DAFTAR SATUAN UPAH DAN BAHAN

HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
TENAGA
1 Pekerja hari 103,000.00
2 Tukang Ledeng hari 109,000.00
3 Kepala Tukang hari 147,000.00
4 Mandor hari 116,000.00

PVC AW
1 Pipa PVC AW 1/2” m1 7,000.00
2 Pipa PVC AW 3/4” m1 10,000.00
3 Pipa PVC AW 1” m1 11,000.00
4 Pipa PVC AW 1 1/4” m1 16,200.00
5 Pipa PVC AW 1 1/2” m1 18,600.00
6 Pipa PVC AW 2” m1 18,000.00
7 Pipa PVC AW 2 1/2” m1 34,725.00
8 Pipa PVC AW 3” m1 31,000.00
9 Pipa PVC AW 4” m1 50,000.00
10 Pipa PVC AW 6" m1 180,050.00
11 Pipa PVC AW 8" m1 302,150.00
12 Tee PVC AW Ø 150 mm m1 260,900.00
13 Elbow PVC AW Ø 150 mm m1 205,400.00

PVC D
1 Pipa PVC D 1 1/4” m1 10,175.00
2 Pipa PVC D 1 1/2” m1 11,500.00
3 Pipa PVC D 2” m1 14,750.00
4 Pipa PVC D 2 1/2" m1 19,925.00
5 Pipa PVC D 3" m1 26,450.00
6 Pipa PVC D 4” m1 41,600.00

PPR WAVIN TIGRIS


1 Pipa PPR PN10 4" m1 295,875.25
2 Pipa PPR PN10 3" m1 199,226.50
3 Pipa PPR PN10 2,5" m1 138,030.75
4 Pipa PPR PN10 2" m1 98,645.25
5 Pipa PPR PN10 1 1/2" m1 62,315.00
6 Pipa PPR PN10 ø 1 1/4" m1 40,172.00
7 Pipa PPR PN10 ø 1" m1 25,349.50
8 Pipa PPR PN10 ø 3/4" m1 15,760.25
9 Pipa PPR PN10 ø 1/2" m1 12,039.50
10 Pipa PPR PN20 4" m1 489,324.00
11 Pipa PPR PN20 3" m1 327,426.00
12 Pipa PPR PN20 2,5" m1 227,812.75
13 Pipa PPR PN20 2" m1 160,899.75
14 Pipa PPR PN20 1 1/2" m1 101,549.25
15 Pipa PPR PN20 ø 1 1/4" m1 64,977.00
16 Pipa PPR PN20 ø 1" m1 42,138.25
17 Pipa PPR PN20 ø 3/4" m1 25,621.75
18 Pipa PPR PN20 ø 1/2" m1 16,698.00
PIPA GIP MEDIUM
1 Pipa GIP MEDIUM 6" m1 655,500.00
2 Pipa GIP MEDIUM 4" m1 409,166.67
3 Pipa GIP MEDIUM 3" m1 282,666.67
4 Pipa GIP MEDIUM 2,5" m1 218,833.33
5 Pipa GIP MEDIUM 2" m1 171,500.00
6 Pipa GIP MEDIUM 1 1/2" m1 125,666.67
7 Pipa GIP MEDIUM ø 1 1/4" m1 109,333.33
8 Pipa GIP MEDIUM ø 1" m1 82,833.33
9 Pipa GIP MEDIUM ø 3/4" m1 54,000.00
10 Pipa GIP MEDIUM ø 1/2" m1 42,000.00
11 Tee GIP Ø 150 mm 6" bh 735,600.00
12 Elbow GIP Medium Ø 150 mm 6" bh 269,000.00

PIPA BS SCH 40
1 Pipa BS SCH 40 8" m1 692,083.33
2 Pipa BS SCH 40 6" m1 685,166.67
3 Pipa BS SCH 40 5" m1 530,166.67
4 Pipa BS SCH 40 4" m1 391,833.33
5 Pipa BS SCH 40 3" m1 312,541.67
6 Pipa BS SCH 40 2,5" m1 211,166.67
7 Pipa BS SCH 40 2" m1 132,500.00
8 Pipa BS SCH 40 1 1/2" m1 99,166.67
9 Pipa BS SCH 40 ø 1 1/4" m1 83,500.00
10 Pipa BS SCH 40 ø 1" m1 61,166.67
11 Pipa BS SCH 40 ø 3/4" m1 41,333.33
12 Pipa BS SCH 40 ø 1/2" m1 32,541.67
13 Tee BS SCH 40 Ø 125 mm bh 635,000.00
14 Elbow BS SCH40 Ø 125 mm bh 203,000.00
15 Tee BS SCH 40 Ø 150 mm bh 780,000.00
16 Elbow BS SCH 40 Ø 150 mm 6" bh 265,000.00

PIPA LAIN
1 Pipa PVC Conduit HIC dia 20 mm m1 5,000.00
2 Pipa Metal Conduit HIC dia 25 mm m1 45,000.00
3 Pipa Tembaga 1/4" m1 14,500.00
4 Pipa Tembaga 3/8" m1 22,400.00
5 Pipa Tembaga 1/2" m1 33,000.00
6 Pipa Tembaga 5/8" m1 50,000.00
7 Pipa Tembaga 3/4" m1 78,000.00
8 Pipa Tembaga 1" m1 95,000.00
9 Pipa Tembaga 1 1/4" m1 112,000.00
10 Pipa Tembaga 1 1/2" m1 125,000.00
11 Pipa Tembaga 2" m1 185,000.00
12 Pipa Tembaga 2 1/2" m1 225,000.00
13 Pipa Tembaga 3" m1 245,000.00
6 Valve Ø 4" bh 2,454,000.00
7 Valve Ø 6" bh 4,737,000.00

ISOLASI PIPA
1 Isolasi Pipa Refrigerant 1/4" m1 12,000.00
2 Isolasi Pipa Refrigerant 3/8" m1 13,000.00
3 Isolasi Pipa Refrigerant 1/2" m1 18,000.00
4 Isolasi Pipa Tembaga m1 28,300.00

KABEL & PENDUKUNG


1 Kabel NYM 3x2.5 sqmm m1 13,000.00
2 Kabel NYFGBY 3x2.5 mm2 m1 37,000.00
3 Kabel NYY 5x2.5 sqmm m1 23,000.00
4 Kabel ITC 2X0.6 m1 4,000.00
5 Kabel NYMHY 2x1.5 mm2 m1 9,800.00
6 Kabel Coaxial RG 6 m1 7,000.00
7 Kabel NYA 2x1.5 mm2 m1 7,000.00
8 Kabel UTP Cat 5e m1 7,500.00
9 Kabel UTP Cat 6 m1 8,500.00
10 Kabel UTP ITC 2x0.6 mm2 m1 4,000.00
11 Kabel STP AWG #18 & NYA 2x1.5 mm2 m1 18,050.00
12 T-Duce 20 bh 5,700.00
13 Sock 20 bh 800.00
14 Flexible 20 m1 3,500.00
15 T-Duce 25 bh 50,000.00
16 Sock 25 bh 25,000.00
17 Flexible 25 m1 3,500.00
18 Klem plus Fischer S6 bh 800.00
19 Pasir, Urug plus gali m1 10,000.00

ELEKTRICAL
1 Box Panel bh 1,500,000.00
2 Box Panel bh 500,000.00
3 Box Panel (TYPE OUTDOOR IP 65) bh 850,000.00
4 MCCB 3 Phase 400-500 A 25 Ka c/w Proteksi Motor Micrologic 2 bh 14,036,000.00
5 MCCB 3 Phase 63 A 18 kA bh 980,100.00
6 MCCB 3 Phase 40 A 18 kA bh 980,100.00
7 MCCB 3 Phase 30 A 18 kA bh 980,100.00
8 MCCB 3 Phase 25 A 18 kA bh 980,100.00
9 MCCB 3 Phase 20 A 18 kA bh 980,100.00
10 MCCB 3 Phase 10A 18 kA bh 980,100.00
11 MCCB 3 Phase 250-300A 25 kA c/w Proteksi Motor Micrologic 2 bh 10,961,500.00
12 MCCB 3 Phase 63 A 16 kA bh 980,100.00
13 MCCB 3 Phase 40 A 16 kA bh 980,100.00
14 MCCB 3 Phase 30 A 16 kA bh 980,100.00
15 MCCB 3 Phase 25 A 16 kA bh 980,100.00
16 MCCB 3 Phase 10 A 16 kA bh 980,100.00
17 MCCB 3 Phase 75A 16 kA c/w Proteksi Motor Micrologic bh 10,327,900.00
18 MCB 3 Phase 40 A 16 kA bh 980,100.00
19 MCB 3 Phase 16 A 16 kA bh 980,100.00
20 MCCB 3 Phase 450-500A 25 kA c/w Proteksi Motor Micrologic bh 6,671,500.00
21 MCCB 3 Phase 250A 16 Ka bh 1,685,200.00
22 MCCB 3 Phase 150A 16 Ka bh 1,685,200.00
23 MCCB 3 Phase 400-450A 25 kA c/w Proteksi Motor Micrologic bh 6,671,500.00
24 MCB 1 Phase 16 A 6 kA bh 93,610.00
25 MCB 1 Phase 10 A 6 kA bh 93,610.00
26 MCB 1 Phase 16 A 6 kA bh 93,610.00
27 MCB 1 Phase 16 A 16 Ka bh 232,870.00
28 MCB 1 Phase 6 A 6 kA bh 93,610.00
29 CONTACTOR 3PH 16 A bh 164,000.00
30 CONTACTOR 3PH 32 A bh 325,000.00
31 WLC bh 450,000.00
32 Switch Auto Manual bh 91,200.00
33 Switch On-Off bh 91,200.00
34 ELCB 2 Phase 10 A 30mA bh 577,500.00
35 ELCB 2 Phase 40 A 30mA bh 748,550.00
36 ELCB 2 Phase 63 A 30mA bh 748,550.00
37 ELCB 2 Phase 25 A 30mA bh 748,550.00
38 Pilot Lamp bh 22,500.00
39 Fuse bh 25,000.00
40 Voltage Selector bh 70,500.00
41 Voltmeter bh 250,000.00
42 Amperemeter bh 288,000.00
43 Bus bar lot 450,000.00
44 Terminal Blok lot 500,000.00
45 Wiring & Accessories lot 150,000.00

SEWA ALAT
1 handle crane 2 T hari 25,000.00
2 Peralatan potong pipa T2/mekanik / cilinder saw hari 100,000.00
3 watt hari 150,000.00
4 Submersible 3m3/h hari 75,000.00

