Você está na página 1de 15

Vol corte (m3) Vol relleno (m3)

Bocatoma 3,351.99 -
Desarenador 15,467.99 150.00
Camara de carga 30,899.90 150.00
Transicion 13,701.29 60.50
Canales 345,537.92 2,789.59
Casa de maquinas 11,594.57
Total 420,553.66 3,150.09
Volumen de concreto armado
Area L und
Bocatoma 78.91 25 1
52 31.2 1
10.76 13.97 1
4.67 20.23 1
581.53 0.4 2
Transicion 464.02 0.4 1
2.64 15 1
26.34 0.4 1
6.99 15 1
Desarenador 13.19 18.3 1
22.34 26.8 1
15.17 18.3 1
54.44 72 1
Camara de carga 5.152 7 1
22 50.51 1
Canal 1.1955 2678.9 1
Total
Volumen de concreto armado
Volumen TOTAL
1,972.75 4,645.76
1,622.40
150.32
94.47
465.22
185.61
39.60
10.54
104.85
241.38 5,037.38
598.71
277.61
3,919.68
36.06 1,147.28
1,111.22
3,202.62
14,033.05 m3
Vol corte Vol relleno
Bocatoma 10067.76 0
Desarenador 79506.2155
Camara de carga 18749.55 150
Transicion 5745.65 60.5
Canales 162610 2789.59
Canales-tunel 5007.0701 0
281,686.25 3,000.09 m3
5007.0701
21,126,468.42
Canal B - D 20 129.53 109.53
Canal conduccion 264.93 2853.52 2588.59
2698.12
160
170
180
190
200
210
220
230
240
250
260
270
280
290
carama de carga
2880
2890
2900
2910
2920
2930
0
10
20
Hd 4.48
0.2 0.896
0.5 2.24
0.175 0.784
0.282 1.26336
103.27 5 516.35 99.19 51216.7565
27.16
72.02
99.18
27.53 55.07 513.7
27.54
L
Bocatoma 31.6
35.67
40.46
76.13 65.77
26,250,000.00
7,545,167.29
33,795,167.29 49,795,167.29
16000000
100366.54
37.19869391
Area corte Area relleno
0 10 0 0
0 10 0 0
1075 10 537.5 5375
995.06 10 1035.03 10350.3
883.6 10 939.33 9393.3
767.2 10 825.4 8254
735.51 10 751.355 7513.55
652.8 10 694.155 6941.55
584.4 8.36 10 618.6 6186 15.565 10
514.1 22.77 10 549.25 5492.5 16.605 10
500.8 10.44 10 507.45 5074.5
588.6 10 544.7 5447
640.5 10 614.55 6145.5
10 320.25 3202.5
79375.7
carama de carga
10 120.285 1202.85
240.57 10 120.285 1202.85
359.09 10 299.83 2998.3
219.74 10 289.415 2894.15
331.04 10 275.39 2753.9
302.59 10 316.815 3168.15
301.64 10 302.115 3021.15
10 150.82 1508.2
18749.55
441
391.72 10 416.36 4163.6
316.41 10 158.205 1582.05
5745.65
28289.459
corte
318.6 10067.76
1,611,494.09
155.65
166.05
321.7
Volumen de concreto armado = 14,033.05
Area L und Vol
Bocatoma 78.91 25 1 1,972.75
52 31.2 1 1,622.40
10.76 13.97 1 150.32
4.67 20.23 1 94.47
581.53 0.4 2 465.22
Transicion 464.02 0.4 1 185.61
2.64 15 1 39.60
26.34 0.4 1 10.54
6.99 15 1 104.85
Desarenador 13.19 18.3 1 241.38
22.34 26.8 1 598.71
15.17 18.3 1 277.61
54.44 72 1 3,919.68
Camara de carga 5.152 7 1 36.06
22 50.51 1 1,111.22
Canal 1.1955 2678.9 1 3,202.62
m3 220.00 3,087,270.62
4,305.17
340.59
5,037.38
1,147.28
L e
Canal 0.15 7.97
PRESUPUESTO - ALTERNATIVA 1
CONSTRUCCION CENTRAL HIDROELECTRICA MANTA 1
UND METRADO
COSTO UNIT.
