Escolar Documentos
Profissional Documentos
Cultura Documentos
RESUMO
ABSTRACT
Considering the requirements of NR-18 regulatory standard, the following research was
to verify the adequacy and implementation of the Program Conditions and Working
Environment - PCMAT on small, medium and large civil construction works. Two
checklists were developed, one concerning the preparation of PCMAT and another of
the same implantation. After that, there was the application of these in 30 construction
sites in the city of Chapecó-SC as a way to assess the current situation in the city is to
this question of NR-18. The results show that only sixteen of the thirty construction
sites surveyed had to PCMAT, 53% of the total sample. Both in the preparation and in
the implementation of PCMAT, are the largest non-conformities related to the execution
of projects of collective protection (42% compliance in the preparation and 35% in
implementation) and the implementation schedule of preventive measures (48% in the
preparation and 26% in the implementation of PCMAT). Deficiencies are mainly
identified in the preparation of the basic document, causing not have a correct and
detailed parameter to deploy all necessary security measures. Still, it was found that, for
sixteen construction site that had PCMAT, the average achievement of the checklist
items was 69% in the preparation of the document and 58% in the implementation of
the same.
1. INTRODUÇÃO
Boa parte das exigências da NR-18 não são cumpridas, entre outros aspectos, devido à
falta de planejamento das atividades, bem como ausência da conscientização de sua
importância, já que algumas possuem baixo custo e tem facilidade em serem executadas
na própria obra (MENEZES; SERRA, 2003).
Segundo Martins e Serra (2003), no Brasil, nos canteiros de obra são adotadas
instalações
físicas mínimas de segurança, não sendo estabelecidas metas de redução de acidentes,
diferentemente de países desenvolvidos, onde adota-se uma política de segurança
voltada para a valorização dos recursos humanos. Ainda, cita-se que a alteração deste
quadro depende das ações tomadas pela direção em relação à valorização dos recursos
humanos como peças primordiais no processo de implantação do PCMAT.
Segundo Saurin (2002, cap.1, p. 2) “apesar de constituir a exigência central da norma, o
PCMAT apresenta deficiências na sua concepção, além de muitas vezes ser implantado
precariamente”. O autor define os principais problemas na implantação do programa,
sendo destacados os seguintes:
A implantação é normalmente tida como uma atividade extra para os gerentes,
não sendo integrado às atividades rotineiras de gestão da produção;
A elaboração do PCMAT normalmente se dá por profissionais externos à
empresa, com pouco ou nenhum envolvimento de gerentes de produção,
subempreiteiros e trabalhadores;
Não são realizadas atualizações no PCMAT no decorrer da obra, não levando em
conta a incerteza inerente aos empreendimentos de construção;
O PCMAT dá ênfase às proteções físicas contra acidentes, normalmente
negligenciando as ações gerenciais necessárias para obtenção de um ambiente de
trabalho seguro, como por exemplo a implementação de indicadores de
desempenho pró-ativo;
O PCMAT não exige a adoção de medidas preventivas, que eliminem os riscos
em sua origem, sendo esta uma abordagem prioritária para a prevenção de
acidentes.
Ainda, de acordo com Martins e Serra (2003), observa-se que o baixo índice de
aplicação das normas de segurança deve-se às características do setor da construção no
Brasil. Faz-se grande uso de mão-de-obra não qualificada, sem treinamento e com
promoções escassas. Além disso, a indefinição das estratégias de administração e
planejamento dos empreendimentos, a falta de conhecimento das exigências da Norma,
somadas ao custo que se tem e à questão cultural.
3. PROCEDIMENTOS METODOLÓGICOS
O presente estudo se subdividiu em duas etapas: primeiramente, foi feita uma análise
dos itens contidos no PCMAT, exigidos pela NR-18, de forma a avaliar a eficiência do
documento. Em seguida, foi feita a visita no canteiro de obras e, com base no conteúdo
do PCMAT, fez-se a verificação da aplicação na obra de todos os sistemas descritos.
Para coleta de dados, utilizou-se o método de investigação direta, onde por meio de
visitas foram obtidas informações das reais condições do meio ambiente de trabalho,
juntamente com aplicação de um check list da elaboração do PCMAT e um check list de
implantação do mesmo na obra.
