DATA DE ATUALIZAÇÃO: 01-Mar-17 TASK filter: All Activities

Nº DA ATIVIDADE DESCRIÇÃO % EXEC. DUR. INÍCIO FIM DESVIO April 2017 May 2017 June 2017 July 2017
META
27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17
REPARO REFRATÁRIO E MECÂNICO HS8 0% 1906.00h 12-Apr-17 30-Jun-17 0.00h
07:00 17:00 12-Apr-17 07:00 30-Jun-17 17:00
INÍCIO ATIVIDADES 0% 0.00h 12-Apr-17 12-Apr-17 0.00h
07:00 07:00 12-Apr-17 07:00 12-Apr-17 07:00
DOCUMENTAÇÃO SEGURANÇA 0% 40.00h 12-Apr-17 17-Apr-17 0.00h
07:00 17:00 12-Apr-17 07:00 17-Apr-17 17:00
SUPRIMENTOS 0% 10.00h 12-Apr-17 12-Apr-17 0.00h
07:00 17:00 12-Apr-17 07:00 12-Apr-17 17:00
EXECUÇÃO 0% 1690.00h 12-Apr-17 21-Jun-17 0.00h
07:00 17:00 12-Apr-17 07:00 21-Jun-17 17:00
SERVIÇOS PREPARATIVOS PARA PARADA 0% 220.00h 12-Apr-17 11-May-17 0.00h
07:00 17:00 12-Apr-17 07:00 11-May-17 17:00
PARADA 0% 746.00h 10-May-17 10-Jun-17 0.00h
07:00 09:00 10-May-17 07:00 10-Jun-17 09:00
1ª PARADA 0% 50.00h 10-May-17 12-May-17 0.00h
07:00 09:00 10-May-17 07:00 12-May-17 09:00
DESMONTAR JUNTA DE EXPANSÃO DE AR QUENTE 0% 23.00h 10-May-17 11-May-17 0.00h
07:00 06:00 10-May-17 07:00 11-May-17 06:00
RIP1530 Liberação de área e bloqueio de equipamentos 0% 2.00h 10-May-17 10-May-17 0.00h
10-May-17 07:00 10-May-17 09:00
07:00* 09:00
RIP1560 Transportar ferramental e os parafusos estojo 0% 1.00h 10-May-17 10-May-17 0.00h
10-May-17 09:00 10-May-17 10:00
09:00 10:00
RIP1570 Instalar e posicionar ventiladores para conforto térmico 0% 1.00h 10-May-17 10-May-17 0.00h
10-May-17 09:00 10-May-17 10:00
09:00 10:00
RIP1580 Montar os 2 cilindros hidráulicos de 50ton nos dispositivos 0% 3.00h 10-May-17 10-May-17 0.00h
10-May-17 09:00 10-May-17 12:00
de tubulação de ar quente 09:00 12:00
RIP1540 Grafitar o enclausuramento 0% 6.00h 10-May-17 10-May-17 0.00h
10-May-17 09:00 10-May-17 15:00
09:00 15:00
RIP1550 Demolir o enclausuramento 0% 2.00h 10-May-17 10-May-17 0.00h
10-May-17 15:00 10-May-17 17:00
15:00 17:00
RIP1590 Cortar e remover 120 parafusos Ø 42 e 45mm deixando 4 0% 4.50h 10-May-17 10-May-17 0.00h
10-May-17 17:00 10-May-17 21:30
parafusos sem porcas a 90º 17:00 21:30
RIP1600 Efetuar lingada da junta de expansão 0% 1.00h 10-May-17 10-May-17 0.00h
10-May-17 21:30 10-May-17 22:30
21:30 22:30
RIP1610 Instalações dos 8 cilindros hidráulicos de 30ton do 0% 1.50h 10-May-17 10-May-17 0.00h
10-May-17 22:00 10-May-17 23:30
acionamento sincronizado para compressão da junta de 22:00 23:30
expansão
RIP1620 Desmontar 1 ou 2 tirantes de 80mm e soltar os outros que 0% 1.50h 10-May-17 11-May-17 0.00h
10-May-17 23:00 11-May-17 00:30
prendem a tubulação de ar quente 23:00 00:30
RIP1630 Tensionar os cilindros hidráulicos para deslocar tubulação 0% 1.50h 11-May-17 11-May-17 0.00h
11-May-17 00:00 11-May-17 01:30
de ar quente 00:00 01:30
RIP1640 Acionar 8 cilindros hidráulicos sincronizados para comprimir 0% 1.50h 11-May-17 11-May-17 0.00h
11-May-17 01:30 11-May-17 03:00
a junta de expansão 01:30 03:00
RIP2330 Montar guindaste 0% 4.00h 10-May-17 11-May-17 0.00h
10-May-17 23:30 11-May-17 03:30
23:30 03:30
RIP1650 Efetuar o travamento da junta de expansão através dos 0% 1.00h 11-May-17 11-May-17 0.00h
11-May-17 03:00 11-May-17 04:00
tirantes 03:00 04:00
RIP1660 Retirar junta de expansão e cilindros hidráulicos do 0% 1.00h 11-May-17 11-May-17 0.00h
11-May-17 04:00 11-May-17 05:00
dispositivo tubular 04:00 05:00

