Você está na página 1de 32

RESUMEN DIARIO DE ACTIVIDADES

Cantidad
Descripción
Contractual Homologada PH Ejecutada día Acumulada Total a facturar Por ejecutar
Fosos Auger 126 24 24 102
Pilotes (Und) Cámaras 26 0 26
Zanja 394 16 1 9 25 369
Cruce Vía Perimetral 14.11 14.11 14.11 0
Canal la Villa y el Tabú 141.66 0 141.66
Canal Salin Bechara 50 0 50
Canal Libano 40 0 40
Auger Boring (m) Canal San Martín 60 0 60
Canal Amador y Cortes 70.25 0 70.25
Canal Barcelona 46 0 46
Canal San Pablo 50 0 50
Canal Ma. Auxiliadora 60.5 60.5 60.5 0
Excavación 1388.6 51.19 51.19 1337.41
ZCA (m) Concretos 1388.6 51.19 51.19 1337.41
Rellenos 1388.6 51.19 51.19 1337.41
Excavación 3 0 3
Cajas (Und) Concreto 3 0 3
Rellenos 3 0 3
RESUMEN DIARIO DE ACTIVIDADES CONCRETO
Peso camisas
Cantidad Volumen teórico Volumen % de acero (Kg)
Descripción
Contractual Ejecutados Por ejecutar (m3) Comprado (m3) Sobreexcavación
Pilotes (Und) 499 368 131 1947.03 2615.5 34.33% 78277.85
Fecha de Longitud
Consecutivo Identificación Longitud UNITARIOS
vaciado camisa
9 274A 17-Jul 18 9.6 5.09 7 1.91
13 272A 19-Jul 17.9 9.6 5.06 7 1.94
23 271A 2-Aug 18 14.4 5.09 6.5 1.41
26 271B 5-Aug 18 9.6 5.09 6.75 1.66
27 183B 5-Aug 17.9 9.6 5.06 8.5 3.44
31 272B 8-Aug 18 14.4 5.09 6.75 1.66
32 183A 8-Aug 17.9 9.6 5.06 6.5 1.44
33 273B 9-Aug 18 9.6 5.09 6.75 1.66
36 182B 10-Aug 17.9 9.6 5.06 6.5 1.44
37 180B 12-Aug 17.9 9.6 5.06 8.5 3.44
38 181B 12-Aug 17.9 9.6 5.06 8.5 3.44
43 273A 15-Aug 18 16.8 5.09 6.75 1.66
47 182A 17-Aug 17.9 9.6 5.06 6.5 1.44
62 181A 29-Aug 17.9 9.6 5.06 7 1.94
71 180A 31-Aug 17.9 9.6 5.06 7 1.94
220 86B 26-Nov 18.4 9.6 5.2 6.75 1.55
221 84B 26-Nov 18.4 9.6 5.2 6.75 1.55
222 86A 27-Nov 18.5 9.6 5.23 6.75 1.52
223 84A 27-Nov 18.4 9.6 5.2 6.75 1.55
224 85B 27-Nov 18.4 9.6 5.2 6.75 1.55
225 85A 28-Nov 18.5 9.6 5.23 6.75 1.52
226 83B 28-Nov 18.4 9.6 5.2 6.75 1.55
227 82A 28-Nov 18.4 9.6 5.2 7 1.8
230 82B 29-Nov 18.5 9.6 5.23 6.75 1.52
231 83A 29-Nov 18.5 9.6 5.23 6.75 1.52

