Pesquisa Operacional - CPM 2023-05-21 15:46

ATIVIDADE ΔT ΔC Custo Incremental


1 --- 2 1 100 100
1 --- 3 1 50 50
1 --- 4 2 240 120
2 --- 4 2 160 80
2 --- 5 2 120 60
3 --- 4 0 0
3 --- 5 1 100 100
4 --- 5 2 280 140

************ ESQUEMA NORMAL ***********

ATIVIDADE DATA MAIS CEDO DATA MAIS FOLGA ATIVIDADE


TARDE
I --- J DURAÇÃO INÍCIO FIM INÍCIO FIM TOTAL CRÍTICA
1 --- 2 4 0 4 0 4 0 *
1 --- 3 3 0 3 4 7 4
1 --- 4 7 0 7 2 9 2
2 --- 4 5 4 9 4 9 0 *
2 --- 5 10 4 14 6 16 2
3 --- 4 2 3 5 7 9 4
3 --- 5 2 3 5 14 16 11
4 --- 5 7 9 16 9 16 0 *

***** CAMINHO(S) CRÍTICO(S) *****

1-2 2-4 4-5

CUSTO = 1320 DURAÇÃO = 16

COMPRESSÃO DA ATIVIDADE (2 --- 4) DE 2 UNIDADE(S) CUSTO INC. = 80


ATIVIDADE DATA MAIS CEDO DATA MAIS FOLGA ATIVIDADE
TARDE
I --- J DURAÇÃO INÍCIO FIM INÍCIO FIM TOTAL CRÍTICA
1 --- 2 4 0 4 0 4 0 *
1 --- 3 3 0 3 2 5 2
1 --- 4 7 0 7 0 7 0 *
2 --- 4 3 4 7 4 7 0 *
2 --- 5 10 4 14 4 14 0 *
3 --- 4 2 3 5 5 7 2
3 --- 5 2 3 5 12 14 9
4 --- 5 7 7 14 7 14 0 *

***** CAMINHO(S) CRÍTICO(S) *****

1-2 2-4 4-5

1-4 4-5

1-4 4-5

1-4 4-5

1-2 2-5

CUSTO = 1480 DURAÇÃO = 14

COMPRESSÃO DA ATIVIDADE (2 --- 5) DE 2 UNIDADE(S) CUSTO INC. = 60

COMPRESSÃO DA ATIVIDADE (4 --- 5) DE 2 UNIDADE(S) CUSTO INC. = 140

ATIVIDADE DATA MAIS CEDO DATA MAIS FOLGA ATIVIDADE


TARDE
I --- J DURAÇÃO INÍCIO FIM INÍCIO FIM TOTAL CRÍTICA
1 --- 2 4 0 4 0 4 0 *
1 --- 3 3 0 3 2 5 2
1 --- 4 7 0 7 0 7 0 *
2 --- 4 3 4 7 4 7 0 *
2 --- 5 8 4 12 4 12 0 *
3 --- 4 2 3 5 5 7 2
3 --- 5 2 3 5 10 12 7
4 --- 5 5 7 12 7 12 0 *

***** CAMINHO(S) CRÍTICO(S) *****


1-2 2-4 4-5

1-4 4-5

1-4 4-5

1-4 4-5

1-2 2-5

CUSTO = 1880 DURAÇÃO = 12

COMPRESSÃO DA ATIVIDADE (1 --- 2) DE 1 UNIDADE(S) CUSTO INC. = 100

COMPRESSÃO DA ATIVIDADE (1 --- 4) DE 1 UNIDADE(S) CUSTO INC. = 120

ATIVIDADE DATA MAIS CEDO DATA MAIS FOLGA ATIVIDADE


TARDE
I --- J DURAÇÃO INÍCIO FIM INÍCIO FIM TOTAL CRÍTICA
1 --- 2 3 0 3 0 3 0 *
1 --- 3 3 0 3 1 4 1
1 --- 4 6 0 6 0 6 0 *
2 --- 4 3 3 6 3 6 0 *
2 --- 5 8 3 11 3 11 0 *
3 --- 4 2 3 5 4 6 1
3 --- 5 2 3 5 9 11 6
4 --- 5 5 6 11 6 11 0 *

***** CAMINHO(S) CRÍTICO(S) *****

1-2 2-4 4-5

1-4 4-5

1-4 4-5

1-4 4-5

1-2 2-5

CUSTO = 2100 DURAÇÃO = 11