LAIN-LAIN
1 Besi Siku 5cm x 5cm x 6m m1 75,666.67
2 Besi polos 8 mm m1 42,000.00
3 Pasir pasang m3 165,000.00
4 Pasir urug m3 157,400.00
5 Waterheater 15l bh 1,832,600.00
6 Kran Taman bh 325,000.00
7 Vent Cap diameter 2" bh 45,000.00
8 Roofdrain (cast iron tipe meshroom) 4" bh 121,000.00
9 Pressure Tank 200Lt bh 10,625,000.00
10 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 8,120,000.00
11 Unit AC Wall Split 1/2 PK unit 3,564,000.00
12 Unit AC Wall Split 3/4 PK unit 3,707,000.00
13 Unit AC Wall Split 1 PK unit 3,872,000.00
14 Unit AC Wall Split 1 1/2 PK unit 4,840,000.00
15 Unit AC Wall Split 2 PK unit 6,413,000.00
16 Unit AC Wall Split 2 1/2 PK unit 9,108,000.00
17 Unit AC Ceiling Cassete 2 1/2 PK unit 18,491,000.00
18 Unit AC Ceiling Cassete 3 PK unit 24,002,000.00
19 Unit AC Ceiling Cassete 4 PK unit 31,999,000.00
20 Unit AC Ceiling Cassete 5 PK unit 37,488,000.00
21 Unit AC Ceiling Cassete 6 PK unit 46,387,000.00
22 Unit AC Split Duct 9.000 BTUH unit 7,216,000.00
23 Unit AC Split Duct 13.000 BTUH unit 8,240,980.00
24 Unit AC Split Duct 18.000 BTUH unit 12,089,000.00
25 Unit AC Split Duct 21.000 BTUH unit 15,906,000.00
26 Unit AC Split Duct 26.000 BTUH unit 22,200,000.00
27 Unit AC Split Duct 48.000 BTUH unit 37,345,000.00
28 Unit AC Ceiling Duct middle static 54600 Btuh unit 26,609,000.00
29 Unit AC Outdoor 54.600 Btuh VRV unit 81,664,000.00
30 Unit AC Split Wall 7500 Btuh INDOOR VRV unit 11,814,000.00
31 Unit AC Split Wall 9600 Btuh INDOOR VRV unit 12,309,000.00
32 Unit AC Ceiling Cassete 12300 Btuh INDOOR VRV unit 12,804,000.00
33 Unit AC Ceiling Cassete 15400 Btuh INDOOR VRV unit 13,640,000.00
34 Unit AC Ceiling Cassete 19100 Btuh INDOOR VRV unit 15,972,000.00
35 Unit AC Ceiling Cassete 24200 Btuh INDOOR VRV unit 16,797,000.00
36 Unit AC Ceiling Cassete 30700 Btuh INDOOR VRV unit 24,871,000.00
37 Unit AC Ceiling Cassete 38200 Btuh INDOOR VRV unit 25,036,000.00
38 Unit AC Ceiling Duct 24.200 BTUH INDOOR VRV unit 16,797,000.00
39 Unit AC Ceiling Duct 54.600 BTUH INDOOR VRV unit 25,278,000.00
40 Wall Fan 70 Watt, 63 m3/m, 16" c/w Switch unit 650,000.00
41 Unit AC Outdoor 324.000 Btuh VRV unit 332,640,000.00
42 Unit AC Outdoor 341.000 Btuh VRV unit 339,966,000.00
43 Exhaust Toilet Fan Type Wall 50 cfm, 30 cm unit 705,000.00
44 Head Pendant Sprinkler unit 56,500.00
45 Indor Hydran BOX unit 4,504,700.00
46 Kabel BC 2.5 mm2 m 4,125.00
47 Kabel BC 4 mm2 m 5,700.00
48 Kabel BC 6 mm2 m 7,050.00
49 Kabel BC 10 mm2 m 11,400.00
50 Kabel BC 16 mm2 m 16,650.00
51 Kabel BC 25 mm2 m 39,500.00
52 Kabel BC 35 mm2 m 30,450.00
53 Kabel BC 50 mm2 m 36,700.00
54 Kabel BC 70 mm2 m 53,600.00
55 Kabel BC 95 mm2 m 98,750.00
56 Kabel BC 120 mm2 m 113,500.00
57 Kabel BC 150 mm2 m 173,000.00
58 Kabel BC 185 mm2 m 254,800.00
59 Kabel BC 240 mm2 m 295,000.00
60 Kabel NYY 4 x 2.5 mm² m 40,000.00
61 Kabel NYY 4 x 4 mm² m 58,000.00
62 Kabel NYY 4 x 6 mm² m 72,000.00
63 Kabel NYY 4 x 10 mm² m 98,000.00
64 Kabel NYY 4 x 16 mm² m 111,000.00
65 Kabel NYY 4 x 25 mm² m 197,500.00
66 Kabel NYY 4 x 35 mm² m 231,000.00
67 Kabel NYY 4 x 50 mm² m 314,000.00
68 Kabel NYY 4 x 70 mm² m 444,000.00
69 Kabel NYY 4 x 95 mm² m 610,000.00
70 Kabel NYY 4 x 120 mm² m 764,000.00
71 Kabel NYY 4 x 150 mm² m 940,000.00
72 Kabel NYY 4 x 185 mm² m 1,169,000.00
73 Kabel NYY 4 x 240 mm² m 1,530,000.00
74 Kabel NYY 4 x 300 mm² m 1,903,000.00
75 Kabel NYY 5 x 2.5 mm² m 50,000.00
76 Kabel NYA 1 x 50 mm² m 38,000.00
77 Kabel NYA 1 x 70 mm² m 54,000.00
78 Kabel NYFGBY 4 x 6 mm² m 55,000.00
79 Kabel NYFGBY 4 x 16 mm² m 108,375.00
80 Kabel FRC 4 x 4 mm² m 63,000.00
80 Kabel FRC 4 x 16 mm² m 226,500.00
81 Kabel FRC 4 x 95 mm² m 650,000.00
82 Tray 500 x 100 mm m 460,000.00
82 Tray 300 x 100 mm m 240,000.00
83 Tray 200 x 100 mm m 192,000.00
84 Tray 100 x 100 mm m 168,000.00
85 Support unit 10,500.00
86 Kabel Backbone Data UTP Cat6 m 5,566.67
87 Coaxial cable RG 11 m 6,800.00
88 NYMHY 3x2.5 mm² m 6,200.00
89 Conduit 20mm btg 10,500.00
90 Kabel Ladder W=400 H=100 m 10,500.00
91 Kabel Ladder W=600 H=100 m 10,500.00
92 Kabel Ladder W=800 H=100 m 10,500.00
93 Kabel Ladder W=1000 H=100 m 10,500.00
94 Kabel N2XSY 3 x 95 mm² m 497,000.00
95 Kabel N2XSEBY 3 x 120 mm² m 548,000.00
96 Gate Valve 1" bh 180,000.00
97 Gate Valve 1 1/4" bh 201,000.00
98 Gate Valve 1 1/2" bh 355,000.00
99 Gate Valve 2" bh 702,000.00
100 Gate Valve 2 1/2" bh 1,375,000.00
101 Gate Valve 3" bh 1,641,000.00
102 Gate Valve 4" bh 2,490,000.00
103 Gate Valve 5" bh 3,680,000.00
104 Gate Valve 6" bh 4,670,000.00
105 Strainer 2" bh 425,800.00
106 Strainer 2 1/2" bh 935,100.00
107 Strainer 3" bh 1,590,000.00
108 Strainer 6" bh 4,410,000.00
109 Flexible Joint 1 1/2" bh 625,000.00
110 Flexible Joint 2" bh 748,000.00
111 Flexible Joint 2 1/2" bh 975,000.00
112 Flexible Joint 3" bh 1,425,000.00
113 Flexible Joint 5" bh 2,500,000.00
114 Flexible Joint 6" bh 3,075,000.00
115 Check Valve 1 1/2" bh 1,860,000.00
116 Check Valve 2" bh 2,170,000.00
117 Check Valve 2 1/2" bh 3,725,000.00
118 Check Valve 5" bh 7,045,000.00
119 Float Valve 2" bh 2,145,000.00
120 Foot Valve 3" bh 3,250,000.00
121 Safety Valve 4" bh 7,885,000.00
122 Clean Out diameter 4" bh 255,000.00
123 Clean Out diameter 6" bh 315,000.00

PEKERJAAN MEKANIKAL:
PEKERJAAN DEEP WELL
Pompa Deep Well 35,000,000.00
Screen Stainless Steel 950,000.00
Pengeboran termasuk pengisian kerikil 29,160,000.00
Pipa instalasi dari pompa s/d water meter dg pipa Galvanis Medium 135,000.00
Gate Valve 700,000.00
Bak kontrol ukuran (60 x 80) cm dengan tutup chequer plate 750,000.00
WLC u/Sumur dalam + Pengkabelan 850,000.00
Biaya Geolistrik 20,000,000.00
Biaya perijinan termasuk water meter 65 mm 7,000,000.00
Testing Commissioning 5,000,000.00

PEKERJAAN SISTEM AIR BERSIH


Pompa Transfer ke Rooftank 13,500,000.00
Pompa Filter 11,760,000.00
Carbon Filter 45,000,000.00
Sand Filter 65,000,000.00
Instalasi pipa sirkulasi air bersih ke unit water filter 6,500,000.00
Material Bantu 7,300,000.00
Testing & Commissioning (Filter & Transfer) 2,000,000.00
Pompa Booster 25,000,000.00
Rooftank kapasitas 18 m³ 100,000,000.00

PEKERJAAN SISTEM AIR BEKAS & AIR KOTOR


IPAL STP ROTORDISK, RBC Kap 100 m3/hari 1,003,200,000.00
Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph 20,000,000.00
Septic Tank Uk. 12 m³ 128,500,000.00

PEKERJAAN SISTEM AIR HUJAN


Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph Ex Grundfos 20,000,000.00

PEKERJAAN SISTEM FIRE FIGHTING


ELECTRIC HYDRANT PUMP STANDART NFPA 295,000,000.00
DIESEL HYDRANT PUMP STANDART NFPA 465,000,000.00
JOCKEY PUMP STANDART NFPA 84,500,000.00
Material Bantu 20,104,000.00
AAV 4" 3,675,000.00
Portable fire extinguisher Dry Chemical kap. 3 kg 838,000.00
siamase connection 2,365,000.00
PEKERJAAN TATA UDARA (VAC)
Pekerjaan Ducting Lt 1 s.d 3 7,000,000.00
Pekerjaan Ducting R.OK 51,500,000.00
Pekerjaan Ducting Lt 4 s.d 6 45,000,000.00
Instalasi & Accessories Lt 4 254,259,200.00
Instalasi & Accessories Lt 5 263,908,400.00
Instalasi & Accessories Lt 6 256,181,200.00

PEKERJAAN SISTEM GAS MEDIS


Medical Vacuum System (V)-NFPA 99 Compliant 165,000,000.00
Medical Air Supply 175,000,000.00
Unit Sentral Gas Oxygen ( O2 ) 257,600,000.00
Unit Sentral Gas NitrogenOxide ( NO2 ) 76,800,000.00
Central Alarm Panel c/w Main Valve 30,200,000.00
Pemasangan Peralatan Utama dan Testing Commisioning (Flushing dg Nitrogen) 20,000,000.00
Pengadaan dan Pasang Multipoint 2,185,800.00
Pengadaan dan Pasang Box Valve dan Zone Alarm 22,210,000.00
Ball Valve 1/2" 133,600.00
Ball Valve 3/4" 176,900.00
Ball Valve 1" 215,000.00

PEKERJAAN MEKANIKAL:
PEKERJAAN TRANSFORMATOR DAYA DAN SUPLAI TEGANGAN MENENGAH
Transformer 150,000,000.00
Incoming Cubicle PUTM Type DM-1A 215,000,000.00
Outgoing Cubicle DM (lihat Spesifikasi Teknis) 65,800,000.00

PEKERJAAN GENERATOR SET


Genset 1250 kVA silent type 3,140,000,000.00
Pompa solar tangan 1,458,000.00
Pompa solar listrik 7,290,000.00
Tangki harian 1500 liter, plat t = 3 mm 3,500,000.00
Tangki mingguan, kap. 10.000 liter, t = 8 mm, tidak termasuk pondasi struktur 10,000,000.00
Piping, valve, wiring control pompa, fuel level control dan accessoris Panel Pompa 15,000,000.00
Pemipaan exhaust dia. 6" 9,500,000.00
Isolasi rock wool seluruh pipa exhaust lengkap Jacketing 3,250,000.00
Wall lining sound Proof ' dengan Rockwool density 80 kg/cm3 lengkap 162,400.00
Testing & Commissioning Genset termasuk pengadaan solar selama testing 15,000,000.00
Biaya Transportasi / Pengiriman 26,000,000.00
Perijinan Depnaker 3,500,000.00
Grounding pentanahan 5,000,000.00

PEKERJAAN PANEL LISTRIK UTAMA TEGANGAN RENDAH


Panel PUTR (lihat drawing) 240,500,000.00
Panel Kontrol Genset (lihat drawing) 85,000,000.00

PEKERJAAN KABEL LADDER & TRAY


Tee Ladder W:1000/800 mm H:100mm, tebal plat 2mm 1,991,000.00
Tee Ladder W:800/800 mm H:100mm, tebal plat 2mm 676,000.00
Tee Ladder W:800/600 mm H:100mm, tebal plat 2mm 566,500.00
Elbow Ladder W:800 mm H:100mm, tebal plat 2mm 1,441,000.00
Reducer Ladder W:800/400 mm H:100mm, tebal plat 2mm 264,000.00
Tee Ladder W:600/600 mm H:100mm, tebal plat 2mm 875,000.00
Elbow IR Ladder W:600 mm H:100mm, tebal plat 2mm 979,000.00
Elbow Ladder W:400 mm H:100mm, tebal plat 2mm 660,500.00
Material bantu & aksesoris 7,772,287.60
Material bantu & aksesoris (Rises) 3,230,304.00
Material bantu & aksesoris (Basement s.d. Lt 6) 2,931,000.00
Material bantu & aksesoris (Atap) 637,500.00

PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK


TL 2x36W 560,000.00
TL 1x36W 178,750.00
TL 2x18W 475,200.00
DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 196,900.00
DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery 596,900.00
EXIT Lamp (Sign) 18 Watt c/w Battery 720,500.00
TLC 22W, armatur Baret Square 226,600.00
Saklar tunggal inbow 10 A 32,500.00
Saklar ganda inbow 10 A 58,500.00
Saklar Hotel Tunggal inbow 85,000.00
Stop kontak 1 ph Inbow Single 45,500.00
Stop kontak 1 ph Outbow Single 45,500.00
Stop kontak 3 ph 2200 Watt 133,900.00
Bed Head Wall c/w standart accessories + Instalasi 3,318,900.00
HPL-N 250W,PJU Sodium Type, termasuk pondasi & tiang 1 tangkai tinggi 7 meter. 5,950,000.00

PEKERJAAN SISTEM FIRE ALARM


MCFA Semiaddressable 2 Loop 78,560,000.00
STP AWG #18, kabel Data Loop dari MCFA ke TBFA 16,520.00
NYA 2x1.5, kabel Power dari MCFA ke TBFA 3,750.00
TBFA ISO 2,000,000.00
ROR Temperature Heat Detector Konvensional 210,900.00
Manual Call Point 225,000.00
Indicator Lamp 562,000.00
Alarm Bell 433,000.00
End Of Line 60,500.00
TBFA 1 4,000,000.00

PEKERJAAN SISTEM TELEPON


TBT - 1 350,000.00
Outlet Telephone Extension tipe wall mounted 65,000.00
Single Line Telephone 375,000.00
Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) 1,650,000.00

PEKERJAAN SISTEM TATA SUARA


Power Amplifier TOA ZP-2240 - 240 watt 4,000,000.00
Mixer Amplifier TOA Za-2240 Power 240 Watt 3,500,000.00
Selector Switch min. 8 Zone 185,000.00
Dynamic Microphone 466,800.00
CD/VCD/DVD/MP3 Player 1,500,000.00
Consumable Material termasuk rak besi. 5,000,000.00
Wiring & Tescomm 2,000,000.00
TBS 380,000.00
Horn Speaker 15 W TOA 350,000.00
Ceilling Speaker 6 W TOA 102,000.00
Testing commissioning 1,000,000.00

PEKERJAAN SISTEM MATV


Antena Parabola 12 channel 17,100,000.00
Satellite Receiver 2,360,000.00
Decoder 1,480,000.00
Modulator 2,430,000.00
Active Combiner 1,764,000.00
LED TV 32" ex. Samsung (Server) 3,500,000.00
CD/VCD/DVD/MP3 Player 1,500,000.00
Splitter 2 Way 250,000.00
Booster 2,410,000.00
Rack Peralatan MATV 4,500,000.00
Wiring & Tescomm 2,000,000.00
Splitter 4 Way 261,000.00
Coupler 4 Way 338,000.00
Outlet MATV 36,500.00
Coupler 2 Way 300,000.00
Testing commissioning 2,000,000.00

PEKERJAAN SISTEM DATA


Komputer Server BUILDUP 17,000,000.00
LED TV 32" ex. Samsung (Server) 3,500,000.00
Keyboard & mouse ex. Logitech 350,000.00
1 TB HDD 1,000,000.00
SWITCH HUB 16 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps 1,200,000.00
UPS 1.5 KVA Eaton 5,000,000.00
Ijin dan Biaya Penyambungan Paket Data 10,000,000.00
Wifi 3G/4G 600 Mbps Dual Band 1,000,000.00
Outlet data kabel 150,000.00
SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps 2,000,000.00

PEKERJAAN SISTEM CCTV


Komputer Server Lenovo DC 19" 5,500,000.00
LED TV 32" ex. Samsung (Server) 3,500,000.00
LED TV 43" ex. Samsung (R. Direktur) 4,750,000.00
HDD 2 TB 2,500,000.00
NVR Hikvision 32 Chanell 7732NI-E4 6,500,000.00
Hikvision Joystick Controlrer PTZ DS-1005KI 4,500,000.00
SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps 2,000,000.00
Power Supply 20 A 750,000.00
UPS 1.5 KVA Eaton 5,000,000.00
Wiring & Tescomm 5,000,000.00
Outdoor CCTV Hikvision IP PTZ Full HD 2 MP DS-2DE4225IW-DE 4,650,000.00
Indoor CCTV DS-2CD1123G0E-I Hikvision IP Camera CCTV Indoor 2MP 650,000.00
Testing commissioning 2,000,000.00

PEKERJAAN SISTEM NURSE CALL


Master Station 107,000,000.00
Display Anunciator 30,800,000.00
Call Report Software 6,160,000.00
Nurse Call Console (c/w Speaker & Mic) 2,070,000.00
Corridor Light 1,232,000.00
Emergency Button (Toilet) 1,629,000.00
Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm 111,540.00
Instalasi Cabang 2 pair, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm 150,040.00
Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm 594,440.00
Testing commissioning 2,000,000.00

PEKERJAAN PENANGKAL PETIR DAN GROUNDING


PENANGKAL PETIR C/W GROUNDING PENANGKAL PETIR (R. Max. 2 Ohm) 58,600,000.00
Grounding (BC 25) Max 1 Ohm & 20 meter 3,500,000.00
Grounding (BC 120) Max 2 Ohm & 20 meter 5,000,000.00

PEKERJAAN SISTEM TRANSPORTASI VERTIKAL (LIFT)


Dumbwaiter 258,851,331.00
Hospital Bed Elevator 519,177,065.00
ANALISA HARGA SATUAN PEKERJAAN
1 titik Instalasi Penerangan

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYM 3x2.5 sqmm m 9.00 13,000.00 117,000.00
Pipa PVC Conduit HIC dia 20 mm m 9.00 5,000.00 45,000.00
T-Duce 20 bh 2.00 5,700.00 11,400.00
Sock 20 bh 3.00 800.00 2,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 6.00 800.00 4,800.00
JUMLAH HARGA BAHAN 184,100.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 224,100.00


D Overhead & Profit 10% 22,410.00
E Harga Satuan Pekerjaan (C+D) 246,510.00

1 titik Instalasi Penerangan Eksternal

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYFGBY 3x2.5 mm2 m 29.00 37,000.00 1,073,000.00
Pasir, Urug plus gali m 29.00 10,000.00 290,000.00
Pipa PVC Conduit HIC dia 20 mm m 9.00 5,000.00 45,000.00
Sock 20 bh 3.00 800.00 2,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 15.00 800.00 12,000.00
JUMLAH HARGA BAHAN 1,425,900.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 1,460,900.00


D Overhead & Profit 10% 146,090.00
E Harga Satuan Pekerjaan (C+D) 1,606,990.00

1 titik Instalasi Stop Kontak 1 PH

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYM 3x2.5 sqmm m 12.15 13,000.00 157,950.00
Pipa PVC Conduit HIC dia 20 mm m 11.15 5,000.00 55,750.00
T-Duce 20 bh 2.00 5,700.00 11,400.00
Sock 20 bh 3.72 800.00 2,973.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 7.43 800.00 5,946.67
JUMLAH HARGA BAHAN 237,520.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 277,520.00


D Overhead & Profit 10% 27,752.00
E Harga Satuan Pekerjaan (C+D) 305,272.00

1 titik Instalasi AC 1 PH

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYM 3x2.5 sqmm m 20.00 13,000.00 260,000.00
Pipa PVC Conduit HIC dia 20 mm m 19.00 5,000.00 95,000.00
T-Duce 20 bh 2.00 5,700.00 11,400.00
Sock 20 bh 6.33 800.00 5,066.67
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 12.67 800.00 10,133.33
JUMLAH HARGA BAHAN 385,100.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 425,100.00


D Overhead & Profit 10% 42,510.00
E Harga Satuan Pekerjaan (C+D) 467,610.00

1 titik Instalasi FAN

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYM 3x2.5 sqmm m 7.50 13,000.00 97,500.00
Pipa PVC Conduit HIC dia 20 mm m 6.50 5,000.00 32,500.00
T-Duce 20 bh 2.00 5,700.00 11,400.00
Sock 20 bh 2.17 800.00 1,733.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 4.33 800.00 3,466.67
JUMLAH HARGA BAHAN 150,100.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 190,100.00


D Overhead & Profit 10% 19,010.00
E Harga Satuan Pekerjaan (C+D) 209,110.00

1 titik Instalasi Pintu Hermetik

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYM 3x2.5 sqmm m 32.00 13,000.00 416,000.00
Pipa PVC Conduit HIC dia 20 mm m 31.00 5,000.00 155,000.00
T-Duce 20 bh 2.00 5,700.00 11,400.00
Sock 20 bh 10.33 800.00 8,266.67
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 20.67 800.00 16,533.33
JUMLAH HARGA BAHAN 610,700.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 650,700.00


D Overhead & Profit 10% 65,070.00
E Harga Satuan Pekerjaan (C+D) 715,770.00

1 titik Instalasi Stop Kontak 3 PH

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYY 5x2.5 sqmm m 30.00 23,000.00 690,000.00
Pipa Metal Conduit HIC dia 25 mm m 29.00 45,000.00 1,305,000.00
T-Duce 25 bh 2.00 50,000.00 100,000.00
Sock 25 bh 9.67 25,000.00 241,666.67
Flexible 25 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 19.33 800.00 15,466.67
JUMLAH HARGA BAHAN 2,355,633.33
B TENAGA
Upah OH 1.00 50,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 2,405,633.33


D Overhead & Profit 10% 240,563.33
E Harga Satuan Pekerjaan (C+D) 2,646,196.67

1 titik Instalasi Telepon


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel ITC 2X0.6 m 78.00 4,000.00 312,000.00
Pipa PVC Conduit HIC dia 20 mm m 77.00 5,000.00 385,000.00
Sock 20 bh 25.67 800.00 20,533.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 51.33 800.00 41,066.67
JUMLAH HARGA BAHAN 762,100.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 797,100.00


D Overhead & Profit 10% 79,710.00
E Harga Satuan Pekerjaan (C+D) 876,810.00

1 titik Instalasi Speaker

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYMHY 2x1.5 mm2 m 11.00 9,800.00 107,800.00
Pipa PVC Conduit HIC dia 20 mm m 10.00 5,000.00 50,000.00
Sock 20 bh 3.33 800.00 2,666.67
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 6.67 800.00 5,333.33
JUMLAH HARGA BAHAN 169,300.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 204,300.00


D Overhead & Profit 10% 20,430.00
E Harga Satuan Pekerjaan (C+D) 224,730.00

1 titik Instalasi MATV

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel Coaxial RG 6 m 15.00 7,000.00 105,000.00
Pipa PVC Conduit HIC dia 20 mm m 14.00 5,000.00 70,000.00
Sock 20 bh 4.67 800.00 3,733.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 9.33 800.00 7,466.67
JUMLAH HARGA BAHAN 189,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 224,700.00


D Overhead & Profit 10% 22,470.00
E Harga Satuan Pekerjaan (C+D) 247,170.00

1 titik Instalasi Detektor

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYA 2x1.5 mm2 m 10.00 7,000.00 70,000.00
Pipa PVC Conduit HIC dia 20 mm m 9.00 5,000.00 45,000.00
Sock 20 bh 3.00 800.00 2,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 6.00 800.00 4,800.00
JUMLAH HARGA BAHAN 125,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00
C Jumlah (A+B) 160,700.00
D Overhead & Profit 10% 16,070.00
E Harga Satuan Pekerjaan (C+D) 176,770.00

1 titik Instalasi Breakglass, Bell & Stobe Lamp

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYA 2x1.5 mm2 m 30.00 7,000.00 210,000.00
Pipa PVC Conduit HIC dia 20 mm m 29.00 5,000.00 145,000.00
Sock 20 bh 9.67 800.00 7,733.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 19.33 800.00 15,466.67
JUMLAH HARGA BAHAN 381,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 416,700.00


D Overhead & Profit 10% 41,670.00
E Harga Satuan Pekerjaan (C+D) 458,370.00

1 titik Instalasi Data

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel UTP Cat5e m 30.00 7,500.00 225,000.00
Pipa PVC Conduit HIC dia 20 mm m 29.00 5,000.00 145,000.00
Sock 20 bh 9.67 800.00 7,733.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 19.33 800.00 15,466.67
JUMLAH HARGA BAHAN 396,700.00
B TENAGA
Upah OH 1.00 50,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 446,700.00