Sobrevolumen 34%
RIOS ACUMULADOS Ubicación
37.52% 45.57 60.00 14.43 31.67% Caja
38.34% 65.81 88.00 22.19 33.72% Caja
27.70% 121.67 162.75 41.08 33.76% Caja
32.61% 136.94 183 46.06 33.64% Caja
67.98% 142 191.5 49.5 34.86% Caja
32.61% 162.33 217.75 55.42 34.14% Caja
28.46% 167.39 224.25 56.86 33.97% Caja
32.61% 172.48 231 58.52 33.93% Caja
28.46% 187.69 251 63.31 33.73% Caja
67.98% 197.3 266 68.7 34.82% Caja
67.98% 202.36 274.5 72.14 35.65% Caja
32.61% 227.78 308.25 80.47 35.33% Caja
28.46% 248.02 334.25 86.23 34.77% Caja
38.34% 326.31 440.5 114.19 34.99% Caja
38.34% 373.06 503.5 130.44 34.96% Caja
29.81% 1146.91 1568.25 421.34 36.74% Caja
29.81% 1152.11 1575 422.89 36.71% Caja
29.06% 1157.34 1581.75 424.41 36.67% Caja
29.81% 1162.54 1588.5 425.96 36.64% Caja
29.81% 1167.74 1595.25 427.51 36.61% Caja
29.06% 1172.97 1602 429.03 36.58% Caja
29.81% 1178.17 1608.75 430.58 36.55% Caja
34.62% 1183.37 1615.75 432.38 36.54% Caja
29.06% 1199.12 1636.25 437.13 36.45% Caja
29.06% 1204.35 1643 438.65 36.42% Caja
El pedido fue de 8 m3, se emplearon 1,25 m3 para solado.
UNITARIOS ACUM
Fecha de
Consecutivo Identificación Volumen Volumen Sobre % Sobre Volumen
vaciado
teórico empleado volumen volumen teórico
1 267 20-Sep 2.4 2.5 0.1 4.17% 2.4
2 269 20-Sep 2.4 2.5 0.1 4.17% 4.8
3 243 23-Sep 2.4 2.5 0.1 4.17% 7.2
4 244 23-Sep 2.4 2.5 0.1 4.17% 9.6
5 240 24-Sep 2.4 2.5 0.1 4.17% 12
6 241 24-Sep 2.4 2.5 0.1 4.17% 14.4
7 266 26-Sep 3.3 3.5 0.2 6.06% 17.7
8 268 26-Sep 3.3 3.5 0.2 6.06% 21
9 270 27-Sep 3.5 3.75 0.25 7.14% 24.5
10 237 2-Oct 2.4 2.5 0.1 4.17% 26.9
11 238 2-Oct 2.4 2.5 0.1 4.17% 29.3
12 239' 2-Oct 2.4 2.5 0.1 4.17% 31.7
13 239'' 11-Oct 2.4 2.5 0.1 4.17% 34.1
14 242 11-Oct 2.4 3.5 1.1 45.83% 36.5
15 171 22-Oct 2.4 2.5 0.1 4.17% 38.9
16 172 22-Oct 2.4 2.5 0.1 4.17% 41.3
17 173 22-Oct 2.4 2.5 0.1 4.17% 43.7
18 174 22-Oct 2.4 2.5 0.1 4.17% 46.1
19 175 25-Oct 2.4 2.5 0.1 4.17% 48.5
20 176 25-Oct 2.4 2.5 0.1 4.17% 50.9
21 177 28-Oct 2.4 2.5 0.1 4.17% 53.3
22 178 29-Oct 2.4 3 0.6 25.00% 55.7
23 179 31-Oct 2.4 2.5 0.1 4.17% 58.1
24 188 27-Nov 2.4 2.5 0.1 4.17% 60.5
25 189 27-Nov 2.4 2.5 0.1 4.17% 62.9
26 186 30-Nov 3.2 3.25 0.05 1.56% 66.1
27 187 30-Nov 3.2 3.25 0.05 1.56% 69.3
28 214 3-Dec 2.4 2.5 0.1 4.17% 71.7
29 215 3-Dec 2.4 2.5 0.1 4.17% 74.1
30 216 3-Dec 2.4 2.5 0.1 4.17% 76.5
31 217 6-Dec 2.4 2.5 0.1 4.17% 78.9
32 218 6-Dec 2.4 2.5 0.1 4.17% 81.3
33 162 11-Dec 2.4 2.5 0.1 4.17% 83.7
34 163 11-Dec 2.4 2.5 0.1 4.17% 86.1
35 160 13-Dec 2.4 2.5 0.1 4.17% 88.5
36 161 13-Dec 2.4 2.5 0.1 4.17% 90.9
37 185 14-Dec 2.4 2.5 0.1 4.17% 93.3
38 223 14-Dec 2.4 2.5 0.1 4.17% 95.7
39 224 14-Dec 2.4 2.5 0.1 4.17% 98.1
40 158 17-Dec 2.4 2.5 0.1 4.17% 100.5
41 159 17-Dec 2.4 2.5 0.1 4.17% 102.9
42 221 17-Dec 2.4 2.5 0.1 4.17% 105.3
43 222 17-Dec 2.4 2.5 0.1 4.17% 107.7
44 220 19-Dec 2.4 2.5 0.1 4.17% 110.1
45 156 19-Dec 2.4 2.5 0.1 4.17% 112.5
46 157 19-Dec 2.4 2.5 0.1 4.17% 114.9
47 184 20-Dec 2.4 2.5 0.1 4.17% 117.3
48 219 20-Dec 2.4 2.5 0.1 4.17% 119.7
49 155 28-Dec 2.4 2.5 0.1 4.17% 122.1
50 198 3-Jan 2.4 2.5 0.1 4.17% 124.5
51 199 3-Jan 2.4 2.5 0.1 4.17% 126.9
52 200 4-Jan 2.4 2.5 0.1 4.17% 129.3
53 201 4-Jan 2.4 2.5 0.1 4.17% 131.7
54 153 7-Jan 2.4 2.5 0.1 4.17% 134.1
55 154 7-Jan 2.4 2.5 0.1 4.17% 136.5
56 202 8-Jan 2.4 2.5 0.1 4.17% 138.9
57 213 9-Jan 2.4 2.5 0.1 4.17% 141.3
58 212 10-Jan 2.4 2.5 0.1 4.17% 143.7
59 197 11-Jan 2.4 2.5 0.1 4.17% 146.1
60 152 13-Jan 2.4 2.5 0.1 4.17% 148.5
61 203 13-Jan 2.4 2.5 0.1 4.17% 150.9
62 210 13-Jan 2.4 2.5 0.1 4.17% 153.3
63 211 13-Jan 2.4 2.5 0.1 4.17% 155.7
64 151 14-Jan 2.4 2.5 0.1 4.17% 158.1
65 209 14-Jan 2.4 2.5 0.1 4.17% 160.5
66 204 15-Jan 2.4 2.5 0.1 4.17% 162.9
67 205 17-Jan 2.4 2.5 0.1 4.17% 165.3
68 206 18-Jan 2.4 2.5 0.1 4.17% 167.7
69 150 20-Jan 2.4 2.5 0.1 4.17% 170.1
70 208 20-Jan 2.4 2.5 0.1 4.17% 172.5
71 149 21-Jan 2.4 2.5 0.1 4.17% 174.9
72 207 23-Jan 2.4 2.5 0.1 4.17% 177.3
73 148 27-Jan 2.4 2.5 0.1 4.17% 179.7
74 39 29-Jan 2.4 2.5 0.1 4.17% 182.1
75 146 29-Jan 2.4 2.5 0.1 4.17% 184.5
76 147 29-Jan 2.4 2.5 0.1 4.17% 186.9
77 40 30-Jan 2.4 2.5 0.1 4.17% 189.3
78 51 31-Jan 2.4 2.5 0.1 4.17% 191.7
79 52 31-Jan 2.4 2.5 0.1 4.17% 194.1
