PLANTA BAIXA - ARMADURAS

TOTAL PESO
542 542 ELEMENTO N FACE QUANT. COMPR. (M)
(MM) (M) (KG)

SUPERIOR /
1 A-A 8.0 28 4.47 125.16 50.06
266 5 133 266 5 133 INFERIOR
INFERIOR /
Va Va 2 A-A
SUPERIOR
8.0 15 4.76 71.40 28.56

3 A-A SUPERIOR 8.0 28 1.10 30.80 12.32

4 B-B SUPERIOR 8.0 9 5.74 51.66 20.66


sobe sobe sobe sobe
5 B-B INFERIOR 8.0 17 5.68 96.56 38.62

SUPERIOR /
6 C-C 8.0 20 4.89 97.80 39.12
9 9 9 INFERIOR
ESCADA
SUPERIOR /
10 8 10 7 C-C 8.0 20 4.76 95.20 38.08

372

372
INFERIOR
11 7 11 8 C-C INFERIOR 8.0 20 1.10 22.00 8.80
12 6 12
9 D-D SUPERIOR 8.0 30 2.72 81.60 32.64
13 5 13
14 4 14 10 D-D INFERIOR 8.0 30 2.72 81.60 32.64
15 3 15
11 E-E SUPERIOR 8.0 28 1.40 39.20 15.68
16 2 16
17 1 17 12 E-E INFERIOR 8.0 26 1.40 36.40 14.56

18 18 TOTAL + 10% = 364.93


VB24 VB24
CARIMBOS:

266 5 133

N4 N4 9 PATAMAR
8
7
6 LEGENDA:
N5 N5 5 1 - MEDIDAS EM CM, EXCETO QUANDO MOSTRADO O
4
3 Va
2 - CONFERIR MEDIDAS NO LOCAL DA OBRA;
2
536 1
3 - CONCRETO FCK = 25 MPA;
50
4 - VOLUME ESTIMADO DE CONCRETO = 3,78 M3;

5
50
536

5
6 - VOLUME DE CIMBRAMENTO = 28,58 M3;
V24 7 - COBRIMENTO = 2,5 CM.
136

5
Viga Baldrame

2
29

AUTOR(ES) DO PROJETO E ART: AUTOR(ES) DO PROJETO E ART:


121
266

5
__________________________ __________________________
37

6
1
31

260 __________________________ __________________________


10

260

REGISTRO CONTROLE INTERNO

FASE III (4 CAMPI)


DATA:
18 1o PAVIMENTO
17 20/03/2016
16 NOME ARQUIVO:
15
14 V17 IFAM - FASE III - EIRU-ESCADA - ESTRUTURAL.DWG
13 NOME ARQUIVO ANTERIOR:
12
11
10
PATAMAR 9

ESTRUTURAL
7
10
19

FASE III
Va BRASIL AMAZONAS
6
25 REITOR AMAZONAS:
31

1/1
10

7 ANTONIO VENANCIO CASTELO BRANCO


5
166 27
5

13
ASSUNTO: ESCALA:

10 PROJ.ESTRUT. DA ESCADA DE CONC. ARMADO 1/50


151
5

REITORIA/CAMPUS:
5

50
50
5

BAIRRO: CIDADE: UF:

AM
CEP: TELEFONE: HOME PAGE:

69.880-000 (097) 3481-1217 www.ifam.edu.br