D Overhead & Profit 10% 44,670.00
E Harga Satuan Pekerjaan (C+D) 491,370.00

1 titik Instalasi CCTV

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel UTP Cat 6 m 65.00 8,500.00 552,500.00
Pipa PVC Conduit HIC dia 20 mm m 64.00 5,000.00 320,000.00
Sock 20 bh 21.33 800.00 17,066.67
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 42.67 800.00 34,133.33
JUMLAH HARGA BAHAN 927,200.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 967,200.00


D Overhead & Profit 10% 96,720.00
E Harga Satuan Pekerjaan (C+D) 1,063,920.00

1 titik Instalasi Door Contact

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel UTP ITC 2x0.6 mm2 m 40.00 4,000.00 160,000.00
Pipa PVC Conduit HIC dia 20 mm m 39.00 5,000.00 195,000.00
Sock 20 bh 13.00 800.00 10,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 26.00 800.00 20,800.00
JUMLAH HARGA BAHAN 389,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 424,700.00


D Overhead & Profit 10% 42,470.00
E Harga Satuan Pekerjaan (C+D) 467,170.00

1 titik Instalasi Push Button (Access Card)

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYA 2x1.5 mm2 m 40.00 7,000.00 280,000.00
Pipa PVC Conduit HIC dia 20 mm m 39.00 5,000.00 195,000.00
Sock 20 bh 13.00 800.00 10,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 26.00 800.00 20,800.00
JUMLAH HARGA BAHAN 509,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 544,700.00


D Overhead & Profit 10% 54,470.00
E Harga Satuan Pekerjaan (C+D) 599,170.00

1 titik Instalasi Magnetic Lock

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYA 2x1.5 mm2 m 40.00 7,000.00 280,000.00
Pipa PVC Conduit HIC dia 20 mm m 39.00 5,000.00 195,000.00
Sock 20 bh 13.00 800.00 10,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 26.00 800.00 20,800.00
JUMLAH HARGA BAHAN 509,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 544,700.00


D Overhead & Profit 10% 54,470.00
E Harga Satuan Pekerjaan (C+D) 599,170.00

1 titik Instalasi Card Reader

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel STP AWG #18 & NYA 2x1.5 mm2 m 40.00 18,050.00 722,000.00
Pipa PVC Conduit HIC dia 20 mm m 39.00 5,000.00 195,000.00
Sock 20 bh 13.00 800.00 10,400.00
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 26.00 800.00 20,800.00
JUMLAH HARGA BAHAN 951,700.00
B TENAGA
Upah OH 1.00 35,000.00 35,000.00
JUMLAH HARGA ALAT 35,000.00

C Jumlah (A+B) 986,700.00


D Overhead & Profit 10% 98,670.00
E Harga Satuan Pekerjaan (C+D) 1,085,370.00

1 titik Instalasi Panel Elektronik

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYM 3x2.5 sqmm m 15.00 13,000.00 195,000.00
Pipa PVC Conduit HIC dia 20 mm m 14.00 5,000.00 70,000.00
T-Duce 20 bh 2.00 5,700.00 11,400.00
Sock 20 bh 4.67 800.00 3,733.33
Flexible 20 m 1.00 3,500.00 3,500.00
Klem plus Fischer S6 bh 9.33 800.00 7,466.67
JUMLAH HARGA BAHAN 291,100.00
B TENAGA
Upah OH 1.00 40,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

C Jumlah (A+B) 331,100.00


D Overhead & Profit 10% 33,110.00
E Harga Satuan Pekerjaan (C+D) 364,210.00

1 titik Panel SDP 3

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 1000-1250 A 25 Ka c/w Proteksi Motor Micrologic 2 bh 1.00 17,335,000.00 17,335,000.00
MCCB 3 Phase 350 A 18 kA bh 1.00 3,905,000.00 3,905,000.00
MCCB 3 Phase 300 A 18 Ka bh 1.00 3,756,500.00 3,756,500.00
MCCB 3 Phase 100 A 18 kA bh 4.00 980,100.00 3,920,400.00
MCCB 3 Phase 80 A 18 kA bh 1.00 980,100.00 980,100.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 3.00 250,000.00 750,000.00
Amperemeter bh 3.00 288,000.00 864,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 34,324,000.00
B TENAGA
Upah OH 1.00 4,200,000.00 4,200,000.00
JUMLAH HARGA ALAT 4,200,000.00

C Jumlah (A+B) 38,524,000.00


D Overhead & Profit 10% 3,852,400.00
E Harga Satuan Pekerjaan (C+D) 42,376,400.00

1 titik Panel SDP 4

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 1000-1250A 25 kA c/w Proteksi Motor Micrologic 2 bh 1.00 10,961,500.00 10,961,500.00
MCCB 3 Phase 100 A 16 kA bh 3.00 980,100.00 2,940,300.00
MCCB 3 Phase 80 A 16 kA bh 1.00 980,100.00 980,100.00
MCCB 3 Phase 50 A 16 kA bh 1.00 897,600.00 897,600.00
MCCB 3 Phase 320 A 16 kA bh 1.00 3,756,500.00 3,756,500.00
MCCB 3 Phase 300 A 16 kA bh 1.00 3,756,500.00 3,756,500.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 3.00 250,000.00 750,000.00
Amperemeter bh 3.00 288,000.00 864,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 27,719,500.00
B TENAGA
Upah OH 1.00 4,200,000.00 4,200,000.00
JUMLAH HARGA ALAT 4,200,000.00

C Jumlah (A+B) 31,919,500.00


D Overhead & Profit 10% 3,191,950.00
E Harga Satuan Pekerjaan (C+D) 35,111,450.00

1 titik Panel PP POMPA


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 75A 16 kA c/w Proteksi Motor Micrologic bh 1.00 10,327,900.00 10,327,900.00
MCB 3 Phase 40 A 16 kA bh 2.00 980,100.00 1,960,200.00
MCB 3 Phase 16 A 16 kA bh 4.00 980,100.00 3,920,400.00
MCB 1 Phase 16 A 6 kA bh 3.00 93,610.00 280,830.00
CONTACTOR 3PH 16 A bh 1.00 164,000.00 164,000.00
CONTACTOR 3PH 32 A bh 1.00 325,000.00 325,000.00
WLC bh 2.00 450,000.00 900,000.00
Switch Auto Manual bh 2.00 91,200.00 182,400.00
Switch On-Off bh 4.00 91,200.00 364,800.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 3.00 250,000.00 750,000.00
Amperemeter bh 3.00 288,000.00 864,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 22,852,530.00
B TENAGA
Upah OH 1.00 800,000.00 800,000.00
JUMLAH HARGA ALAT 800,000.00

C Jumlah (A+B) 23,652,530.00


D Overhead & Profit 10% 2,365,253.00
E Harga Satuan Pekerjaan (C+D) 26,017,783.00

1 titik Panel PP FIRE PUMP

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 200-250A 25 kA c/w Proteksi Motor Micrologic bh 1.00 10,961,500.00 10,961,500.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 13,111,500.00
B TENAGA
Upah OH 1.00 300,000.00 300,000.00
JUMLAH HARGA ALAT 300,000.00

C Jumlah (A+B) 13,411,500.00


D Overhead & Profit 10% 1,341,150.00
E Harga Satuan Pekerjaan (C+D) 14,752,650.00

1 titik Panel LP-BASEMENT

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 25 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 10 A 6 kA bh 15.00 93,610.00 1,404,150.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,447,250.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,047,250.00


D Overhead & Profit 10% 604,725.00
E Harga Satuan Pekerjaan (C+D) 6,651,975.00
1 titik Panel LP-1

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 80 A 18 kA bh 1.00 980,100.00 980,100.00
ELCB 2 Phase 10 A 30mA bh 577,500.00 -
MCB 1 Phase 10 A 6 kA bh 11.00 93,610.00 1,029,710.00
MCB 1 Phase 16 A 6 kA bh 23.00 93,610.00 2,153,030.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 7,225,840.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 7,825,840.00


D Overhead & Profit 10% 782,584.00
E Harga Satuan Pekerjaan (C+D) 8,608,424.00

1 titik Panel LP-2

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 100 A 18kA bh 1.00 951,500.00 951,500.00
MCB 1 Phase 10 A 6 kA bh 11.00 93,610.00 1,029,710.00
MCB 1 Phase 16 A 6 kA bh 24.00 93,610.00 2,246,640.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 7,290,850.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 7,890,850.00


D Overhead & Profit 10% 789,085.00
E Harga Satuan Pekerjaan (C+D) 8,679,935.00

1 titik Panel LP-3

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 40 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 16 A 6 kA bh 20.00 93,610.00 1,872,200.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,915,300.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00
C Jumlah (A+B) 6,515,300.00
D Overhead & Profit 10% 651,530.00
E Harga Satuan Pekerjaan (C+D) 7,166,830.00

1 titik Panel LP-4

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 40 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 16 A 6 kA bh 20.00 93,610.00 1,872,200.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,915,300.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,515,300.00


D Overhead & Profit 10% 651,530.00
E Harga Satuan Pekerjaan (C+D) 7,166,830.00

1 titik Panel LP-5

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 40 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 16 A 6 kA bh 19.00 93,610.00 1,778,590.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,821,690.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,421,690.00


D Overhead & Profit 10% 642,169.00
E Harga Satuan Pekerjaan (C+D) 7,063,859.00

1 titik Panel LP-6

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 40 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 16 A 6 kA bh 26.00 93,610.00 2,433,860.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 6,476,960.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00
C Jumlah (A+B) 7,076,960.00
D Overhead & Profit 10% 707,696.00
E Harga Satuan Pekerjaan (C+D) 7,784,656.00

1 titik Panel PP.AC-BASEMENT

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 30 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 10 A 6 kA bh 14.00 93,610.00 1,310,540.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,353,640.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 5,953,640.00


D Overhead & Profit 10% 595,364.00
E Harga Satuan Pekerjaan (C+D) 6,549,004.00

1 titik Panel PP.AC-C1

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 63 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 3 Phase 16 A 6 kA bh 13.00 412,830.00 5,366,790.00
MCB 1 Phase 16 A 16 Ka bh 73.00 103,950.00 7,588,350.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 16,998,240.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 17,598,240.00


D Overhead & Profit 10% 1,759,824.00
E Harga Satuan Pekerjaan (C+D) 19,358,064.00

1 titik Panel PP.AC-C2

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 63 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 3 Phase 16 A 6 kA bh 7.00 412,830.00 2,889,810.00
MCB 1 Phase 16 A 6 kA bh 74.00 93,610.00 6,927,140.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 13,860,050.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 14,460,050.00


D Overhead & Profit 10% 1,446,005.00
E Harga Satuan Pekerjaan (C+D) 15,906,055.00

1 titik Panel PP.AC-3

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 63 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 10 A 6 Ka bh 25.00 93,610.00 2,340,250.00
MCB 1 Phase 16 A 6 kA bh 4.00 93,610.00 374,440.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 6,757,790.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 7,357,790.00


D Overhead & Profit 10% 735,779.00
E Harga Satuan Pekerjaan (C+D) 8,093,569.00

1 titik Panel PP.AC-4

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCB 3 Phase 10 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 6 A 6 kA bh 23.00 93,610.00 2,153,030.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 6,196,130.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,796,130.00


D Overhead & Profit 10% 679,613.00
E Harga Satuan Pekerjaan (C+D) 7,475,743.00

1 titik Panel PP.AC-5

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCB 3 Phase 10 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 6 A 6 kA bh 24.00 93,610.00 2,246,640.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 6,289,740.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,889,740.00


D Overhead & Profit 10% 688,974.00
E Harga Satuan Pekerjaan (C+D) 7,578,714.00

1 titik Panel PP.AC-6

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCB 3 Phase 10 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 6 A 6 kA bh 24.00 93,610.00 2,246,640.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 6,289,740.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,889,740.00


D Overhead & Profit 10% 688,974.00
E Harga Satuan Pekerjaan (C+D) 7,578,714.00

1 titik Panel PP.EC

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 30 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 16 A 6 kA bh 9.00 93,610.00 842,490.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 4,885,590.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 5,485,590.00


D Overhead & Profit 10% 548,559.00
E Harga Satuan Pekerjaan (C+D) 6,034,149.00

1 titik Panel PP.Radiography

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 450-500A 25 kA c/w Proteksi Motor Micrologic bh 1.00 6,671,500.00 6,671,500.00
MCCB 3 Phase 250A 16 Ka bh 1.00 1,685,200.00 1,685,200.00
MCCB 3 Phase 150A 16 Ka bh 1.00 1,685,200.00 1,685,200.00
MCB 1 Phase 16 A 6 kA bh 7.00 93,610.00 655,270.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 13,760,170.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 14,360,170.00