80 145 1-Feb 2.4 2.5 0.1 4.17% 196.5
81 53 3-Feb 2.4 2.5 0.1 4.17% 198.9
82 41 4-Feb 2.4 2.5 0.1 4.17% 201.3
83 42 4-Feb 2.4 2.5 0.1 4.17% 203.7
84 54 4-Feb 2.4 2.5 0.1 4.17% 206.1
85 144 4-Feb 2.4 2.5 0.1 4.17% 208.5
86 43 5-Feb 2.4 2.5 0.1 4.17% 210.9
87 55 5-Feb 2.4 2.5 0.1 4.17% 213.3
88 143 7-Feb 2.4 2.5 0.1 4.17% 215.7
89 56 8-Feb 2.4 2.5 0.1 4.17% 218.1
90 45 11-Feb 2.4 2.5 0.1 4.17% 220.5
91 142 11-Feb 2.4 2.5 0.1 4.17% 222.9
92 44 12-Feb 2.4 2.5 0.1 4.17% 225.3
93 46 12-Feb 2.4 2.5 0.1 4.17% 227.7
94 57 12-Feb 2.4 2.5 0.1 4.17% 230.1
95 141 12-Feb 2.4 2.5 0.1 4.17% 232.5
96 50 13-Feb 2.4 2.5 0.1 4.17% 234.9
97 58 13-Feb 2.4 2.5 0.1 4.17% 237.3
98 140 15-Feb 2.4 2.5 0.1 4.17% 239.7
99 139 17-Feb 2.4 2.5 0.1 4.17% 242.1
100 49 18-Feb 2.4 2.5 0.1 4.17% 244.5
101 137 19-Feb 2.4 2.5 0.1 4.17% 246.9
102 138 19-Feb 2.4 2.5 0.1 4.17% 249.3
103 47 19-Feb 2.4 2.5 0.1 4.17% 251.7
104 59 19-Feb 2.4 2.5 0.1 4.17% 254.1
105 48 20-Feb 2.4 2.5 0.1 4.17% 256.5
106 136 20-Feb 2.4 2.5 0.1 4.17% 258.9
107 135 21-Feb 2.4 2.5 0.1 4.17% 261.3
108 60 21-Feb 2.4 2.5 0.1 4.17% 263.7
109 38 24-Feb 2.4 2.5 0.1 4.17% 266.1
110 134 24-Feb 2.4 2.5 0.1 4.17% 268.5
111 61 24-Feb 2.4 2.5 0.1 4.17% 270.9
112 133 25-Feb 2.4 2.5 0.1 4.17% 273.3
113 37 25-Feb 2.4 2.5 0.1 4.17% 275.7
114 62 26-Feb 2.4 2.5 0.1 4.17% 278.1
115 36 27-Feb 2.4 2.5 0.1 4.17% 280.5
116 132 28-Feb 2.4 2.5 0.1 4.17% 282.9
117 35 29-Feb 2.4 2.5 0.1 4.17% 285.3
118 63 2-Mar 2.4 2.5 0.1 4.17% 287.7
119 131 2-Mar 2.4 2.5 0.1 4.17% 290.1
120 130 3-Mar 2.4 2.5 0.1 4.17% 292.5
121 30 4-Mar 2.4 2.5 0.1 4.17% 294.9
122 29 5-Mar 2.4 2.5 0.1 4.17% 297.3
123 31 6-Mar 2.4 2.5 0.1 4.17% 299.7
124 32 11-Mar 2.4 2.5 0.1 4.17% 302.1
125 33 12-Mar 2.4 2.5 0.1 4.17% 304.5
126 34 14-Mar 2.4 2.5 0.1 4.17% 306.9
0 0.00%
0 0.00%
0 0.00%
0 0.00%
0 0.00%
0 0.00%
306.9 321.25 4.68%
ACUMULADOS
Volumen Sobre % Sobre
empleado volumen volumen
2.50 0.10 4.17%
5.00 0.20 4.17%
7.50 0.30 4.17%
10.00 0.40 4.17%
12.50 0.50 4.17%
15.00 0.60 4.17%
18.50 0.80 4.52%
22.00 1.00 4.76%
25.75 1.25 5.10%
28.25 1.35 5.02%
30.75 1.45 4.95%
33.25 1.55 4.89%
35.75 1.65 4.84%
39.25 2.75 7.53%
41.75 2.85 7.33%
44.25 2.95 7.14%
46.75 3.05 6.98%
49.25 3.15 6.83%
51.75 3.25 6.70%
54.25 3.35 6.58%
56.75 3.45 6.47%
59.75 4.05 7.27%
62.25 4.15 7.14%
64.75 4.25 7.02%
67.25 4.35 6.92%
70.50 4.40 6.66%
73.75 4.45 6.42%
76.25 4.55 6.35%
78.75 4.65 6.28%
81.25 4.75 6.21%
83.75 4.85 6.15%
86.25 4.95 6.09%
88.75 5.05 6.03%
91.25 5.15 5.98%
93.75 5.25 5.93%
96.25 5.35 5.89%
98.75 5.45 5.84%
101.25 5.55 5.80%
103.75 5.65 5.76%
106.25 5.75 5.72%
108.75 5.85 5.69%
111.25 5.95 5.65%
113.75 6.05 5.62%
116.25 6.15 5.59%
118.75 6.25 5.56%
121.25 6.35 5.53%
123.75 6.45 5.50%
126.25 6.55 5.47%
128.75 6.65 5.45%
131.25 6.75 5.42%
133.75 6.85 5.40%
136.25 6.95 5.38%
138.75 7.05 5.35%
141.25 7.15 5.33%
143.75 7.25 5.31%
146.25 7.35 5.29%
148.75 7.45 5.27%
151.25 7.55 5.25%
153.75 7.65 5.24%
156.25 7.75 5.22%
158.75 7.85 5.20%
161.25 7.95 5.19%
163.75 8.05 5.17%
166.25 8.15 5.15%
168.75 8.25 5.14%
171.25 8.35 5.13%
173.75 8.45 5.11%
176.25 8.55 5.10%
178.75 8.65 5.09%
181.25 8.75 5.07%
183.75 8.85 5.06%
186.25 8.95 5.05%
188.75 9.05 5.04%
191.25 9.15 5.02%
193.75 9.25 5.01%
196.25 9.35 5.00%
198.75 9.45 4.99%
201.25 9.55 4.98%
203.75 9.65 4.97%
206.25 9.75 4.96%
208.75 9.85 4.95%
211.25 9.95 4.94%
213.75 10.05 4.93%
216.25 10.15 4.92%
218.75 10.25 4.92%
221.25 10.35 4.91%
223.75 10.45 4.90%
226.25 10.55 4.89%
228.75 10.65 4.88%
231.25 10.75 4.88%
233.75 10.85 4.87%
236.25 10.95 4.86%
238.75 11.05 4.85%
241.25 11.15 4.85%
243.75 11.25 4.84%
246.25 11.35 4.83%
248.75 11.45 4.83%
251.25 11.55 4.82%
253.75 11.65 4.81%
256.25 11.75 4.81%
258.75 11.85 4.80%
261.25 11.95 4.79%
263.75 12.05 4.79%
266.25 12.15 4.78%
268.75 12.25 4.78%
271.25 12.35 4.77%
273.75 12.45 4.76%
276.25 12.55 4.76%
278.75 12.65 4.75%
281.25 12.75 4.75%
283.75 12.85 4.74%
286.25 12.95 4.74%
288.75 13.05 4.73%
291.25 13.15 4.73%
293.75 13.25 4.72%
296.25 13.35 4.72%
298.75 13.45 4.71%
301.25 13.55 4.71%
303.75 13.65 4.71%
306.25 13.75 4.70%
308.75 13.85 4.70%
311.25 13.95 4.69%
313.75 14.05 4.69%
316.25 14.15 4.68%
318.75 14.25 4.68%
321.25 14.35 4.68%
Observaciones

