1 Projek 427,400.00 17/07/17 03/12/17
2 Prelim 21,820.00
3 Mobilization
4 Demolition-Dormitory
5 a) Wall & Floor 8,200.00 25/07/17 07/08/17
6 b) Ceiling & dll 3,000.00 27/07/17 09/08/17
7 New Work - Dormitory
8 a) Brickwork & Rendering 14,030.00 07/08/17 16/09/17
9 b) Piping work 6,000.00 14/08/17 09/09/17
10 c) W/proofing work 2,240.00 28/08/17 11/09/17
11 d) Tiling Work 44,610.00 03/09/17 14/10/17
12 e) Skin coat & painting 14,800.00 21/08/17 07/10/17
13 f) Door & HPL work 14,400.00 23/09/17 12/10/17
14 g) Bar counter & cabinet 10,000.00 30/09/17 20/10/17
15 h) Artificial Grass 4,500.00 06/10/17 26/10/17
16 i) Sanitary fitting 14,780.00 29/09/17 13/10/17
17 j) Grill & roller blind 4,950.00 13/10/17 27/10/17
18 Demolition - Gazebo
19 a) Struktur binaan & pokok 4,000.00 07/08/17 21/08/17
20 b) Lantai & dll 4,500.00 14/08/17 28/08/17
21 New Work - Gazebo
22 a) Lowest Gid work 7,660.00 28/08/17 16/09/17
23 b) R.C work 40,010.00 10/09/17 01/10/17
24 c) Column RHS 12,000.00 25/09/17 08/10/17
25 d) Roof Structure 36,000.00 09/10/17 30/10/17
26 e) Roof Finishing 24,000.00 01/10/17 21/10/17
27 f) Brick work 22,720.00 22/09/17 21/10/17
28 g) Railing 18,600.00 28/10/17 19/11/17
29 h) Floor Finishing 7,490.00 05/11/17 26/11/17
30 i) Door & glass work 6,600.00 03/10/17 19/11/17
31 j) Counter work & grill 10,000.00 22/10/17 26/11/17
32 k) Furniture & dll 10,100.00 05/11/17 26/11/17
33 Demolition (Rumah Sampah)
34 a) Brickwall 2,000.00 16/09/17 30/09/17
35 b) Lantai Concrete 1,400.00 23/09/17 07/10/17
36 New Work (Rumah Sampah)
37 a) Lowest Gid work 5,400.00 23/09/17 14/10/17
38 b) R.C work 6,000.00 07/10/17 21/10/17
39 c) Roof Structure 9,000.00 14/10/17 28/10/17
40 d) Roof Finishing 7,200.00 14/10/17 14/11/17
41 e) Brick work 8,160.00 21/10/17 14/11/17
42 f) Ceiling work 5,220.00 28/10/17 05/11/17
43 g) Tiling work 4,410.00 28/10/17 12/11/17
44 h) Painting & door 6,200.00 05/11/17 12/11/17
45 i) Apron & pipe work 1,900.00 05/11/17 19/11/17
46 j) M.sgrating & dll 3,500.00 12/11/17 03/12/17
47 k) Testing & cleaning 19/11/17 03/12/17
48 l) Hand Over 26/11/17 03/12/17