Actual Work Critical Remaining W... REPARO REFRATÁRIO E MECÂNICO HS8 Página: 1 / 4

Remaining Work Milestone


Página 1 de 4
DATA DE ATUALIZAÇÃO: 01-Mar-17 TASK filter: All Activities
Nº DA ATIVIDADE DESCRIÇÃO % EXEC. DUR. INÍCIO FIM DESVIO April 2017 May 2017 June 2017 July 2017
META
27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17
RIP1670 Instalar cortina no bocal da sáida do tubo se necessário 0% 1.00h 11-May-17 11-May-17 0.00h
11-May-17 05:00 11-May-17 06:00
para minimizar saída de vapor quente 05:00 06:00
DESMONTAR VÁLVUL A DE AR QUENTE 0% 48.00h 10-May-17 12-May-17 0.00h
09:00 09:00 10-May-17 09:00 12-May-17 09:00
RIP1680 Desconectar sistema de lubrificação 0% 1.00h 10-May-17 10-May-17 0.00h
10-May-17 09:00 10-May-17 10:00
09:00 10:00
RIP1690 Desconectar rede de ar comprimida 0% 1.00h 10-May-17 10-May-17 0.00h
10-May-17 10:00 10-May-17 11:00
10:00 11:00
RIP1700 Desconectar sistema elétrico, sensores conduletes e 0% 1.00h 10-May-17 10-May-17 0.00h
10-May-17 11:00 10-May-17 12:00
flexível 11:00 12:00
RIP1710 Travar contra peso 0% 1.50h 10-May-17 10-May-17 0.00h
10-May-17 12:00 10-May-17 13:30
12:00 13:30
RIP1720 Efetuar a lingada da válvula de ar quente 0% 2.00h 11-May-17 11-May-17 0.00h
11-May-17 06:00 11-May-17 08:00
06:00 08:00
RIP1730 Efetuar corte nos 60 parafusos Ø42 e 45mm 0% 3.00h 11-May-17 11-May-17 0.00h
11-May-17 08:00 11-May-17 11:00
08:00 11:00
RIP1740 Desconectar 14 conexões de refrigeração da VAQ, sendo 7 0% 2.00h 11-May-17 11-May-17 0.00h
11-May-17 10:00 11-May-17 12:00
entrada e 7 saída 10:00 12:00
RIP1750 Retirar VAQ posicionando sobre cavalete entre HS7 e HS8 0% 2.00h 11-May-17 11-May-17 0.00h
11-May-17 10:00 11-May-17 12:00
10:00 12:00
RIP1760 Desmontar contra peso da VAQ para transporte 0% 1.00h 11-May-17 11-May-17 0.00h