Se funde parte del pilote con el dado.

El pedido fue de 5,5 m3 se emplearon 0,5 m3 en solado.


El pedido fue de 5,5 m3 se emplearon 0,5 m3 en solado.

El pedido fue de 5,5 m3 se emplearon 0,5 m3 en solado.

El pedido fue de 4 m3 se emplearon 1,5 m3 en solado

El pedido fue de 4,75 m3 del cual se utilizó el restante para solado de vigas cabezal y foso en canal San Pablo.

De los pedidos para viga cabezal se emplearon 2 m3 para solado

El pedido fue de 4 m3, se emplearon 1,5 m3 en solado.

El pedido fue de 7,5 m3, se emplearon 2,5 m3 en solado.


El pedido fue de 7,5 m3, se emplearon 2,5 m3 en solado.

El pedido fue de 8 m3, se emplearon 3 m3 en solado.

El pedido fue de 3,5 m3, se emplearon 1 m3 para solado.

El pedido fue de 7,5 m3, se emplearon 2,5 m3 en solado.

El pedido fue de 7,5 m3 se emplearon 2,5 m3 en solado.

El pedido fue de 3 m3, se emplearon 0,5 m3 en solado


El pedido fue de 5 m3, se emplearon 2,5 m3 en solado

El pedido fue de 4 m3, se emplearon 1,5 m3 para atraques.


