Cómputos métricos

 Losa
Acero de repartición longitudinal
L=19.86 M Lacero =19.86 M +0.10( 19.86) = 21.25 m
2 Ø ⅝ c/d 18 cm
Ltransv= 21.46
Cantidad Along 21.46/0.18 = 12x2 = 2.40 elementos
240x21.85 = 5244 Ø ⅝’’
Cantidad de cabillas = 437 Ø ⅝´´ ,12.0 m

Acero transversal
(Volado):
Lav 1.35 + 0.10 (1.35) = 1.485 ml x2 volados = 2.97ml
Llong = 19.86 m
2 Ø⅝´´ c/d 17 cm
Entonces cantidad Atransv= 117+1x2 Ø= 234 elementos
Cantidad total = 2.97 ml x 243 Ø = 695 ml
N de cabillas = 58 Ø ⅝´, 12 m

Tramos
LATRANS = 270+0.10 ( 2.70) = 2.47 M X 7 tramos = 20.79 ml
2 ø⅝´´ c/d 13 cm
20,79 x2 ø = 41.58 ml
19.86 / 0.13 = 152.77 ~ 153 espacios +1 = 154 elementos
Cant. Acero 154 x 41.58 ml = 6362 m
N cabillas = 530 ø ⅝´´ , 12 m
Apoyos intermedios
LA AI = 2.97 m x 6 apoyos = 17.82 ml x 2 ø = 35.64 ml
2 ø⅝´ c/d 12
Entonces 19.86 / 0.12 = 165.50 ø 1.66 espacios +1 = 167 elementos
Cant de acero 165,50 x 35.64 = 5848 ml
N ø 5/8 ´´ = 492 ø 5/8 , 12 M

 Vigas
Vigas : acero longitudinal
LViga= 20,0 m
Lacero = 19.86 m + 0.10 ( 19.86) = 21.85 ml
10 Ø ½,, 21 .85 ML * 10 = 219 ml * 8 vigas = 1752 ML 146 Ø ½,, , 12m
5 Ø 7/8 ,, 21 .85 ML * 5 = 109 .25 ml * 8 vigas = 874 ML 73Ø 7/8 , 12m
12 Ø 1½,, 21 .85 ML * 12 = 262.20 ml * 8 vigas = 20.98 ML 175 Ø ½,, , 12m
8 Ø 1/4 ,, 21 .85 ML * 8= 174 .8 ml * 8 vigas = 139.4 ML 117 Ø 1/4 ,, , 12m

 Acero transversal
1 Ø 3/8 2.94 ml x 1= 2.94 x 8 vigas = 23.52 ml 2 Ø 3/8 ,12

 Aceras
Laceras = 2.00 m
L acero acera = 19.86
Acero long = 19.86 + 0.10 ( 19.86) = 21.85 ml
Cant Ø = 2.00 / 0.18 = 11.11 Ø +1 = 12 elementos
Cantidad acero = 21.85 x 11.11 = 243 ml x 2 Acera = 486 ml
486x 2 Ø = 172 ml / 12ml 81 Ø 5/8 ´´ , 12 m
Defensas
LA defensas = 19.86 M
L defensas = 0.40 m
19.86 + 0.10 (19.86) = 21.8ml
Cant Ø = 0.40 / 0.60 = 0.67 Ø ~ 1 elemento

 ENCOFRADO DE ESTRIBO

2.45∗0.2
A1= =¿0.245 m2
2
A2= (2.45+1.20+155)*0.90 = 4.68 m2
A3 = 1.20*0.20= 0.28 m
1.55∗0.2
A4= =¿ 0.155 m
2

A5= 1.2 *5.34 = 6.408 m


0.4∗1.6
A6= =¿ 0.32
2
0.4∗1.7
A7= 2
= 0.34

A8= 0.4*0.50 = 0.2


A9= 0.3 *1.35= 0.405
∑=13.033 m2

ATOTAL1=13.033 m2 *2caras = 26.066 m2


ATOTAL2=0.9 + 22.8 *2caras = 41.08 m2
ATOTAL3=4.45 * 22.8 *2caras = 101.046 m2
ATOTAL4=8.75 + 22.8 *= 199.6 m2
ATOTAL5=1.35 * 22.8 = 30.78 m2
∑encofrado total =398.986 m2
398.986 m2 * 2 estribos = 797.972

 CONCRETO DE ESTRIBO

A1= 5.2*0.9*22.8= 106,704 m3


A2= 0.245*22.8= 5.586 m3
A3= 0.28 m 22.8= 6.384 m3
A4= 0.155 m 22.8= 3.534 m3
A5= 6.408m 22.8= 146,102 m3
A6= 0.32 m 22.8= 7.296 m3
A7= 0.34m 22.8= 7.752 m3
A8= 0.2m 22.8= 4.56 m3
A9= 0.405m 22.8= 9.234 m3

∑concreto total =297.152 m3