($) PARCIAL($) TOTAL ($)
OBRAS PRELIMINARES 1,230,000.00
MOVILIZACION Y DESMOVILIZACION GLB 1.00 350,000.00 350,000.00
CONSTRUCCION DE ACCESO KM 2.20 400,000.00 880,000.00
CONSTRUCCION DE CAMPAMENTOS GLB 1.00 140,000.00 140,000.00
-
BOCATOMA - 1,242,898.52
TRAZO Y REPLANTEO DE OBRA M2 5,700.00 3.50 19,950.00
LIMPIEZA DE TERRENO M2 5,700.00 2.00 11,400.00
-
MOVIMIENTO DE TIERRAS -
CORTE DE MATERIAL NATURAL COMPACTO M3 17,053.28 6.00 102,319.68
NIVELACION Y REFINE M2 5,700.00 12.00 68,400.00
RELLENO Y COMPACTADO M3 2,215.00 20.00 44,300.00
ELIMINACION DE MATERIAL EXEDENTE M3 14,838.28 3.00 44,514.84
ESTABILIZACION DE TALUDES M2 4,990.00 51.00 254,490.00
-
OBRAS DE CONCRETO -
SOLADO DE CONCRETO M2 2,803.00 24.00 67,272.00
CONCRETO M3 1,500.00 190.00 285,000.00
ENCOFRADO M2 1,760.00 22.00 38,720.00
ACERO KG 53,460.00 4.20 224,532.00
-
OBRAS VARIOS -
COMPUERTAS GLB 1.00 70,000.00 70,000.00
INSTALACION DE INSTRUMENTACION GLB 1.00 12,000.00 12,000.00
-
DESARENADOR EN SUPERFICIE - 507,445.41
TRAZO Y REPLANTEO DE OBRA M2 2,939.00 3.50 10,286.50
LIMPIEZA DE TERRENO M2 2,939.00 2.00 5,878.00
-
MOVIMIENTO DE TIERRAS -
CORTE DE MATERIAL NATURAL COMPACTO M3 15,467.99 6.00 92,807.94
NIVELACION Y REFINE M2 2,939.00 21.00 61,719.00
RELLENO Y COMPACTADO M3 1,200.00 20.00 24,000.00
ELIMINACION DE MATERIAL EXEDENTE M3 14,267.99 3.00 42,803.97
-
OBRAS DE CONCRETO -
SOLADO DE CONCRETO M2 400.00 24.00 9,600.00
CONCRETO M3 405.00 190.00 76,950.00
ENCOFRADO M2 720.00 22.00 15,840.00
ACERO KG 44,550.00 3.20 142,560.00
-
OBRAS VARIOS -
COMPUERTAS GLB 1.00 15,000.00 15,000.00
INSTALACION DE INSTRUMENTACION GLB 1.00 10,000.00 10,000.00
-
OBRA DE CONDUCCION - 7,581,109.08
TRAZO Y REPLANTEO DE OBRA M2 62,500.00 3.50 218,750.00
LIMPIEZA DE TERRENO M2 62,500.00 2.00 125,000.00
-
MOVIMIENTO DE TIERRAS -
CORTE DE MATERIAL NATURAL COMPACTO M3 345,537.92 6.00 2,073,227.52
NIVELACION Y REFINE M2 62,500.00 12.00 750,000.00
RELLENO Y COMPACTADO M3 5,784.00 20.00 115,680.00
ESTABILLIZACION DE TALUDES M2 6,250.00 51.00 318,750.00
RELLENO Y COMPACTACION DE AFIRMADO PARA
CAMINO DE MANTENIMIENTO M3 2,625.00 16.00 42,000.00
ELIMINACION DE MATERIAL EXEDENTE M3 337,128.92 3.00 1,011,386.76
-
OBRAS DE CONCRETO -
SOLADO DE CONCRETO M2 2,170.00 24.00 52,080.00
CONCRETO M3 798.00 190.00 151,620.00
ENCOFRADO M2 415.40 22.00 9,138.80
ACERO KG 5,830.00 3.20 18,656.00
TUBERIA DE CONDUCCION -