El pedido fue de 4 m3, se emplearon 1,5 m3 para solado.
El pedido fue de 3 m3, se emplearon 0,5 m3 en solado
El pedido fue de 4 m3, se emplearon 1,5 m3 para solado.
Identificación VACIADO FONDO
Consecutivo Longitud Volumen Volumen % Sobre
Inicio Fin Fecha
teórico empleado volumen
1 171 172 6 13-Nov 2.16 2.22 3%
2 173 174 6 13-Nov 2.16 2.22 3%
3 174 175 6 13-Nov 2.16 2.22 3%
4 177 178 6 13-Nov 2.16 2.22 3%
5 178 179 6 13-Nov 2.16 2.22 3%
6 266 267 6 14-Nov 2.16 2.22 3%
7 267 268 6 14-Nov 2.16 2.22 3%
8 268 269 6 14-Nov 2.16 2.22 3%
9 269 270 6 14-Nov 2.16 2.22 3%
10 270 271 6 14-Nov 3.1 3.2 3%
11 240 241 8 16-Nov 2.88 3 4%
12 241 242 8 16-Nov 2.88 3 4%
13 242 243 8 16-Nov 2.88 3 4%
14 172 173 6 19-Nov 2.16 2.25 4%
15 175 176 6 19-Nov 2.16 2.25 4%
16 176 177 6 19-Nov 2.16 2.25 4%
17 239' 239'' 8 19-Nov 2.88 3 4%
18 243 244 8 19-Nov 2.88 3 4%
19 237 238 4 20-Nov 1.44 1.5 4%
20 238 239' 4 20-Nov 1.44 1.5 4%
21 239'' 240 4 20-Nov 1.44 1.5 4%
22 214 215 8 7-Dec 2.88 3 4%
23 215 216 8 7-Dec 2.88 3 4%
24 216 217 8 12-Dec 2.88 3 4%
25 217 218 8 12-Dec 2.88 3 4%
26 186 187 6 13-Dec 2.16 2.25 4%
27 187 188 6 13-Dec 2.16 2.25 4%
28 188 189 6 13-Dec 2.16 2.25 4%
29 185 186 8 17-Dec 2.88 3 4%
30 179 180 6 18-Dec 2.16 2.25 4%
31 183 184 5.5 26-Dec 1.98 2 1%
32 184 185 8 26-Dec 2.88 3 4%
33 160 161 4 26-Dec 1.44 1.5 4%
34 161 162 4 26-Dec 1.44 1.5 4%
35 162 163 4 26-Dec 1.44 1.5 4%
36 221 222 8 27-Dec 2.88 3 4%
37 222 223 8 27-Dec 2.88 3 4%
38 223 224 8 27-Dec 2.88 3 4%
39 218 219 8 28-Dec 2.88 3 4%
40 219 220 8 28-Dec 2.88 3 4%
41 220 221 8 28-Dec 2.88 3 4%
42 156 157 6 3-Jan 2.16 2.25 4%
43 157 158 6 3-Jan 2.16 2.25 4%
44 158 159 4 3-Jan 1.44 1.5 4%
45 159 160 4 3-Jan 1.44 1.5 4%
46 155 156 6 7-Jan 2.16 2.25 4%
47 198 199 6 8-Jan 2.16 2.25 4%
48 199 200 6 9-Jan 2.16 2.25 4%
49 200 201 6 9-Jan 2.16 2.25 4%
50 201 202 8 13-Jan 2.88 3 4%
51 212 213 8 14-Jan 2.88 3 4%
52 213 214 8 14-Jan 2.88 3 4%
53 153 154 6 15-Jan 2.16 2.25 4%
54 154 155 6 15-Jan 2.16 2.25 4%
55 197 198 6 15-Jan 2.16 2.25 4%
56 202 203 8 16-Jan 2.88 3 4%
57 210 211 8 16-Jan 2.88 3 4%
58 211 212 8 16-Jan 2.88 3 4%
59 209 210 8 17-Jan 2.88 3 4%
60 151 152 6 18-Jan 2.16 2.25 4%
61 152 153 6 18-Jan 2.16 2.25 4%
62 203 204 8 20-Jan 2.88 3 4%
63 150 151 6 22-Jan 2.16 2.25 4%
64 204 205 8 22-Jan 2.88 3 4%
65 205 206 8 22-Jan 2.88 3 4%
66 208 209 8 22-Jan 2.88 3 4%
67 149 150 6 23-Jan 2.16 2.25 4%
68 206 207 8 25-Jan 2.88 3 4%
69 207 208 8 25-Jan 2.88 3 4%
70 148 149 6 30-Jan 2.16 2.25 4%
71 146 147 6 31-Jan 2.16 2.25 4%
72 147 148 6 31-Jan 2.16 2.25 4%
73 39 40 8 1-Feb 2.88 3 4%
74 51 52 8 3-Feb 2.88 3 4%
75 40 41 8 5-Feb 2.88 3 4%
76 52 53 8 5-Feb 2.88 3 4%
77 41 42 8 6-Feb 2.88 3 4%
78 145 146 6 6-Feb 2.16 2.25 4%
79 144 145 6 7-Feb 2.16 2.25 4%
80 42 43 8 7-Feb 2.88 3 4%
81 53 54 8 7-Feb 2.88 3 4%
82 54 55 8 8-Feb 2.88 3 4%
83 55 56 8 11-Feb 2.88 3 4%
84 143 144 6 11-Feb 2.16 2.25 4%
85 142 143 6 13-Feb 2.16 2.25 4%
86 44 45 8 14-Feb 2.88 3 4%
87 45 46 8 14-Feb 2.88 3 4%
88 141 142 6 14-Feb 2.16 2.25 4%
89 43 44 8 14-Feb 2.88 3 4%
90 56 57 8 15-Feb 2.88 3 4%
91 57 58 8 15-Feb 2.88 3 4%
92 50 51 8 17-Feb 2.88 3 4%
93 140 141 6 18-Feb 2.16 2.25 4%
94 139 140 6 19-Feb 2.16 2.25 4%
95 46 47 8 20-Feb 2.88 3 4%
96 49 50 8 20-Feb 2.88 3 4%
97 47 48 8 21-Feb 2.88 3 4%
98 48 49 8 21-Feb 2.88 3 4%
99 58 59 8 21-Feb 2.88 3 4%
100 137 138 6 21-Feb 2.16 3 39%
101 138 139 6 21-Feb 2.16 3 39%
102 136 137 6 22-Feb 2.16 2.25 4%
103 59 60 8 24-Feb 2.88 3 4%
104 135 136 6 25-Feb 2.16 2.25 4%
105 38 39 8 25-Feb 2.88 3 4%
106 60 61 8 25-Feb 2.88 3 4%
107 37 38 8 26-Feb 2.88 3 4%
108 134 135 6 26-Feb 2.16 2.25 4%
109 133 134 6 27-Feb 2.16 2.25 4%
110 36 37 8 28-Feb 2.88 3 4%
111 61 62 8 28-Feb 2.88 3 4%
112 35 36 8 2-Mar 2.88 3 4%
113 62 63 8 3-Mar 2.88 3 4%
114 131 132 6 4-Mar 2.16 2.25 4%
115 132 133 6 4-Mar 2.16 2.25 4%
116 130 131 6 5-Mar 2.16 2.25 4%
117 29 30 4 7-Mar 1.44 1.5 4%
118 32 33 8 13-Mar 2.88 3 4%
119 33 34 8 16-Mar 2.88 3 4%
120 34 35 8 16-Mar 2.88 3 4%
823.5 297.4 310.93 4.55%
VACIADO MUROS