O check list foi dividido em sete partes, sendo que contemplavam tanto a elaboração
quanto a implantação do PCMAT, as quais são:
Memorial sobre condições e meio ambiente de trabalho nas atividades e
operações;
Projeto de execução das proteções coletivas;
Especificação técnica das proteções coletivas e individuais a serem utilizadas;
Cronograma de implantação das medidas preventivas;
Layout inicial e atualizado do canteiro de obras;
Programa educativo;
Procedimentos úteis.
Foram visitados 30 canteiros de obra em Chapecó – SC, espalhados em diferentes
regiões, com objetivo de aproximar os resultados obtidos à real situação do local. Os
canteiros de obra dividiram-se em três tipologias: pequeno, médio e grande porte, sendo
10 canteiros para cada uma destas. As obras de pequeno porte abrangem as residências
unifamiliares de até dois pavimentos (máximo de 250 m²); as obras de médio porte
compreendem edifícios de dois a quatro pavimentos, com área entre 250 m² e 2.000 m².
Por fim, as obras de grande porte consistem em edificações de quatro a dezesseis
pavimentos, com área superior a 2.000 m².
Os dados foram coletados através de uma cópia física dos check list do PCMAT e de
Implantação. Primeiramente, como forma de testar a formulação das perguntas, o check
list piloto foi aplicado em dois canteiros de obra, sendo uma edificação residencial de
médio porte e a outra de grande porte. Após isso, percebeu-se que algumas questões
relativas às proteções coletivas geraram dúvidas, sendo assim necessário a alteração
destas para que ficassem mais claras, sem perder o foco principal. Com as modificações
feitas, chegou-se ao check list definitivo, aplicado nos 30 canteiros de obras visitados.
71% 70%
70% 67% 67% 67%
64% 63%
60% 56% 59%
56%
50% 50%
50%
40%
30% 27%
21%
20% 15%
10%
0%
A B C D E F G H I J K L M N O P
PCMAT
Obras
Implantação
Fonte: Elaboração do autor.
O projeto de execução das proteções coletivas deve estar anexado ao PCMAT, sempre
em conformidade com as etapas de execução da obra. A seguir, o gráfico da figura 03
apresenta as porcentagens de cumprimento deste item para cada uma das obras que
continham PCMAT.
Figura 03 – Porcentagem de aprovação do projeto de execução das proteções coletivas.
90%
Porcentagem de Aprovação
80%
70%
60%
50%
40%
33% 33% 33% 33% 33% 33% 33% 33% 33% 33% 33% 33% 33% 33%
30%
20%
10%
0% 0% 0%
0%
A B C D E F G H I J K L M N O P
Obras PCMAT
Implantação
Fonte: Elaboração do autor.
O projeto de execução das proteções coletivas foi o item que apresentou menor
cumprimento das exigências feitas pelo check list de elaboração do PCMAT, baseadas
na NR-18, com um percentual médio de cumprimento de 42%. Entre os dezesseis
canteiros de obras, apenas dois apresentaram 100% de aprovação para este item
(canteiros N e O). Os demais cumpriam somente o que se referia à descrição das
proteções coletivas mínimas a serem executadas nos canteiros.
Foi possível verificar que quatorze entre os dezesseis PCMAT’s pesquisados dispunham
apenas de representações gráficas muito vagas referentes ao projeto de proteções
coletivas, atingindo apenas 33% de cumprimento. Não se tinha uma adaptação do
projeto ao canteiro em si, impossibilitando a sua execução em conformidade com o
cronograma da obra. Ainda, estes mesmos não apresentaram memorial de cálculo para
as proteções coletivas.
Já na implantação do projeto, pode-se observar que os dois canteiros de obras que
possuíam o projeto de execução das proteções coletivas (N e O) os implantavam
integralmente, indicando 100% de cumprimento dos requisitos. Os canteiros de obras C,
E e L não possuíam o projeto, sendo que foram inteiramente reprovados por não
implantarem as proteções coletivas mínimas que descreviam em seu PCMAT. A maior
falha observada na implantação do projeto de execução das proteções coletivas é a
própria ausência do projeto em anexo ao PCMAT. Desta forma, não se tem um
parâmetro para avaliar se as proteções estão sendo executadas em conformidade com o
andamento da obra, bem como se satisfazem há um dimensionamento feito por
responsável técnico habilitado.
Figura 04 – Porcentagem de aprovação das especificações técnicas das proteções coletivas e individuais.