D Overhead & Profit 10% 1,436,017.00
E Harga Satuan Pekerjaan (C+D) 15,796,187.00

1 titik Panel PP.X-RAY

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 250A 16 Ka bh 1.00 1,685,200.00 1,685,200.00
MCB 1 Phase 16 A 6 kA bh 3.00 93,610.00 280,830.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,029,030.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 5,629,030.00


D Overhead & Profit 10% 562,903.00
E Harga Satuan Pekerjaan (C+D) 6,191,933.00

1 titik Panel PP.OK

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCB 3 Phase 25A 16 Ka bh 1.00 439,560.00 439,560.00
MCB 3 Phase 16A 16 Ka bh 2.00 412,830.00 825,660.00
MCB 1 Phase 16 A 6 kA bh 4.00 93,610.00 374,440.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 4,702,660.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 5,302,660.00


D Overhead & Profit 10% 530,266.00
E Harga Satuan Pekerjaan (C+D) 5,832,926.00

1 titik Panel PP.AC ATAP

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 400-450A 25 kA c/w Proteksi Motor Micrologic bh 1.00 6,671,500.00 6,671,500.00
MCCB 3 Phase 16A 16 Ka bh 2.00 980,100.00 1,960,200.00
MCCB 3 Phase 63A 16 Ka bh 4.00 980,100.00 3,920,400.00
MCB 1 Phase 16 A 6 kA bh 4.00 93,610.00 374,440.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 15,989,540.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 16,589,540.00


D Overhead & Profit 10% 1,658,954.00
E Harga Satuan Pekerjaan (C+D) 18,248,494.00

1 titik Panel PP.ATAP

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 1,500,000.00 1,500,000.00
MCCB 3 Phase 50 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 3 Phase 16 A 16 kA bh 3.00 412,830.00 1,238,490.00
MCB 1 Phase 16 A 6 kA bh 4.00 93,610.00 374,440.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 5,656,030.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 6,256,030.00


D Overhead & Profit 10% 625,603.00
E Harga Satuan Pekerjaan (C+D) 6,881,633.00

1 titik Panel LP.EKSTERNAL

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel (TYPE OUTDOOR IP 65) bh 1.00 850,000.00 850,000.00
MCCB 3 Phase 10 A 16 kA bh 1.00 980,100.00 980,100.00
MCB 1 Phase 6A 6 kA bh 6.00 93,610.00 561,660.00
CONTACTOR 3PH 16 A bh 1.00 164,000.00 164,000.00
Switch Auto Manual bh 3.00 91,200.00 273,600.00
Switch On-Off bh 3.00 91,200.00 273,600.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 4,665,960.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 5,265,960.00


D Overhead & Profit 10% 526,596.00
E Harga Satuan Pekerjaan (C+D) 5,792,556.00

1 titik Panel PP-WH 1

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 500,000.00 500,000.00
MCB 1 Phase 16 A 6 kA bh 41.00 93,610.00 3,838,010.00
ELCB 2 Phase 100 A 30mA bh 1.00 2,923,800.00 2,923,800.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 8,824,810.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 9,424,810.00


D Overhead & Profit 10% 942,481.00
E Harga Satuan Pekerjaan (C+D) 10,367,291.00

1 titik Panel PP-WH 2

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 500,000.00 500,000.00
MCB 1 Phase 16 A 6 kA bh 42.00 93,610.00 3,931,620.00
ELCB 2 Phase 100 A 30mA bh 1.00 2,923,800.00 2,923,800.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 8,918,420.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 9,518,420.00


D Overhead & Profit 10% 951,842.00
E Harga Satuan Pekerjaan (C+D) 10,470,262.00

1 titik Panel PP-WH 5

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 500,000.00 500,000.00
MCB 1 Phase 16 A 6 kA bh 16.00 93,610.00 1,497,760.00
ELCB 2 Phase 63 A 30mA bh 1.00 748,550.00 748,550.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 4,309,310.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 4,909,310.00


D Overhead & Profit 10% 490,931.00
E Harga Satuan Pekerjaan (C+D) 5,400,241.00

1 titik Panel PP-WH 6

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 500,000.00 500,000.00
MCB 1 Phase 16 A 6 kA bh 11.00 93,610.00 1,029,710.00
ELCB 2 Phase 25 A 30mA bh 1.00 748,550.00 748,550.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 3,841,260.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 4,441,260.00


D Overhead & Profit 10% 444,126.00
E Harga Satuan Pekerjaan (C+D) 4,885,386.00

1 titik Panel PP.POMPA

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Box Panel bh 1.00 500,000.00 500,000.00
MCCB 3 Phase 75 A 16 kA bh 1.00 10,327,900.00 10,327,900.00
MCB 3 Phase 40 A 16 kA bh 2.00 980,100.00 1,960,200.00
MCB 3 Phase 16 A 16 kA bh 4.00 980,100.00 3,920,400.00
MCB 1 Phase 16 A 6 kA bh 3.00 93,610.00 280,830.00
Pilot Lamp bh 3.00 22,500.00 67,500.00
Fuse bh 3.00 25,000.00 75,000.00
Voltage Selector bh 1.00 70,500.00 70,500.00
Voltmeter bh 1.00 250,000.00 250,000.00
Bus bar lot 1.00 450,000.00 450,000.00
Terminal Blok lot 1.00 500,000.00 500,000.00
Wiring & Accessories lot 1.00 150,000.00 150,000.00
JUMLAH HARGA BAHAN 18,552,330.00
B TENAGA
Upah OH 1.00 600,000.00 600,000.00
JUMLAH HARGA ALAT 600,000.00

C Jumlah (A+B) 19,152,330.00


D Overhead & Profit 10% 1,915,233.00
E Harga Satuan Pekerjaan (C+D) 21,067,563.00

1 titik Instalasi Pipa Refrigerant 1pk

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa Tembaga 1/4" m 17.50 14,500.00 253,750.00
Pipa Tembaga 3/8" m 17.50 22,400.00 392,000.00
Isolasi Pipa Refrigerant 1/4" m 17.50 12,000.00 210,000.00
Isolasi Pipa Refrigerant 3/8" m 17.50 13,000.00 227,500.00
Pipa Drain & Perlengkapan 30% harga pipa 0.30 645,750.00 193,725.00
Kabel NYM 3x2.5 mm m 17.50 13,000.00 227,500.00
JUMLAH HARGA BAHAN 1,504,475.00
B TENAGA
Pekerja OH 0.05 103,000.00 5,562.00
Tukang Ledeng OH 0.09 109,000.00 9,810.00
Kepala Tukang OH 0.01 147,000.00 1,323.00
Mandor OH 0.03 116,000.00 3,132.00
JUMLAH HARGA ALAT 346,972.50

C Jumlah (A+B) 1,851,447.50


D Overhead & Profit 10% 185,144.75
E Harga Satuan Pekerjaan (C+D) 2,036,592.25

1 titik Instalasi Pipa Refrigerant 1.5 & 2 pk

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa Tembaga 1/4" m 17.50 14,500.00 253,750.00
Pipa Tembaga 1/2" m 17.50 33,000.00 577,500.00
Isolasi Pipa Refrigerant 1/4" m 17.50 12,000.00 210,000.00
Isolasi Pipa Refrigerant 1/2" m 17.50 18,000.00 315,000.00
Pipa Drain & Perlengkapan 30% harga pipa 0.30 831,250.00 249,375.00
Kabel NYM 3x2.5 mm m 17.50 13,000.00 227,500.00
JUMLAH HARGA BAHAN 1,833,125.00
B TENAGA
Pekerja OH 0.05 103,000.00 5,562.00
Tukang Ledeng OH 0.09 109,000.00 9,810.00
Kepala Tukang OH 0.01 147,000.00 1,323.00
Mandor OH 0.03 116,000.00 3,132.00
JUMLAH HARGA ALAT 346,972.50

C Jumlah (A+B) 2,180,097.50


D Overhead & Profit 10% 218,009.75
E Harga Satuan Pekerjaan (C+D) 2,398,107.25

1 titik Instalasi Pipa Refrigerant 1.5 & 2 pk

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa Tembaga 1/4" m 17.50 14,500.00 253,750.00
Pipa Tembaga 1/2" m 17.50 33,000.00 577,500.00
Isolasi Pipa Refrigerant 1/4" m 17.50 12,000.00 210,000.00
Isolasi Pipa Refrigerant 1/2" m 17.50 18,000.00 315,000.00
Pipa Drain & Perlengkapan 30% harga pipa 0.30 831,250.00 249,375.00
Kabel NYM 3x2.5 mm m 17.50 13,000.00 227,500.00
JUMLAH HARGA BAHAN 1,833,125.00
B TENAGA
Pekerja OH 0.05 103,000.00 5,562.00
Tukang Ledeng OH 0.09 109,000.00 9,810.00
Kepala Tukang OH 0.01 147,000.00 1,323.00
Mandor OH 0.03 116,000.00 3,132.00
JUMLAH HARGA ALAT 346,972.50

C Jumlah (A+B) 2,180,097.50


D Overhead & Profit 10% 218,009.75
E Harga Satuan Pekerjaan (C+D) 2,398,107.25

A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PVC AW 1/2” M 1.2 7,000.00 8,400.00
Perlengkapan % 35% 7,000.00 2,450.00
JUMLAH HARGA BAHAN 10,850.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,212.00


E Overhead & Profit 10% 2,221.20
F Harga Satuan Pekerjaan (D+E) 24,433.20

A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PVC AW 3/4” M 1.2 10,000.00 12,000.00
Perlengkapan % 35% 10,000.00 3,500.00
JUMLAH HARGA BAHAN 15,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 26,862.00


E Overhead & Profit 10% 2,686.20
F Harga Satuan Pekerjaan (D+E) 29,548.20

A.5.1.1 27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PVC AW 1” M 1.2 11,000.00 13,200.00
Perlengkapan % 35% 11,000.00 3,850.00
JUMLAH HARGA BAHAN 17,050.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 28,412.00


E Overhead & Profit 10% 2,841.20
F Harga Satuan Pekerjaan (D+E) 31,253.20

A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 1 1/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC AW 1 1/4” M 1.2 16,200.00 19,440.00
Perlengkapan % 35% 16,200.00 5,670.00
JUMLAH HARGA BAHAN 25,110.00
C PERALATAN 0.00

JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 42,153.00


E Overhead & Profit 10% 4,215.30
F Harga Satuan Pekerjaan (D+E) 46,368.30

A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 1 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC AW 1 1/2” M 1.2 18,600.00 22,320.00
Perlengkapan % 35% 18,600.00 6,510.00
JUMLAH HARGA BAHAN 28,830.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 45,873.00
E Overhead & Profit 10% 4,587.30
F Harga Satuan Pekerjaan (D+E) 50,460.30

A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe D diameter 1 1/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC D 1 1/4” M 1.2 10,175.00 12,210.00
Perlengkapan % 35% 10,175.00 3,561.25
JUMLAH HARGA BAHAN 15,771.25
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 32,814.25


E Overhead & Profit 10% 3,281.43
F Harga Satuan Pekerjaan (D+E) 36,095.68

A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe D diameter 1 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC D 1 1/2” M 1.2 11,500.00 13,800.00
Perlengkapan % 35% 11,500.00 4,025.00
JUMLAH HARGA BAHAN 17,825.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 34,868.00


E Overhead & Profit 10% 3,486.80
F Harga Satuan Pekerjaan (D+E) 38,354.80

A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC AW 2” M 1.2 18,000.00 21,600.00
Perlengkapan % 35% 18,000.00 6,300.00
JUMLAH HARGA BAHAN 27,900.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 44,943.00


E Overhead & Profit 10% 4,494.30
F Harga Satuan Pekerjaan (D+E) 49,437.30

A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe D diameter 2”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC D 2” M 1.2 14,750.00 17,700.00
Perlengkapan % 35% 14,750.00 5,162.50
JUMLAH HARGA BAHAN 22,862.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 39,905.50


E Overhead & Profit 10% 3,990.55
F Harga Satuan Pekerjaan (D+E) 43,896.05

A.5.1.1.36. Pemasangan 1 m’ pipa pvc Underground diameter 2 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 2” Bh 1.1 18,000.00 19,800.00
Perlengkapan % 35% 18,000.00 6,300.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 47,025.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 111,872.60