Fecha Volumen Volumen % Sobre


teórico empleado volumen
18-Nov 1.73 1.84 6%
18-Nov 1.73 1.84 6%
18-Nov 1.73 1.86 8%
14-Nov 1.62 1.68 4%
14-Nov 1.62 1.68 4%
18-Nov 1.80 1.98 10%
18-Nov 1.80 1.98 10%
18-Nov 1.80 1.98 10%
18-Nov 1.80 1.98 10%
18-Nov 1.80 2 11%
23-Nov 2.40 2.55 6%
23-Nov 2.40 2.55 6%
23-Nov 2.40 2.6 8%
21-Nov 1.80 1.92 7%
21-Nov 1.80 1.92 7%
21-Nov 1.80 1.91 6%
26-Nov 2.40 2.55 6%
23-Nov 2.40 2.55 6%
26-Nov 1.20 1.23 2%
26-Nov 1.20 1.23 2%
26-Nov 1.20 1.24 3%
11-Dec 2.40 2.5 4%
11-Dec 2.40 2.5 4%
13-Dec 2.40 2.5 4%
13-Dec 2.40 2.5 4%
16-Dec 1.80 1.87 4%
16-Dec 1.80 1.87 4%
16-Dec 1.80 1.87 4%
19-Dec 2.40 2.5 4%
19-Dec 1.80 1.85 3%
28-Dec 1.65 1.7 3%
28-Dec 2.40 2.5 4%
28-Dec 1.20 1.25 4%
28-Dec 1.20 1.25 4%
28-Dec 1.20 1.25 4%
4-Jan 2.40 2.5 4%
4-Jan 2.40 2.5 4%
4-Jan 2.40 2.5 4%
3-Jan 2.40 2.5 4%
3-Jan 2.40 2.5 4%
3-Jan 2.40 2.5 4%
13-Jan 1.80 1.85 3%
10-Jan 1.80 1.85 3%
10-Jan 1.20 1.245 4%
10-Jan 1.20 1.245 4%
13-Jan 1.80 1.85 3%
10-Jan 1.80 1.85 3%
10-Jan 1.80 1.85 3%
10-Jan 1.80 1.85 3%
15-Jan 2.40 2.5 4%
15-Jan 2.40 2.5 4%
15-Jan 2.40 2.5 4%
17-Jan 1.80 1.85 3%
17-Jan 1.80 1.85 3%
16-Jan 1.80 1.85 3%
17-Jan 2.40 2.5 4%
17-Jan 2.40 2.5 4%
17-Jan 2.40 2.5 4%
18-Jan 2.40 2.5 4%
21-Jan 1.80 1.85 3%
21-Jan 1.80 1.85 3%
21-Jan 2.40 2.5 4%
24-Jan 1.80 1.85 3%
23-Jan 2.40 2.5 4%
23-Jan 2.40 2.5 4%
23-Jan 2.40 2.5 4%
24-Jan 1.80 1.85 3%
27-Jan 2.40 2.5 4%
27-Jan 2.40 2.5 4%
3-Feb 1.80 1.85 3%
4-Feb 1.80 1.85 3%
3-Feb 1.80 1.85 3%
3-Feb 2.40 2.5 4%
4-Feb 2.40 2.5 4%
6-Feb 2.40 2.5 4%
6-Feb 2.40 2.5 4%
7-Feb 2.40 2.5 4%
7-Feb 1.80 1.85 3%
8-Feb 1.80 1.85 3%
8-Feb 2.40 2.5 4%
8-Feb 2.40 2.5 4%
11-Feb 2.40 2.5 4%
12-Feb 2.40 2.5 4%
12-Feb 1.80 1.85 3%
14-Feb 1.80 1.85 3%
15-Feb 2.40 2.5 4%
15-Feb 2.40 2.5 4%
15-Feb 1.80 1.85 3%
15-Feb 2.40 2.5 4%
17-Feb 2.40 2.5 4%
17-Feb 2.40 2.5 4%
18-Feb 2.40 2.5 4%
19-Feb 1.80 1.85 3%
20-Feb 1.80 1.85 3%
21-Feb 2.40 2.5 4%
21-Feb 2.40 2.5 4%
22-Feb 2.40 2.5 4%
22-Feb 2.40 2.5 4%
24-Feb 2.40 2.5 4%
22-Feb 1.80 1.85 3%
22-Feb 1.80 1.85 3%
24-Feb 1.80 1.85 3%
25-Feb 2.40 2.5 4%
26-Feb 1.80 1.85 3%
26-Feb 2.40 2.5 4%
26-Feb 2.40 2.5 4%
27-Feb 2.40 2.5 4%
27-Feb 1.80 1.85 3%
28-Feb 1.80 1.85 3%
29-Feb 2.40 2.5 4%
29-Feb 2.40 2.5 4%
3-Mar 2.40 2.5 4%
4-Mar 2.40 2.5 4%
6-Mar 1.80 1.85 3%
6-Mar 1.80 1.85 3%
7-Mar 1.80 1.85 3%
0.00 0.25 0%
14-Mar 2.40 2.5 4%
17-Mar 2.40 2.5 4%
17-Mar 2.40 2.5 4%
245.274 255.92 4.34%
2
542.674 564.85 4.09%
OBSERVACIONES

La cantidad requerida para muros era de 4,5 m, pero debido a que


pueden quedar entre 0,2 y 0,3 m3 entre la bomba y la tubería, se
solicitaron 5 m3 (Cemex no despacha 4,8 m3)
Los muros se fundieron con retroexcavadora
Los muros se fundieron con retroexcavadora

La cantidad requerida para muros era de 8,5 m, pero debido a que


pueden quedar entre 0,2 y 0,3 m3 entre la bomba y la tubería, se
solicitaron 9 m3 (Cemex no despacha 8,8 m3)

Se vacia bordillos de los ejes 171 a 177 con el pedido de muros.

El pedido se realizó de 6 m3, se emplearon 1,4 m3 para solado.


Se vacia bordillos de los ejes 171 a 177 con el pedido de muros.

El pedido se realizó de 6 m3, se emplearon 1,4 m3 para solado.

El pedido de muros fue de 5,5 m3, se emplearon 1,5 m3 para


solado.

El pedido de muros fue de 5,5 m3 se empleó 1 m3 para solado.

El pedido fue de 6 m3, se emplearon 1,14 m3 para solado de V.U


185-186

El pedido para fondo fue de 4 m3, se emplearon 0,5 m3 en solado. En muro se pidieron 5 m3, de los cuales 1,4 m3 se emplear
El pedido para fondo fue de 3 m3 se emplearon 0,5 m3 en solado.

El pedido de muros fue de 4,5 m3 se emplearon 0,8 m3 en solado.