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
100%
90%
Porcentagem de Aprovação
100%
90%
80%
80% 80% 80%
Porcentagem de Aprovação
70%
60% 60% 60% 60% 60% 60% 60% 60%
60%
50%
40% 40% 40% 40% 40% 40%
40%
30%
20% 20% 20% 20% 20%
20%
10%
0% 0% 0% 0%
0%
A B C D E F G H I J K L M N O P
Obras PCMAT
Implantação
Fonte: Elaboração do autor.
A elaboração do cronograma de implantação das medidas preventivas obteve um
cumprimento de 48% do total do check list, ficando entre os itens do PCMAT com
menos da metade dos requisitos aprovados. De acordo com o gráfico da figura 05,
nenhum dos dezesseis PCMAT’s pesquisados apresentou 100% de conformidade para o
cronograma de implantação; Quatro PCMAT’s (I, J, K e L) não o dispunham em anexo,
representando assim 25% no total. Apenas três cronogramas atingiram 80% de
cumprimento (A, C e E, sendo 18,75%); os outros nove obtiveram de 40% a 60% de
conformidade com o check list (56,25%).
Dentre os pontos falhos, verificou-se que nenhum dos cronogramas previa a elaboração,
implementação e atualização de programas como o PPRA e PCMSO. Ainda, grande
parte não dispunham de previsão para reavaliação global do PCMAT. Quanto aos
treinamentos de segurança a serem dados aos funcionários quando se iniciam novas
etapas da obra, apenas três dos doze cronogramas encontrados os contemplavam.
Se tratando da implantação, o cronograma obteve a menor porcentagem de todos os
itens do check list, com aprovação média total de 26%. Apenas os canteiros de obras H
e M implantaram todos os procedimentos que descreveram no cronograma, mantendo
aprovação de 60% tanto para o PCMAT quanto para implantação deste.
Os canteiros de obras I, J, K e L não possuíam cronograma, portanto não há como
avaliar a implantação, fazendo com que fossem inteiramente reprovados. Os itens com
maior número de falhas correspondem à falta de acompanhamento do cronograma das
medidas preventivas em conformidade com o cronograma físico-executivo da obra. Dos
doze canteiros que dispunham de cronograma em seu PCMAT, apenas dois deles os
mantinham ao lado do cronograma da obra, sendo visivelmente utilizados. Os demais,
dispunham apenas de uma cópia anexada ao PCMAT, porém não havia nenhum indício
de que o seguiam.
90%
83%
80%
Porcentagem de Aprovação
75%
70%
60%
60%
50%
40%
30% 25% 25%
20%
10%
0% 0% 0% 0% 0% 0%
0% 0% 0%
A B C D E F G H I J K L M N O P
PCMAT
Obras Implantação
Programa educativo
100% 100% 100% 100% 100% 100% 100%
100%
90%
90%
80% 80% 80% 80% 80%
Porcentagem de Aprovação
80%
70% 70% 70%
70%
60%
50%
40% 40% 40% 40%
40%
30%
30%
20%
10%
0%
A B C D E F G H I J K L M N O P
PCMAT
Obras
Implantação
Procedimentos úteis
100% 100% 100% 100%100% 100%100%100% 100% 100% 100% 100% 100% 100% 100%
90%
Porcentagem de Aprovação
80%
70%
60%
50% 50% 50% 50%
50%
40%
30%
20%
10%
0%
A B C D E F G H I J K L M N O P
Obras PCMAT
Implantação
Observando os dados gerais, a média obtida na elaboração dos procedimentos úteis foi
de 94% para os dezesseis PCMAT’s pesquisados. De acordo com o gráfico da figura 08,
pode-se perceber que quatorze destes estavam com 100% de conformidade neste item,
representando assim 87,5% do total. Os outros dois PCMAT’s apresentaram 50% de
cumprimento dos itens, isto porque não dispunham dos procedimentos de emergência a
serem tomados em caso de acidentes pequenos, com gravidade média, alta e acidentes
com óbito. Desta forma, pode-se dizer então que, no geral, os procedimentos úteis
encontram-se em conformidade com os itens exigidos pelo check list do PCMAT.
Após fazer uma análise geral dos dados, obteve-se um percentual médio de aprovação
de 88% para a implantação dos procedimentos úteis descritos no PCMAT de cada uma
das obras; sendo assim, se destaca como o item com maior cumprimento dentre os sete
itens do check list de Implantação. Ainda nesse contexto, doze dos canteiros de obras
apresentavam cumprimento de 100% para o item em questão.