11-May-17 11:30 11-May-17 12:30
11:30 12:30
RIP1970 Montar andaime (Adequação) 0% 2.00h 11-May-17 11-May-17 0.00h
11-May-17 12:30 11-May-17 14:30
12:30 14:30
RIP1770 Efetuar parede de contenção na linha de ar quente 0% 5.00h 11-May-17 11-May-17 0.00h
11-May-17 14:30 11-May-17 19:30
14:30 19:30
RIP1840 Içar e montar flange refrigerado com a junta de vedação e 4 0% 2.50h 11-May-17 11-May-17 0.00h
11-May-17 19:30 11-May-17 22:00
parafusos estojo a 90º e aperto manual 19:30 22:00
RIP1850 Montar sistema de refrigeração do flange refrigerado 0% 1.50h 11-May-17 11-May-17 0.00h
11-May-17 21:30 11-May-17 23:00
21:30 23:00
RIP1860 Montar os 56 parafusos estojo e efetuar torqueamento nos 0% 8.00h 11-May-17 12-May-17 0.00h
11-May-17 23:00 12-May-17 07:00
60 parafusos 23:00 07:00
RIP1880 Efetuar topografia dos dutos de ar quente 0% 4.00h 12-May-17 12-May-17 0.00h
12-May-17 05:00 12-May-17 09:00
05:00 09:00
VÁLVULA DE AR DE CO MBUSTÃO DN 1400 0% 11.00h 10-May-17 11-May-17 0.00h
17:00 04:00 10-May-17 17:00 11-May-17 04:00
VÁLVULA DE GÁS DE COMBUSTÃO DN 1500 0% 12.00h 10-May-17 11-May-17 0.00h
17:00 05:00 10-May-17 17:00 11-May-17 05:00
VÁLVULA DE AR FRIO DN 1600 0% 21.00h 11-May-17 12-May-17 0.00h
05:00 02:00 11-May-17 05:00 12-May-17 02:00
VÁLVULA DE ALIVIO D N 300 0% 12.50h 11-May-17 11-May-17 0.00h
05:00 17:30 11-May-17 05:00 11-May-17 17:30
VÁLVULA DE CHAMINÉ DN 1900 0% 12.50h 10-May-17 11-May-17 0.00h
17:00 05:30 10-May-17 17:00 11-May-17 05:30
VÁLVULA DE ALIVIO D N 300- 1 0% 12.50h 10-May-17 11-May-17 0.00h
17:00 05:30 10-May-17 17:00 11-May-17 05:30
DESMONTAR MANHOLES 0% 9.00h 11-May-17 11-May-17 0.00h
07:00 16:00 11-May-17 07:00 11-May-17 16:00

Actual Work Critical Remaining W... REPARO REFRATÁRIO E MECÂNICO HS8 Página: 2 / 4