El pedido de fondo fue de 5,75 m3 de los cuales se emplearon 0,65


m3 en solado. El pedido de muros fue de 3,75 m3, se emplearon 0,6
m3 en solados.

El pedido de muros fue de 7,5 m3, se emplearon 0,5 m3 en solado.

El pedido para fondo fue de 9 m3, se emplearon 0,86 m3 para


solado. El pedido para muros 157-160 fue de 5,5 m3 se emplearon
3,9 m3 en las vigas u y 1,6 en solados.
El pedido para fondo fue de 9 m3, se emplearon 0,86 m3 para
solado. El pedido para muros 157-160 fue de 5,5 m3 se emplearon
3,9 m3 en las vigas u y 1,6 en solados.

El pedido fue de 7,75 m3, de los cuales 5 m3 fueron para vigas cabezal, 2,45 m3 para fondo de viga u y 0,3 m3 para bordillo de
El pedido para fondo fue de 6 m3, se emplearon 2,5 en la viga cabezal 202, 2,45 m3 en la viga u y el resto en el solado de la vig
El pedido de fondo fueron 7,5 m3, de los cuales 2,5 se emplearon
en la viga cabezal 213. El pedido de muros del 198-201 fue de 5,5
m3 se emplearon 4,85 y 0,65 en solados.
El pedido para muro fue de 2,5 m3, se emplearon 0,5 m3 en solado.
El pedido para fondo fue de 9 m3, se emplearon 2 m3 en solados. El
pedido para muros fue de 5 m3, se emplea 1 m3 en solados.
El pedido para fondo fue de 6 m3 de los cuales 1 m3 se emplea en
solado. El pedido de muro fue de 6 m3, se emplearon 2,8 m3 en
solado.

Se emplearon 0,7 m3 en solado en la vaciada de fondo y 0,5 para solado en el vaciado del muro.

En muros se solicitan 3,5 de los cuales 1,5 m3 se emplea en solado.


El pedido de muros fue de 4,25 de los cuales se emplearon 1,05 m3
en solado.
El pedido para fondo fue de 4 m3, se emplearon 0,5 m3 en solado. El pedido de muros fue de 6 m3 de los cuales 4 m3 se empl

El pedido para fondos era de 14 m3, se empleó 1 m3 en solado.


Para las vigas 204-206 y 208-9 se pidieron 7,5 m3 de los cuales 1,5
m3 se emplearon en solado.

Para los muros de las v.u. 149-151 el pedido fue de 4 m3 se usaron 0,8 m3 en solado.

Del pedido de muros se empleó 1 m3 en solados.

El pedido para muros 147-149 y 39-40 fue de 7 m3, se emplearon 2,05 m3 en solados.

El pedido fue de 5,25 m3, se emplearon 0,25 m3 en solado.

El pedido fue de 4,5 m3 se empleó 1 m3 en solado


El pedido fue de 4 m3 para fondo, se emplearon 0,5 m3 para solado. En el vaciado de 51-52 y 146-147 se pidieron 5,5 m3, de l

El pedido para fondo fue de 8 m3, se empleó 1 m3 en solado.

El pedido para fondo fue de 7 m3, se empleó 1 m3 en solado. El de


muros fue de 6,5 m3 se emplearon 2,9 m3 en solado.

El pedido para muros fue de 8 m3, de los cuales 2,4 m3 se


emplearon para solado.

El pedido para muros fue de 2,5 m3, se emplearon 0,5 m3 en solado.


El pedido para fondos fue de 7 m3, se empleó 1 m3 en solado. El
pedido para muros fue de 6 m3 y se emplearon 2,4 m3 en solado.
El pedido fue de 5 m3, se emplearon 2,5 m3 en solado.

Para el pedido de fondos de vigas 43-46, 141-142 y muro de 142-


143, se programaron 19,5 m3, de los cuales 4,9 m3 fueron de
solado.
Para el pedido de fondos de vigas 43-46, 141-142 y muro de 142-
143, se programaron 19,5 m3, de los cuales 4,9 m3 fueron de
solado.

Del pedido para fondos se emplearon 2,4 m3 en solado. El pedido


para muros fue de 5 m3 se empleó 1 m3 para solado.
El pedido para fondo fue de 4 m3, se emplearon 0,5 m3 para solado. El de muro fue de 8 m3 (VC49, fodo 140-141 y uro 50-51)
El pedido para muro 140-141 y fondo 139-140 fue de 5,5 m3 se emplearon 1,4 m3 para solado.
El pedido de concreto para el 20 de febrero fue de 17,75 m3 sin embargo se emplearon 4,15 m3 em solado.

Del pedido se emplean 2 m3 para solado.

Del pedido se emplearon 1,9 m3 en solados.

El pedido fue de 5,5 m3 para viga cabezal y el muro, se emplearon 1 m3 en solado.

Del pedido se emplearon 1,9 m3 en solados.

El pedido fue de 5,75 m3 para viga cabezal y muro, se emplearon 1,65 m3 en solado.
El pedido fue de 7 m3, para viga cabezal y fondo, se emplearon 1 m3 en solados.

El pedido para fondos fue de 12,5 m3, de los cuales 3 m3 se


emplearon en solados.

El pedido total del día fue de 19,75 m3 y se emplearon 3,65 m3 en


solados.
El pedido total del día para vaciado de fondo fue de 12,75 m3, se emplearon 4,15 m3 en solados y atraques de tubería. El tota
El pedido fue de 8 m3, se emplearn 2,5 m3 en vc35, 4 m3 en los
muros y 1,5 m3 en solados.
El pedido fue de 4 m3, se emplearon 0,5 m3 en solado.
El pedido para fondo 62-63 y muro 35-36 fue de 7,5 m3. De los cuales se emplearon 2 m3 para solado y atraques de tubería. E

ue de 6,5 m3, se emplearon 1,5 m3 en solado. El pedido de muros fue de 4 m3, se emplearon 0,8 m3 en solado.