Quanto aos pontos falhos, apenas dois dos dezesseis canteiros de obras (J e P)
diminuíram a porcentagem de aprovação da concepção do PCMAT para a Implantação.
Isso se deve ao fato da falta de adaptação da sinalização de segurança do canteiro de
obras, de acordo com o que foi descrito no PCMAT, fazendo com que o percentual de
cumprimento caísse para 50%.
Nos outros quatorze canteiros de obras, todos os procedimentos de emergência e
sinalização do canteiro foram cumpridos conforme citado no PCMAT. Para os acidentes
de gravidade alta, média e acidentes com óbito, foi perguntado ao funcionário que
estava acompanhando a visita; em todas as obras, não ocorreu nenhum acidente de
gravidade alta e acidente com óbito. No restante, todas as medidas de segurança eram
cumpridas, o que contribuiu para que o item de procedimentos úteis apresentasse maior
percentual de aprovação na implantação do PCMAT.
Figura 09 – Média final por item para o check list do PCMAT e de Implantação.
73%
70%
60%
60%
30% 26%
20%
10%
0%
Memorial Projeto Especificação Cronograma de Layout Inicial Programa Proced. Úteis
Proteções Técnica Implantação Educativo
Coletivas Proteções PCMAT
Coletivas e Implantação
Individuais
Fonte: Elaboração do autor.
5. CONSIDERAÇÕES FINAIS
Ao final da pesquisa, diante dos resultados obtidos, foi possível constatar que a
elaboração e aplicação do PCMAT ainda não possui a abrangência necessária entre as
empresas construtoras. Dos 30 canteiros de obras visitados, somente 53% possuíam o
PCMAT disponível no local.
Considerando os dados como um todo, pode-se concluir que quanto maior o porte da
edificação, maior também são as preocupações com a segurança do trabalho no canteiro
de obras, incluindo a atenção ao PCMAT. Observa-se que 100% dos canteiros de obras
de grande porte possuíam esse documento na obra; para os de médio porte a adesão caía
para 50%. Já nos canteiros de obras de pequeno porte, apenas um entre os dez
pesquisados possuía o PCMAT, sendo que o mesmo encontrava-se incompleto em
diversos quesitos.
Os resultados apontam que, tanto na elaboração do PCMAT quanto na sua implantação,
os itens que apresentaram não-conformidades mais significativas são referentes ao
projeto de execução das proteções coletivas e o cronograma de implantação das medidas
preventivas. Obteve-se que 87,5% dos PCMAT’s não possuíam em anexo o projeto de
execução das proteções coletivas e memorial descritivo de cálculo. Desta forma, como
não há um dimensionamento preciso, conclui-se que a maioria dos construtores
executam estas proteções sem ter um responsável técnico para o respectivo projeto,
podendo assim comprometer a eficiência destes sistemas e a segurança dos
trabalhadores. Portanto, obteve-se um percentual de conformidade de 42% para a
elaboração do projeto e 35% para sua implantação no canteiro de obras.
Quanto ao cronograma de implantação, o mesmo foi encontrado em anexo em 75% dos
PCMAT’s pesquisados. Porém, comparando-se com o exigido pela NR-18, obteve-se
um percentual de aprovação de apenas 48% considerando sua elaboração e 26% na
implantação. Nenhum dos cronogramas encontrados descrevia em seu conteúdo a
concepção e atualização de programas importantes, como o PPRA e PCMSO e até o
próprio PCMAT. Desta forma, é possível concluir que o próprio documento que visa
implantar as medidas de prevenção já encontra-se com não-conformidades, o que trará
deficiências ainda maiores na aplicação propriamente dita.
Com uma análise geral de todos os dados e informações coletadas durante a pesquisa,
para as dezesseis obras que possuíam o PCMAT, obteve-se uma média de cumprimento
de 69% para a elaboração do documento base e 58% na implantação no canteiro de
obras. Desta forma, conclui-se que a origem de grande parte das não-conformidades na
implantação do PCMAT nos canteiros de obras é a própria elaboração do programa;
pode-se afirmar que um documento que não está totalmente de acordo com o exigido
pela norma, também não obterá sucesso na sua implantação. A elaboração de um bom
PCMAT é de extrema importância para dar início aos sistemas segurança do trabalho na
construção civil, bem como para melhorar as condições dos seus integrantes,
diminuindo assim os riscos de doenças e acidentes neste ramo.
6. REFERÊNCIAS BIBLIOGRÁFICAS