Remaining Work Milestone


Página 2 de 4
DATA DE ATUALIZAÇÃO: 01-Mar-17 TASK filter: All Activities
Nº DA ATIVIDADE DESCRIÇÃO % EXEC. DUR. INÍCIO FIM DESVIO April 2017 May 2017 June 2017 July 2017
META
27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17
DERIVAÇÃO DE GÁS NATURAL 0% 2.00h 12-May-17 12-May-17 0.00h
05:00 07:00 12-May-17 05:00 12-May-17 07:00
SERVIÇO ENTRE PARADAS 0% 696.00h 12-May-17 10-Jun-17 0.00h
09:00 09:00 12-May-17 09:00 10-Jun-17 09:00
2ª PARADA 0% 40.00h 08-Jun-17 10-Jun-17 0.00h
09:00 01:00 08-Jun-17 09:00 10-Jun-17 01:00
MONTAR VÁLVULA DE AR QUENTE E JUNTA DE EXPANSÃO 0% 40.00h 08-Jun-17 10-Jun-17 0.00h
09:00 01:00 08-Jun-17 09:00 10-Jun-17 01:00
MONTAR VÁLVULA DE AR QUENTE 0% 24.50h 08-Jun-17 09-Jun-17 0.00h
09:00 09:30 08-Jun-17 09:00 09-Jun-17 09:30
RIP2870 Bloqueio 0% 1.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 09:00 08-Jun-17 10:00
09:00 10:00
RIP2310 Efetuar a estropagem, cortar e retirar os parafusos o flange 0% 4.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 10:00 08-Jun-17 14:00
refrigerado 10:00 14:00
RIP2320 Retirar o flange refrigerado e desconectar sistema de 0% 2.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 12:00 08-Jun-17 14:00
refrigeração 12:00 14:00
RIP2920 Retirar parede de contenção na linha de ar quente 0% 2.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 14:00 08-Jun-17 16:00
14:00 16:00
RIP2340 Limpar a face do flange da tubulação ar quente 0% 1.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 16:00 08-Jun-17 17:00
16:00 17:00
RIP2350 Efetuar lingada, posicionar VAQ e interligar sistema 0% 2.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 16:00 08-Jun-17 18:00
refrigeração 16:00 18:00
RIP2360 Aproximar a VAQ do local de montagem e ligar sistema de 0% 4.00h 08-Jun-17 08-Jun-17 0.00h
08-Jun-17 18:00 08-Jun-17 22:00
refrigeração 18:00 22:00
RIP2370 Posicionar 4 parafusos novos á 90º eqüidistante com junta 0% 3.00h 08-Jun-17 09-Jun-17 0.00h
08-Jun-17 21:00 09-Jun-17 00:00
de vedação e montar juntamente com VAQ 21:00 00:00
RIP2380 Montar os 56 parafusos novos e torquear os 60 parafusos 0% 8.00h 08-Jun-17 09-Jun-17 0.00h
08-Jun-17 22:30 09-Jun-17 06:30
22:30 06:30
RIP2390 Interligar o sistema de lubrificação e ar comprimido 0% 2.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 05:00 09-Jun-17 07:00
05:00 07:00
RIP2400 Efetuar ligações do sistema elétrico e sensores 0% 2.50h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 06:00 09-Jun-17 08:30
06:00 08:30
RIP2410 Retirar suporte do travamento do contra peso da VAQ 0% 2.50h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 07:00 09-Jun-17 09:30
07:00 09:30
MONTAR JUNTA DE EXPANSÃO 0% 25.00h 09-Jun-17 10-Jun-17 0.00h
00:00 01:00 09-Jun-17 00:00 10-Jun-17 01:00
RIP2420 Efetuar a estropagem da junta expansão nova e 0% 2.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 00:00 09-Jun-17 02:00
posicionada entre flanges da VAQ e duto de ar quente lado 00:00 02:00
HS7
RIP2450 Avaliar e corrigir as montagem dos 2 cilindros hidráulicos 0% 2.50h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 00:00 09-Jun-17 02:30
nos suportes do berço móvel e suporte fixo 00:00 02:30
RIP2460 Reinstalar 8 cilindros hidráulicos para expansão da junta e 0% 2.50h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 00:00 09-Jun-17 02:30
abrir os flanges 00:00 02:30
RIP2430 Montar 1 junta de vedação com 4 parafusos do lado VAQ e 0% 2.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 02:00 09-Jun-17 04:00
montar 1 junta de vedação com 4 parafusos lado HS7 02:00 04:00
RIP2440 Folgar os tirantes da junta expansão 0% 2.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 02:00 09-Jun-17 04:00
02:00 04:00
RIP2470 Tensionar sincronizados 8 cilindros hidráulicos e aproximar 0% 2.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 02:00 09-Jun-17 04:00
dos flanges a 1148mm 02:00 04:00