E Overhead & Profit 10% 11,187.26
F Harga Satuan Pekerjaan (D+E) 123,059.86

A.5.1.1 30. Pemasangan 1 m’ pipa PVC tipe AW diameter 2 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC AW 2 1/2” M 1.2 34,725.00 41,670.00
Perlengkapan % 35% 34,725.00 12,153.75
JUMLAH HARGA BAHAN 53,823.75
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 79,330.25


E Overhead & Profit 10% 7,933.03
F Harga Satuan Pekerjaan (D+E) 87,263.28

A.5.1.1.36. Pemasangan 1 m’ pipa pvc Underground diameter 2 1/2"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 2 1/2” M 1.1 34,725.00 38,197.50
Perlengkapan % 35% 34,725.00 12,153.75
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 71,276.85
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 136,123.85


E Overhead & Profit 10% 13,612.39
F Harga Satuan Pekerjaan (D+E) 149,736.24

A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC AW 3” M 1.2 31,000.00 37,200.00
Perlengkapan % 35% 31,000.00 10,850.00
JUMLAH HARGA BAHAN 48,050.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 73,556.50


E Overhead & Profit 10% 7,355.65
F Harga Satuan Pekerjaan (D+E) 80,912.15

A.5.1.1.36. Pemasangan 1 m’ pipa pvc Underground diameter 3"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 3” m 1.1 31,000.00 34,100.00
Perlengkapan % 35% 31,000.00 10,850.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 65,875.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 130,722.60


E Overhead & Profit 10% 13,072.26
F Harga Satuan Pekerjaan (D+E) 143,794.86

A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe D diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC D 4” M 1.2 41,600.00 49,920.00
Perlengkapan % 35% 41,600.00 14,560.00
JUMLAH HARGA BAHAN 64,480.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 89,986.50


E Overhead & Profit 10% 8,998.65
F Harga Satuan Pekerjaan (D+E) 98,985.15

A.5.1.1 32. Pemasangan 1 titik pipa PVC tipe D diameter 4” untuk EXHAUST FAN TOILET

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC D 4” M 7.5 41,600.00 312,000.00
Perlengkapan % 35% 41,600.00 14,560.00
Flexible dan accessories % 20% 41,600.00 8,320.00
JUMLAH HARGA BAHAN 334,880.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 360,386.50


E Overhead & Profit 10% 36,038.65
F Harga Satuan Pekerjaan (D+E) 396,425.15

A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC AW 4” M 1.2 50,000.00 60,000.00
Perlengkapan % 35% 50,000.00 17,500.00
JUMLAH HARGA BAHAN 77,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 103,006.50


E Overhead & Profit 10% 10,300.65
F Harga Satuan Pekerjaan (D+E) 113,307.15

A.5.1.1.36. Pemasangan 1 m’ pipa pvc Underground diameter 100 cm/4 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 4” Bh 1.1 50,000.00 55,000.00
Perlengkapan % 35% 50,000.00 17,500.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 93,425.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 158,272.60


E Overhead & Profit 10% 15,827.26
F Harga Satuan Pekerjaan (D+E) 174,099.86

A.8.4.1.4 Pemasangan 1 m pipa PVC AW Ø 150 mm / 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.118 103,000.00 12,154.00
Tukang pipa L.02 OH 0.059 109,000.00 6,431.00
Mandor L.04 OH 0.012 116,000.00 1,392.00

JUMLAH TENAGA KERJA 19,977.00


B BAHAN
Pipa PVC AW Ø 150 mm 6" m 1 180,050.00 180,050.00
JUMLAH HARGA BAHAN 180,050.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.012 25,000.00 300.00
handle crane 2 T
JUMLAH HARGA ALAT 300.00

D Jumlah (A+B+C) 200,327.00


E Overhead & Profit (Contoh 15 %) 10% 20,032.70
F Harga Satuan Pekerjaan (D+E) 220,359.70

A.8.4.3.15 Pemasangan 1 buah Tee Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Tee PVC AW Ø 150 mm bh 1 260,900.00 260,900.00
JUMLAH HARGA BAHAN 260,900.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 279,571.00


E Overhead & Profit (Contoh 15 %) 10% 27,957.10
F Harga Satuan Pekerjaan (D+E) 307,528.10

A.8.4.3.15 Pemasangan 1 buah Elbow Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH HARGA BAHAN 17,971.00


B BAHAN
Elbow PVC AW Ø 150 mm bh 1 205,400.00 205,400.00
JUMLAH HARGA BAHAN 205,400.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 224,071.00


E Overhead & Profit (Contoh 15 %) 10% 22,407.10
F Harga Satuan Pekerjaan (D+E) 246,478.10

A.5.1.1.36. Pemasangan 1 m’ pipa pvc Underground diameter 150 cm/6 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 6” Bh 1 180,050.00 180,050.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 200,975.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 265,822.60


E Overhead & Profit 10% 26,582.26
F Harga Satuan Pekerjaan (D+E) 292,404.86

A.5.1.1 25. Pemasangan 1 m’ pipa PPR PN 10 diameter 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 1/2” M 1.2 12,039.50 14,447.40
Perlengkapan % 35% 12,039.50 4,213.83
JUMLAH HARGA BAHAN 18,661.23
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 30,023.23


E Overhead & Profit 10% 3,002.32
F Harga Satuan Pekerjaan (D+E) 33,025.55

A.5.1.1 26. Pemasangan 1 m’ pipa PPR PN 10 diameter 3/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 3/4” M 1.2 15,760.25 18,912.30
Perlengkapan % 35% 15,760.25 5,516.09
JUMLAH HARGA BAHAN 24,428.39
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 35,790.39
E Overhead & Profit 10% 3,579.04
F Harga Satuan Pekerjaan (D+E) 39,369.43

A.5.1.1 26. Pemasangan 1 m’ pipa PPR PN 10 diameter 3/4” UNDERGROUND

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 3/4” M 1.2 15,760.25 18,912.30
Perlengkapan % 35% 15,760.25 5,516.09
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 45,353.99
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 56,715.99


E Overhead & Profit 10% 5,671.60
F Harga Satuan Pekerjaan (D+E) 62,387.59

A.5.1.1 27. Pemasangan 1 m’ pipa PPR PN 10 diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 1” M 1.2 25,349.50 30,419.40
Perlengkapan % 35% 25,349.50 8,872.33
JUMLAH HARGA BAHAN 39,291.73
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 50,653.73


E Overhead & Profit 10% 5,065.37
F Harga Satuan Pekerjaan (D+E) 55,719.10

A.5.1.1 27. Pemasangan 1 m’ pipa PPR PN 10 diameter 1” UNDERGROUND

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 1” M 1.2 25,349.50 30,419.40
Perlengkapan % 35% 25,349.50 8,872.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 60,217.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 71,579.33


E Overhead & Profit 10% 7,157.93
F Harga Satuan Pekerjaan (D+E) 78,737.26

A.5.1.1 28. Pemasangan 1 m’ pipa PPR PN 10 diameter 1 1/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 10 11/4” M 1.2 40,172.00 48,206.40
Perlengkapan % 35% 40,172.00 14,060.20
JUMLAH HARGA BAHAN 62,266.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 79,309.60


E Overhead & Profit 10% 7,930.96
F Harga Satuan Pekerjaan (D+E) 87,240.56

A.5.1.1 28. Pemasangan 1 m’ pipa PPR PN 10 diameter 1 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 10 1 1/2” M 1.2 62,315.00 74,778.00
Perlengkapan % 35% 62,315.00 21,810.25
JUMLAH HARGA BAHAN 96,588.25
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 113,631.25


E Overhead & Profit 10% 11,363.13
F Harga Satuan Pekerjaan (D+E) 124,994.38

A.5.1.1.36. Pemasangan 1 m’ pipa PPR PN 10 Underground diameter 1 1/2 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PPR PN 10 DIA 1 1/2” Bh 1.2 62,315.00 74,778.00
Perlengkapan % 35% 62,315.00 21,810.25
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 117,513.85
C PERALATAN

JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 182,360.85


E Overhead & Profit 10% 18,236.09
F Harga Satuan Pekerjaan (D+E) 200,596.94

A.5.1.1 29. Pemasangan 1 m’ pipa PPR PN 10 diameter 2”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 10 2” M 1.2 98,645.25 118,374.30
Perlengkapan % 35% 98,645.25 34,525.84
JUMLAH HARGA BAHAN 152,900.14
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 169,943.14


E Overhead & Profit 10% 16,994.31
F Harga Satuan Pekerjaan (D+E) 186,937.45

A.5.1.1.36. Pemasangan 1 m’ pipa PPR PN 10 Underground diameter 2 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PPR PN 10 2” Bh 1.2 98,645.25 118,374.30
Perlengkapan % 35% 98,645.25 34,525.84
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 173,825.74
C PERALATAN

JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 238,672.74


E Overhead & Profit 10% 23,867.27
F Harga Satuan Pekerjaan (D+E) 262,540.01

A.5.1.1 30. Pemasangan 1 m’ pipa PPR PN 10 diameter 2 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PPR PN 10 2 1/2” M 1.2 138,030.75 165,636.90
Perlengkapan % 35% 138,030.75 48,310.76
JUMLAH HARGA BAHAN 213,947.66
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 239,454.16


E Overhead & Profit 10% 23,945.42
F Harga Satuan Pekerjaan (D+E) 263,399.58

A.5.1.1 31. Pemasangan 1 m’ pipa PPR PN 10 diameter 3”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PPR PN 10 3” M 1.2 199,226.50 239,071.80
Perlengkapan % 35% 199,226.50 69,729.28
JUMLAH HARGA BAHAN 308,801.08
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 334,307.58


E Overhead & Profit 10% 33,430.76
F Harga Satuan Pekerjaan (D+E) 367,738.33

A.5.1.1 32. Pemasangan 1 m’ pipa PPR PN 10 diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PPR PN 10 4” M 1.2 295,875.25 355,050.30
Perlengkapan % 35% 295,875.25 103,556.34
JUMLAH HARGA BAHAN 458,606.64
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 484,113.14


E Overhead & Profit 10% 48,411.31
F Harga Satuan Pekerjaan (D+E) 532,524.45

A.5.1.1.36. Pemasangan 1 m’ pipa PPR PN 10 Underground diameter 100 cm/4 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PPR PN 10 4” Bh 1.2 295,875.25 355,050.30
Perlengkapan % 35% 295,875.25 103,556.34
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 479,532.24
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 544,379.24


E Overhead & Profit 10% 54,437.92
F Harga Satuan Pekerjaan (D+E) 598,817.16

A.5.1.1 25. Pemasangan 1 m’ pipa PPR PN 20 diameter 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 20 1/2” M 1.2 16,698.00 20,037.60
Perlengkapan % 35% 16,698.00 5,844.30
JUMLAH HARGA BAHAN 25,881.90
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 37,243.90


E Overhead & Profit 10% 3,724.39
F Harga Satuan Pekerjaan (D+E) 40,968.29

A.5.1.1 26. Pemasangan 1 m’ pipa PPR PN 20 diameter 3/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 20 3/4” M 1.2 25,621.75 30,746.10
Perlengkapan % 35% 25,621.75 8,967.61
JUMLAH HARGA BAHAN 39,713.71
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 51,075.71


E Overhead & Profit 10% 5,107.57
F Harga Satuan Pekerjaan (D+E) 56,183.28

A.5.1.1 27. Pemasangan 1 m’ pipa PPR PN 20 diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 20 1” M 1.2 42,138.25 50,565.90
Perlengkapan % 35% 42,138.25 14,748.39
JUMLAH HARGA BAHAN 65,314.29
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 76,676.29


E Overhead & Profit 10% 7,667.63
F Harga Satuan Pekerjaan (D+E) 84,343.92

A.5.1.1 28. Pemasangan 1 m’ pipa PPR PN 20 diameter 1 1/2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 20 1 1/2” M 1.2 101,549.25 121,859.10
Perlengkapan % 35% 101,549.25 35,542.24
JUMLAH HARGA BAHAN 157,401.34
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 174,444.34


E Overhead & Profit 10% 17,444.43
F Harga Satuan Pekerjaan (D+E) 191,888.77

A.5.1.1 29. Pemasangan 1 m’ pipa PPR PN 20 diameter 2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 20 2” M 1.2 160,899.75 193,079.70
Perlengkapan % 35% 160,899.75 56,314.91
JUMLAH HARGA BAHAN 249,394.61
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 266,437.61