TUBERIA DE CONDUCCION ML 4,500.00 550.00 2,475,000.00
CAMA DE ARENA M3 2,820.00 11.00 31,020.00
BUZONES DE INSPECCION Y VENTILACION UND 59.00 3,200.00 188,800.00
-
CAMARA DE CARGA - 658,774.02
TRAZO Y REPLANTEO DE OBRA M2 2,368.00 3.50 8,288.00
LIMPIEZA DE TERRENO M2 2,368.00 2.00 4,736.00
-
MOVIMIENTO DE TIERRAS -
CORTE DE MATERIAL NATURAL COMPACTO M3 30,899.90 6.00 185,399.40
NIVELACION Y REFINE M2 2,368.00 12.00 28,416.00
RELLENO Y COMPACTADO M3 130.00 20.00 2,600.00
ESTABILLIZACION DE TALUDES M2 1,371.00 51.00 69,921.00
ELIMINACION DE MATERIAL EXEDENTE M3 30,769.90 3.00 92,309.70
-
OBRAS DE CONCRETO -
SOLADO DE CONCRETO M2 536.00 24.00 12,864.00
CONCRETO M3 413.76 190.00 78,614.40
ENCOFRADO M2 681.00 22.00 14,982.00
ACERO KG 45,513.60 3.20 145,643.52
-
OBRAS VARIOS -
COMPUERTAS GLB 1.00 10,000.00 10,000.00
INSTALACION DE INSTRUMENTACION GLB 1.00 5,000.00 5,000.00
-
TUBERIA FORZADA - 3,852,601.75
TRAZO Y REPLANTEO DE OBRA M2 2,557.50 3.50 8,951.25
LIMPIEZA DE TERRENO M2 2,557.50 2.00 5,115.00
-
MOVIMIENTO DE TIERRAS -
CORTE DE MATERIAL PARA TUBERIA M3 4,603.50 6.00 27,621.00
NIVELACION Y REFINE M2 2,557.50 12.00 30,690.00
ESTABILLIZACION DE TALUD M2 2,557.50 51.00 130,432.50
ELIMINACION DE MATERIAL EXEDENTE M3 4,603.50 3.00 13,810.50
-
OBRAS DE CONCRETO -
SOLADO DE CONCRETO M2 2,557.50 24.00 61,380.00
CONCRETO M3 767.25 190.00 145,777.50
ENCOFRADO M2 1,920.00 22.00 42,240.00
ACERO KG 34,526.25 3.20 110,484.00
-
OBRAS VARIOS -
INSTALACION DE INSTRUMENTACION GLB 1.00 2,500.00 2,500.00
TUBERIA FORZADA DE ACERO M 1,023.00 3,200.00 3,273,600.00
-
CASA DE MAQUINAS Y CONDENSADORES - 1,819,189.67
TRAZO Y REPLANTEO DE OBRA M2 6,651.00 3.50 23,278.50
LIMPIEZA DE TERRENO M2 6,651.00 2.00 13,302.00
-
MOVIMIENTO DE TIERRAS -
CORTE DE MATERIAL M3 11,594.57 18.00 208,702.26
NIVELACION Y REFINE M2 6,651.00 12.00 79,812.00
RELLENO Y COMPACTADO M3 666.60 20.00 13,332.00
ESTABILLIZACION DE TALUD M2 4,429.00 51.00 225,879.00
ELIMINACION DE MATERIAL EXEDENTE M3 10,927.97 3.00 32,783.91
-
OBRAS DE GENERALES -
CONSTRUCCION DE CASA DE MAQUINAS M2 2,222.00 550.00 1,222,100.00
COSTO OBRAS CIVILES 16,892,018.45
OBRAS ELECTROMECANICAS 18,417,240.00
ADICIONALES 11,652,055.29
utilidad (10%) 3,530,925.85
INGENIERIA DE DETALLE (8% ) 2,824,740.68
GASTOS GENERALES Y SUPERVISION (10%) 3,530,925.85
IMPREVISTOS (5%) 1,765,462.92
COSTO TOTAL DE INVERSION
POTENCIA 23.9 Mw
RATIO 1,964.91 $/kw
46,961,313.74