% 8.90% 12.94% 25.10% 10.16% 10.11% 8.64% 6.46% 8.96%
%MENSUAL 8.73% 21.84% 35.26% 18.75% 15.42%
VALORIZACIÓN FISICA DE AVANCE DE OBRA FINAL N°-3 PRIMARIA
INTERVENCION DE LA INFRAESTRUCTURA DEL PROYECTO
MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS EDUCATIVOS EN LA
I.E 501138 JAVIER PEREZ DE CUELLAR KEPASHIATO – ECHARATI – LA
CONVENCION - CUSCO
Apr-23
MONTO A FACTURAR VALORIZACIÓN POR
VALORIZACION
DESCRIPCION
(S/.)
ADELANTOS 0.00
0.00
Son:
VEINTISEIS MIL CIENTO TREINTA Y CUATRO CON 31/100 SOLES
12
PANEL FOTOGRÁFICO
CHARLAS
VISTA DONDE
DE SEGURIDAD
SE MUESTRA
PREVIO
REALIZANDO
A LA JORNADA
LOS TRABAJOS
LABORAL
DE TRAZO PARA LAS ESCALINATAS TEMPORALES
VISTA DONDE SE MUESTRA REALIZANDO LOS TRABAJOS DE TRAZO PARA LA INSTALACION DE CERCO PERIMETRICO PROVICIONAL
DE TRIPLAY
PANEL FOTOGRÁFICO
VISTA DONDE SE MUESTRA REALIZANDO LOS TRABAJOS LIMPIEZA DE MALEZA EN LA ZONA DE TRABAJO
VISTA DONDE SE MUESTRA REALIZANDO LOS TRABAJOS DE INSTALACION DE CERCO PRIMETRICO PROVICIONAL
VISTA DONDE SE MUESTRA REALIZANDO LOS TRABAJOS DE EXCAVACION MANUAL PARA LAS ESCALINATAS
PANEL FOTOGRÁFICO
VISTA DONDE SE MUESTRA DONDE SE REALIZARA LOS TRABAJOS DE DESMONTAJE DE PUERTA MALLA OLIMPICA
VISTA DONDE SE MUESTRA REALIZANDO LOS TRABAJOS DE INSTALACION DE CERCO PERIMETRICO PROVICIONAL