El pedido de fondo fue de 3 m3, se emplearon 0,5 m3 en atraques de tubería. El pedido muro fue de 3 m3, se emplearon 1,4 m
El pedido de fondo fue de 2,5 m3 se emplearon 0,75 m3 en solado.
El pedido de fondo fue de 4 m3, se emplearon 0,5 m3 en solado. El pedido de muro fue de 3 m3, se emplearon 1 m3 en solado
El pedido de fondo fue de 8 m3, se emplearon 1 m3 en atraques de
tubería, el pedido de muros fue de 5,75 m3 se emplearon 1,75 m3
en atraques de tubería.
cuales 1,4 m3 se emplearon en solado.
u y 0,3 m3 para bordillo de vigas cabezal y solado. El pedido de muros para 155-157 fue de 4 m3 de los cuales 0,7 m3 se emplearon en sola
resto en el solado de la viga cabezal 197.

de los cuales 4 m3 se emplearon en solado.

47 se pidieron 5,5 m3, de los cuales 1,9 m3 se emplearon en solado.


fodo 140-141 y uro 50-51), se empleó 1 m3 en solado.

traques de tubería. El total de pedido para vaciados del día fue de 15,5 m3, se emplearon 4,4 m3 en solados.

do y atraques de tubería. El pedido de muro fue de 3 m3, se emplearon 0,5 m3 en solado.

e 3 m3, se emplearon 1,4 m3 en solado.

emplearon 1 m3 en solado.
m3 se emplearon en solado.
Identificación INSTALACIÓN DE ARENA INSTALACIÓN DE TUBERÍA
Consecutivo Longitud
Inicio Fin Fecha inicio Fecha fin Fecha inicio

1 266 271 30 5-Feb 20-Feb 5-Feb


2 239'' 244 38 30-Jan 22-Feb 1-Feb
3 197 204 43 24-Feb 26-Feb 24-Feb
4 171 180 44 24-Feb 26-Feb 24-Feb
5 204 208 43 27-Feb 28-Feb 27-Feb
6 183 185 9 27-Feb 28-Feb 27-Feb
7 208 212 42 28-Feb 29-Feb 28-Feb
8 212 217 36 29-Feb 2-Mar 29-Mar
9 157 162 26 2-Mar 3-Mar 2-Mar
10 53 62 70 3-Mar 4-Mar 3-Apr
11 47 53 42 4-Mar 6-Mar 4-Mar
12 150 157 42 6-Mar 7-Mar 6-Mar
13 42 47 38 7-Mar 9-Mar 7-Mar
14 37 42 42 9-Mar 10-Mar 9-Mar
15 143 150 42 9-Mar 10-Mar 9-Mar
16 35 37 18 10-Mar 11-Mar 10-Mar
17 137 143 36 10-Mar 11-Mar 10-Mar
18 133 137 30 11-Mar 12-Mar 11-Mar
19 217 220 24 17-Mar 18-Mar 17-Mar
20 32 35 24 18-Mar 19-Mar 18-Mar
719
NSTALACIÓN DE TUBERÍA VACIADO DE TAPAS

Fecha fin Fecha Volumen Volumen % Sobre


teórico empleado volumen
19-Feb 20-Feb 5.48 5.75 5%
21-Feb 22-Feb 6.16 6.4 4%
26-Feb 27-Feb 6.97 7.25 4%
26-Feb 27-Feb 7.13 7.5 5%
28-Feb 28-Feb 6.97 7.25 4%
28-Feb 28-Feb 1.46 1.5 3%
29-Feb 29-Feb 6.80 7 3%
2-Mar 2-Feb 5.83 6 3%
3-Mar 3-Mar 4.21 4.4 4%
4-Mar 4-Mar 11.34 11.8 4%
6-Mar 6-Mar 6.80 7 3%
7-Mar 7-Mar 6.80 7 3%
9-Mar 9-Mar 6.16 6.4 4%
10-Mar 10-Mar 6.80 7 3%
10-Mar 10-Mar 6.80 7 3%
11-Mar 11-Mar 2.92 3 3%
11-Mar 11-Mar 5.83 6 3%
12-Mar 12-Mar 4.86 5 3%
18-Mar 18-Mar 3.89 4 3%
19-Mar 19-Mar 3.89 4 3%
117.10 121.25 3.54%
OBSERVACIONES

El pedido fue de 7 m3, se emplearon 0,6 m3 en atraques.

El pedido fue de 7,5 m3, se emplearon 0,25 m3 en atraques de tubería para el tramo 208-212
El pedido fue de 4 m3, se emplearon 2,5 m3 en atraques de tubería para el tramo 208-212 y para fundir los muros faltantes de

El pedido fue de 7 m3, se emplearon 1 m3 en atraques de tubería del tramo 217-224


El pedido fue de 5 m3, se emplearon 0,6 m3 en atraques de tubería
El pedido fue de 14 m3, se emplearon 2,2 m3 en atraques de tubería.
El pedido fue de 8 m3, se usó 1 m3 en atraques de tubería
El pedido fue de 7,5 m3, se usó 0,5 m3 en atraques de tubería
El pedido fue de 7,5 m3, se usó 1,1 m3 en atraques de tubería
El pedido fue de 8 m3, se usó 0,5 m3 en atraques de tubería y 0,5 en solado.
El pedido fue de 7,5 m3, se usó 0,5 m3 en atraques de tubería
El pedido fue de 5,5 m3, se emplearon 1 m3 en atraques de tubería y 1,5 m3 para completar el solado de la caja 1.
El pedido fue de 7,5 m3, se usó 1,5 m3 en atraques de tubería
El pedido fue de 6 m3, se emplearon 1 m3 en atraques de tubería y solado de link box.
El pedido fue de 5 m3, se empleó 1 m3 en atraques de tubería
El pedido fue de 5 m3, se empleó 1 m3 en atraques de tubería
los muros faltantes de la caja de empalme 2.