E Overhead & Profit 10% 26,643.76
F Harga Satuan Pekerjaan (D+E) 293,081.37

A.5.1.1 18. Pemasangan 1 m’ pipa galvanis diameter ½”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa galvanis ½” M 1.2 42,000.00 50,400.00
Perlengkapan Ls 35% 42,000.00 14,700.00
JUMLAH HARGA BAHAN 65,100.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 84,927.00


E Overhead & Profit 10% 8,492.70
F Harga Satuan Pekerjaan (D+E) 93,419.70

A.5.1.1 20. Pemasangan 1 m’ pipa galvanis diameter 3/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa galvanis 3/4” M 1.2 54,000.00 64,800.00
Perlengkapan % 35% 54,000.00 18,900.00
JUMLAH HARGA BAHAN 83,700.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 103,527.00
E Overhead & Profit 10% 10,352.70
F Harga Satuan Pekerjaan (D+E) 113,879.70

A.5.1.1 21. Pemasangan 1 m’ pipa galvanis diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa galvanis 1” M 1.2 82,833.33 99,400.00
Perlengkapan % 35% 82,833.33 28,991.67
JUMLAH HARGA BAHAN 128,391.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 148,218.67


E Overhead & Profit 10% 14,821.87
F Harga Satuan Pekerjaan (D+E) 163,040.53

A.5.1.1 22. Pemasangan 1 m’ pipa galvanis diameter 1 1/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa galvanis 1 1/4” M 1.2 109,333.33 131,200.00
Perlengkapan % 35% 109,333.33 38,266.67
JUMLAH HARGA BAHAN 169,466.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 203,436.67


E Overhead & Profit 10% 20,343.67
F Harga Satuan Pekerjaan (D+E) 223,780.33

A.5.1.1 22. Pemasangan 1 m’ pipa galvanis diameter 1 ½”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa galvanis 1 1/2” M 1.2 125,666.67 150,800.00
Perlengkapan % 35% 125,666.67 43,983.33
JUMLAH HARGA BAHAN 194,783.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 228,753.33


E Overhead & Profit 10% 22,875.33
F Harga Satuan Pekerjaan (D+E) 251,628.67

A.5.1.1 23. Pemasangan 1 m’ pipa galvanis diameter 2”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis 2” M 1.2 171,500.00 205,800.00
Perlengkapan % 35% 171,500.00 60,025.00
JUMLAH HARGA BAHAN 265,825.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 308,448.00


E Overhead & Profit 10% 30,844.80
F Harga Satuan Pekerjaan (D+E) 339,292.80

A.5.1.1 23. Pemasangan 1 m’ pipa galvanis diameter 2.5”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis 2.5” M 1.2 218,833.33 262,600.00
Perlengkapan % 35% 218,833.33 76,591.67
JUMLAH HARGA BAHAN 339,191.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 381,814.67


E Overhead & Profit 10% 38,181.47
F Harga Satuan Pekerjaan (D+E) 419,996.13

A.5.1.1 23. Pemasangan 1 m’ pipa galvanis diameter 3”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis 3” M 1.2 282,666.67 339,200.00
Perlengkapan % 35% 98,933.33 98,933.33
JUMLAH HARGA BAHAN 438,133.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 480,756.33


E Overhead & Profit 10% 48,075.63
F Harga Satuan Pekerjaan (D+E) 528,831.97

A.5.1.1 24. Pemasangan 1 m’ pipa galvanis diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis Medium 4” M 1.2 409,166.67 491,000.00
Perlengkapan % 35% 409,166.67 143,208.33
JUMLAH HARGA BAHAN 634,208.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 676,831.33


E Overhead & Profit 10% 67,683.13
F Harga Satuan Pekerjaan (D+E) 744,514.47

A.5.1.1.36. Pemasangan 1 m’ pipa GIP Underground diameter 100 cm/4 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa GIP Medium 4” Bh 1.2 409,166.67 491,000.00
Perlengkapan % 35% 409,166.67 143,208.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 655,133.93
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T
JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 720,680.93


E Overhead & Profit 10% 72,068.09
F Harga Satuan Pekerjaan (D+E) 792,749.03

A.8.4.1.36 Pemasangan 1 m pipa GIP Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.506 103,000.00 52,118.00
Tukang pipa L.02 OH 0.253 109,000.00 27,577.00
Mandor L.04 OH 0.051 116,000.00 5,916.00
JUMLAH TENAGA KERJA 85,611.00
B BAHAN
Pipa GIP Ø 150 mm 6" m 1 655,500.00 655,500.00
JUMLAH HARGA BAHAN 655,500.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T
JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 741,811.00


E Overhead & Profit (Contoh 15 %) 10% 74,181.10
F Harga Satuan Pekerjaan (D+E) 815,992.10

A.8.4.3.15 Pemasangan 1 buah Tee Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Tee GIP Ø 150 mm 6" bh 1 735,600.00 735,600.00
JUMLAH HARGA BAHAN 735,600.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 754,271.00


E Overhead & Profit (Contoh 15 %) 10% 75,427.10
F Harga Satuan Pekerjaan (D+E) 829,698.10

A.8.4.3.15 Pemasangan 1 buah Elbow Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Elbow GIP Medium Ø 150 mm 6" bh 1 269,000.00 269,000.00
JUMLAH HARGA BAHAN 269,000.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 287,671.00


E Overhead & Profit (Contoh 15 %) 10% 28,767.10
F Harga Satuan Pekerjaan (D+E) 316,438.10

A.5.1.1.36. Pemasangan 1 m’ pipa GIP MEDIUM Underground diameter 150 cm/6 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.506 103,000.00 52,118.00
Tukang Pipa L.02 OH 0.253 109,000.00 27,577.00
Kepala tukang L.03 OH 0.051 147,000.00 7,497.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 89,396.00
B BAHAN
Pipa GIP Medium 6” Bh 1 655,500.00 655,500.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 676,425.60
C PERALATAN

JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 765,821.60


E Overhead & Profit 10% 76,582.16
F Harga Satuan Pekerjaan (D+E) 842,403.76

A.5.1.1 18. Pemasangan 1 m’ pipa BS SCH 40 diameter ½”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa BS SCH 40 ½” M 1.2 32,541.67 39,050.00
Perlengkapan Ls 35% 32,541.67 11,389.58
JUMLAH HARGA BAHAN 50,439.58
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 70,266.58


E Overhead & Profit 10% 7,026.66
F Harga Satuan Pekerjaan (D+E) 77,293.24

A.5.1.1 20. Pemasangan 1 m’ pipa BS SCH 40 diameter 3/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa BS SCH 40 3/4” M 1.2 41,333.33 49,600.00
Perlengkapan % 35% 41,333.33 14,466.67
JUMLAH HARGA BAHAN 64,066.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 83,893.67


E Overhead & Profit 10% 8,389.37
F Harga Satuan Pekerjaan (D+E) 92,283.03

A.5.1.1 21. Pemasangan 1 m’ pipa BS SCH 40 diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa BS SCH 40 1” M 1.2 61,166.67 73,400.00
Perlengkapan % 35% 61,166.67 21,408.33
JUMLAH HARGA BAHAN 94,808.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 114,635.33


E Overhead & Profit 10% 11,463.53
F Harga Satuan Pekerjaan (D+E) 126,098.87

A.5.1.1 22. Pemasangan 1 m’ pipa BS SCH 40 diameter 1 1/4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa BS SCH 40 1 1/4” M 1.2 83,500.00 100,200.00
Perlengkapan % 35% 83,500.00 29,225.00
JUMLAH HARGA BAHAN 129,425.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 163,395.00


E Overhead & Profit 10% 16,339.50
F Harga Satuan Pekerjaan (D+E) 179,734.50

A.5.1.1 22. Pemasangan 1 m’ pipa BS SCH 40 diameter 1 ½”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa BS SCH 40 1 1/2” M 1.2 99,166.67 119,000.00
Perlengkapan % 35% 99,166.67 34,708.33
JUMLAH HARGA BAHAN 153,708.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 187,678.33


E Overhead & Profit 10% 18,767.83
F Harga Satuan Pekerjaan (D+E) 206,446.17

A.5.1.1 23. Pemasangan 1 m’ pipa BS SCH 40 diameter 2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 2” M 1.2 132,500.00 159,000.00
Perlengkapan % 35% 132,500.00 46,375.00
JUMLAH HARGA BAHAN 205,375.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 247,998.00


E Overhead & Profit 10% 24,799.80
F Harga Satuan Pekerjaan (D+E) 272,797.80

A.5.1.1 23. Pemasangan 1 m’ pipa BS SCH 40 diameter 2.5”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 2.5” M 1.2 211,166.67 253,400.00
Perlengkapan % 35% 211,166.67 73,908.33
JUMLAH HARGA BAHAN 327,308.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 369,931.33


E Overhead & Profit 10% 36,993.13
F Harga Satuan Pekerjaan (D+E) 406,924.47

A.5.1.1 23. Pemasangan 1 m’ pipa BS SCH 40 diameter 3”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 3” M 1.2 312,541.67 375,050.00
Perlengkapan % 35% 312,541.67 109,389.58
JUMLAH HARGA BAHAN 484,439.58
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 527,062.58


E Overhead & Profit 10% 52,706.26
F Harga Satuan Pekerjaan (D+E) 579,768.84

A.5.1.1 24. Pemasangan 1 m’ pipa BS SCH 40 diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 4” M 1.2 391,833.33 470,200.00
Perlengkapan % 35% 391,833.33 137,141.67
JUMLAH HARGA BAHAN 607,341.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 649,964.67


E Overhead & Profit 10% 64,996.47
F Harga Satuan Pekerjaan (D+E) 714,961.13

A.5.1.1 24. Pemasangan 1 m’ pipa BS SCH 40 diameter 5”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 5” M 1.2 530,166.67 636,200.00
Perlengkapan % 35% 530,166.67 185,558.33
JUMLAH HARGA BAHAN 821,758.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 864,381.33


E Overhead & Profit 10% 86,438.13
F Harga Satuan Pekerjaan (D+E) 950,819.47

A.5.1.1 24. Pemasangan 1 m’ pipa BS SCH 40 diameter 6”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 6” M 1.2 685,166.67 822,200.00
Perlengkapan % 35% 685,166.67 239,808.33
JUMLAH HARGA BAHAN 1,062,008.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,104,631.33


E Overhead & Profit 10% 110,463.13
F Harga Satuan Pekerjaan (D+E) 1,215,094.47

A.5.1.1.36. Pemasangan 1 m’ pipa BS SCH 40 Underground diameter 100 cm/4 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa BS SCH 40 4” Bh 1.2 391,833.33 470,200.00
Perlengkapan % 35% 137,141.67 47,999.58
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 539,125.18
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 603,972.18


E Overhead & Profit 10% 60,397.22
F Harga Satuan Pekerjaan (D+E) 664,369.40

A.8.4.1.66 Pemasangan 1 m pipa baja Ø 125 mm/5"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.648 103,000.00 66,744.00
Tukang pipa L.02 OH 0.13 109,000.00 14,170.00
Mandor L.04 OH 0.065 116,000.00 7,540.00
JUMLAH TENAGA KERJA 88,454.00
B BAHAN
Pipa Baja Ø 125 mm m 1.2 530,166.67 636,200.00
JUMLAH TENAGA KERJA 636,200.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.004 25,000.00 100.00
handle crane 2 T
JUMLAH HARGA ALAT 100.00
D Jumlah (A+B+C) 724,754.00
E Overhead & Profit (Contoh 15 %) 10% 72,475.40
F Harga Satuan Pekerjaan (D+E) 797,229.40

A.8.4.3.15 Pemasangan 1 buah Tee Ø 125 mm/ 5"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Tee BS SCH 40 Ø 125 mm bh 1 635,000.00 635,000.00
JUMLAH HARGA BAHAN 635,000.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 653,671.00


E Overhead & Profit (Contoh 15 %) 10% 65,367.10
F Harga Satuan Pekerjaan (D+E) 719,038.10

A.8.4.3.15 Pemasangan 1 buah Elbow Ø 125 mm/ 5"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Elbow BS SCH40 Ø 125 mm bh 1 203,000.00 203,000.00
JUMLAH HARGA BAHAN 203,000.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T
JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 221,671.00


E Overhead & Profit (Contoh 15 %) 10% 22,167.10
F Harga Satuan Pekerjaan (D+E) 243,838.10