Actual Work Critical Remaining W... REPARO REFRATÁRIO E MECÂNICO HS8 Página: 3 / 4

Remaining Work Milestone


Página 3 de 4
DATA DE ATUALIZAÇÃO: 01-Mar-17 TASK filter: All Activities
Nº DA ATIVIDADE DESCRIÇÃO % EXEC. DUR. INÍCIO FIM DESVIO April 2017 May 2017 June 2017 July 2017
META
27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17
RIP2480 Retirar dispositivo de expansão da junta de expansão 0% 3.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 03:00 09-Jun-17 06:00
03:00 06:00
RIP2930 Montar junta de expansão 0% 3.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 06:00 09-Jun-17 09:00
06:00 09:00
RIP2490 Montar o restante dos parafusos (56 parafusos de cada 0% 8.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 09:00 09-Jun-17 17:00
lado) e torquear 09:00 17:00
RIP2510 Montar e tensionar os tirantes de 80mm 0% 2.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 20:00 09-Jun-17 22:00
20:00 22:00
RIP2500 Desmontar os 2 cilindros dos tubos mecânicos tensor e 0% 6.00h 09-Jun-17 09-Jun-17 0.00h
09-Jun-17 17:00 09-Jun-17 23:00
sistema de refrigeração 17:00 23:00
RIP2520 Recompor o piso e plataformas de acesso e manutenção 0% 2.00h 09-Jun-17 10-Jun-17 0.00h
09-Jun-17 23:00 10-Jun-17 01:00
da VAQ 23:00 01:00
VÁLVULA DE AR DE CO MBUSTÃO DN 1400 0% 15.00h 08-Jun-17 09-Jun-17 0.00h
09:00 00:00 08-Jun-17 09:00 09-Jun-17 00:00
VÁLVULA DE GÁS DE COMBUSTÃO DN 1500 0% 16.00h 08-Jun-17 09-Jun-17 0.00h
10:00 02:00 08-Jun-17 10:00 09-Jun-17 02:00
VÁLVULA DE AR FRIO DN 1600 0% 10.00h 08-Jun-17 09-Jun-17 0.00h
19:00 05:00 08-Jun-17 19:00 09-Jun-17 05:00
VÁLVULA AL IVIO DN 300 0% 6.00h 08-Jun-17 09-Jun-17 0.00h
19:00 01:00 08-Jun-17 19:00 09-Jun-17 01:00
VÁLVULA DE CHAMINÉ DN 1900 0% 19.00h 09-Jun-17 09-Jun-17 0.00h
04:00 23:00 09-Jun-17 04:00 09-Jun-17 23:00
VÁLVULA EQUALIZAÇÃO DN 300 0% 8.00h 09-Jun-17 09-Jun-17 0.00h
07:00 15:00 09-Jun-17 07:00 09-Jun-17 15:00
MONTAR MANHOLES 0% 7.00h 09-Jun-17 09-Jun-17 0.00h
01:00 08:00 09-Jun-17 01:00 09-Jun-17 08:00
DEVIRAÇÃO DE GÁS NATURAL 0% 5.00h 09-Jun-17 09-Jun-17 0.00h
08:00 13:00 09-Jun-17 08:00 09-Jun-17 13:00
SERVIÇOS FINAIS 0% 80.00h 12-Jun-17 21-Jun-17 0.00h
07:00 17:00 12-Jun-17 07:00 21-Jun-17 17:00
COMISSIONAMENTO 0% 104.00h 09-Jun-17 13-Jun-17 0.00h
01:00 09:00 09-Jun-17 01:00 13-Jun-17 09:00
DESMOBILIZAÇÃO 0% 90.00h 20-Jun-17 30-Jun-17 0.00h
07:00 17:00 20-Jun-17 07:00 30-Jun-17 17:00

Actual Work Critical Remaining W... REPARO REFRATÁRIO E MECÂNICO HS8 Página: 4 / 4