A.5.1.1.36. Pemasangan 1 m’ pipa GIP Underground diameter 125 cm/5 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.648 103,000.00 66,744.00
Tukang Pipa L.02 OH 0.13 109,000.00 14,170.00
Kepala tukang L.03 OH 0.065 147,000.00 9,555.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 92,673.00
B BAHAN
Pipa BS SCH 40 5” Bh 1.1 530,166.67 583,183.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 604,108.93
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00

D Jumlah (A+B+C) 696,781.93


E Overhead & Profit 10% 69,678.19
F Harga Satuan Pekerjaan (D+E) 766,460.13

A.8.4.1.67 Pemasangan 1 m pipa baja Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.708 103,000.00 72,924.00
Tukang pipa L.02 OH 0.142 109,000.00 15,478.00
Mandor L.04 OH 0.071 116,000.00 8,236.00
JUMLAH TENAGA KERJA 96,638.00
B BAHAN
Pipa Baja Ø 150 mm 6" m 1 685,166.67 685,166.67
JUMLAH TENAGA KERJA 685,166.67
C PERALATAN
Sewa Tripot/Tackel & hari 0.004 25,000.00 100.00
handle crane 2 T
JUMLAH HARGA ALAT 100.00
D Jumlah (A+B+C) 781,904.67
E Overhead & Profit (Contoh 15 %) 10% 78,190.47
F Harga Satuan Pekerjaan (D+E) 860,095.13

A.8.4.3.15 Pemasangan 1 buah Tee Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Tee BS SCH 40 Ø 150 mm bh 1 780,000.00 780,000.00
JUMLAH HARGA BAHAN 780,000.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 798,671.00


E Overhead & Profit (Contoh 15 %) 10% 79,867.10
F Harga Satuan Pekerjaan (D+E) 878,538.10

A.8.4.3.15 Pemasangan 1 buah Elbow Ø 150 mm/ 6"

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00

JUMLAH TENAGA KERJA 17,971.00


B BAHAN
Elbow BS SCH 40 Ø 150 mm 6" bh 1 265,000.00 265,000.00
JUMLAH HARGA BAHAN 265,000.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T

JUMLAH HARGA ALAT 700.00

D Jumlah (A+B+C) 283,671.00


E Overhead & Profit (Contoh 15 %) 10% 28,367.10
F Harga Satuan Pekerjaan (D+E) 312,038.10

A.5.1.1.36. Pemasangan 1 m’ pipa BS SCH 40 Underground diameter 150 cm/6 "

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.708 103,000.00 72,924.00
Tukang Pipa L.02 OH 0.142 109,000.00 15,478.00
Kepala tukang L.03 OH 0.071 147,000.00 10,437.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 101,043.00
B BAHAN
Pipa BS SCH 40 DIA 6” Bh 1.1 685,166.67 753,683.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 774,608.93
C PERALATAN
0.00
JUMLAH HARGA ALAT 0

D Jumlah (A+B+C) 875,651.93


E Overhead & Profit 10% 87,565.19
F Harga Satuan Pekerjaan (D+E) 963,217.13
A.8.4.3.1 Pemasangan 1 buah Valve Ø 4"
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.429 103,000.00 147,187.00
Tukang pipa L.02 OH 0.715 109,000.00 77,935.00
Mandor L.04 OH 0.143 116,000.00 16,588.00

JUMLAH TENAGA KERJA 241,710.00


B BAHAN
Valve Ø 4" bh 1 2,454,000.00 2,454,000.00
Material Bantu % 20% 2,454,000.00 490,800.00
JUMLAH HARGA BAHAN 2,944,800.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.1 25,000.00 2,500.00
handle crane 2 T
JUMLAH HARGA ALAT 2,500.00

D Jumlah (A+B+C) 3,189,010.00


E Overhead & Profit (Contoh 15 %) 10% 318,901.00
F Harga Satuan Pekerjaan (D+E) 3,507,911.00

A.8.4.3.1 Pemasangan 1 buah Valve Ø 6"


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.429 103,000.00 147,187.00
Tukang pipa L.02 OH 0.715 109,000.00 77,935.00
Mandor L.04 OH 0.143 116,000.00 16,588.00

JUMLAH TENAGA KERJA 241,710.00


B BAHAN
Valve Ø 6" bh 1 4,737,000.00 4,737,000.00
Material Bantu % 20% 4,737,000.00 947,400.00
JUMLAH HARGA BAHAN 5,684,400.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.1 25,000.00 2,500.00
handle crane 2 T
JUMLAH HARGA ALAT 2,500.00

D Jumlah (A+B+C) 5,928,610.00


E Overhead & Profit (Contoh 15 %) 10% 592,861.00
F Harga Satuan Pekerjaan (D+E) 6,521,471.00

A.8.4.4.1 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 3"


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.466 103,000.00 150,998.00
Tukang pipa L.02 OH 0.733 109,000.00 79,897.00
Mandor L.04 OH 0.147 116,000.00 17,052.00
JUMLAH TENAGA KERJA 247,947.00
B BAHAN
Pipa Ø 80 mm bh 1 0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw hari 0.606 100,000.00 60,600.00
Sewa Genset 1500 hari 0.075 150,000.00 11,250.00
watt
Sewa Pompa hari 0.968 75,000.00 72,600.00
Submersible 3m3/h
Sewa Tripot/Tackel & hari 0.865 25,000.00 21,625.00
handle crane 2 T
JUMLAH HARGA ALAT 166,075.00

D Jumlah (A+B+C) 414,022.00


E Overhead & Profit (Contoh 15 %) 10% 41,402.20
F Harga Satuan Pekerjaan (D+E) 455,424.20

A.8.4.4.2 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.646 103,000.00 169,538.00
Tukang pipa L.02 OH 0.823 109,000.00 89,707.00
Mandor L.04 OH 0.165 116,000.00 19,140.00
JUMLAH TENAGA KERJA 278,385.00
B BAHAN
Pipa Ø 100 mm bh 1 0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
Peralatan potong pipa hari 0.65 100,000.00 65,000.00
T2/mekanik / cilinder saw
Sewa Genset 1500 hari 0.159 150,000.00 23,850.00
watt
Sewa Pompa hari 1.078 75,000.00 80,850.00
Submersible 3m3/h
Sewa Tripot/Tackel & hari 0.911 25,000.00 22,775.00
handle crane 2 T
JUMLAH HARGA ALAT 192,475.00
D Jumlah (A+B+C) 470,860.00
E Overhead & Profit (Contoh 15 %) 10% 47,086.00
F Harga Satuan Pekerjaan (D+E) 517,946.00

A.8.4.4.3 Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.096 103,000.00 215,888.00
Tukang pipa L.02 OH 1.048 109,000.00 114,232.00
Mandor L.04 OH 0.21 116,000.00 24,360.00

JUMLAH TENAGA KERJA 354,480.00


B BAHAN
Pipa Ø 150 mm bh 1 0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw hari 0.76 100,000.00 76,000.00
Sewa Genset 1500 hari 0.369 150,000.00 55,350.00
watt
Sewa Pompa hari 1.353 75,000.00 101,475.00
Submersible 3m3/h
Sewa Tripot/Tackel & hari 1.026 25,000.00 25,650.00
handle crane 2 T
JUMLAH HARGA ALAT 258,475.00
D Jumlah (A+B+C) 612,955.00
E Overhead & Profit (Contoh 15 %) 10% 61,295.50
F Harga Satuan Pekerjaan (D+E) 674,250.50

Empiris. M1 Pasang Besi Gutter

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah


A TENAGA (Rp) Harga
Pekerja L.01 OH 0.015 103,000.00 (Rp)
1,545.00
Tukang L.02 OH 0.25 109,000.00 27,250.00
Kepala Tukang L.03 OH 0.115 147,000.00 16,905.00
Mandor L.04 OH 0.0009 116,000.00 104.40
JUMLAH TENAGA KERJA 45,804.40
B BAHAN
Besi Siku 5cm x 5cm x 6m m1 2.4 75,666.67 181,600.00
Besi polos 8 mm m1 3.9 42,000.00 163,800.00
Perlengkapan % 10% 42,000.00 4,200.00
JUMLAH HARGA BAHAN 349,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 395,404.40


E Overhead & Profit 10% 39,540.44
F Harga Satuan Pekerjaan (D+E) 434,944.84

Empiris. Pemasangan 1 buah Septic tank pasangan bata 1X3 tinggi 1 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0 -
Tukang batu L.02 OH 0 -
Kepala tukang L.03 OH 0 -
Mandor L.04 OH 0 -

JUMLAH TENAGA KERJA -


B BAHAN
Menggali Tanah A. 2.3.1.2 m3 3 85,635.00 256,905.00
SL-10/15 A.4.1.1.36 m1 16 160,179.25 2,562,868.00
KL-11/11 A.4.1.1.35 m1 10 134,431.00 1,344,310.00
BL-10/15 A.4.1.1.36 m1 16 160,179.25 2,562,868.00
Pasir Urug A.2.3.1.11 m3 0.3 289,850.00 86,955.00
Beton Tumbuk-K125 A.4.2.1.3 m3 0.3 1,250,260.00 375,078.00
Beton K-300 A.4.1.1.10 m3 0.33 1,428,570.00 471,428.10
Besi Tulangan A.4.1.1.17 kg 25.96 14,537.00 377,380.52
Bekisting A.4.1.1.21 m2 5.67 174,570.00 989,811.90
Pas. Dinding press adukan 1:2 m2 16 167,586.00 2,681,376.00
Pas. Plesteran &acian dinding 1:2 m2 0 103,778.00 -
JUMLAH HARGA BAHAN 11,708,980.52
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,708,980.52


E Overhead & Profit 10% 1,170,898.05
F Harga Satuan Pekerjaan (D+E) 12,879,878.57

Empiris 3. Pembuatan 1 buah Sumur Resapan

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0 -
Tukang batu L.02 OH 0 -
Kepala tukang L.03 OH 0 -
Mandor L.04 OH 0 -
JUMLAH TENAGA KERJA -
B BAHAN
Penggalian Tanah A. 2.3.1.3. m3 4.225184 79,200.00 334,634.57
Pas. Buis Beton dia 80x50 cm Empiris 1 m1 4 437,277.50 1,749,110.00
Pas. Lapisan Ijuk A. 2.3.1.13 m2 1.056296 451,080.00 476,474.00
Urugan Pasir A. 2.3.1.11 m3 0.17957032 289,850.00 52,048.46
Pas. Batu Koral Empiris 2 m3 0.264074 520,850.00 137,542.94
Beton Bertulang m3 0.16900736 1,668,000.00 281,904.28
Pipa saluran 4" A.5.1.1 32 m1 1.32 79,887.50 105,451.50
JUMLAH HARGA BAHAN 2,802,531.18
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,802,531.18


E Overhead & Profit 10% 280,253.12
F Harga Satuan Pekerjaan (D+E) 3,082,784.29

Empiris. Pemasangan 1 buah bak kontrol beton 75x75 tinggi 75cm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 3.2 80,000.00 256,000.00
Tukang batu L.02 OH 1.15 100,000.00 115,000.00
Kepala tukang L.03 OH 0.011 120,000.00 1,320.00
Mandor L.04 OH 0.016 130,000.00 2,080.00

JUMLAH TENAGA KERJA 374,400.00


B BAHAN
Menggali Tanah A. 2.3.1.2 m3 0.421875 85,635.00 36,127.27
Bata Merah bh 123 1,150.00 141,450.00
Semen Portland kg 114 1,400.00 159,600.00
Pasir Pasang m3 0.184 225,000.00 41,400.00
Pasir Beton m3 0.12 225,000.00 27,000.00
Kerikil m3 0.033 375,000.00 12,375.00
Baja Tulangan kg 4.85 12,000.00 58,200.00
JUMLAH HARGA BAHAN 476,152.27
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 850,552.27


E Overhead & Profit 10% 85,055.23
F Harga Satuan Pekerjaan (D+E) 935,607.49

PENAMBAHAN

Empiris. Kabel Tray Ukuran 300 x 100 mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Tray 300 x 100 mm m 1 240,000.00 240,000.00
Support unit 1 10,500.00 10,500.00
Material & Alat bantu 5% 240,000.00 12,000.00
JUMLAH HARGA BAHAN 262,500.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 300,000.00


D Overhead & Profit 10% 30,000.00
E Harga Satuan Pekerjaan (C+D) 330,000.00

Empiris. Kabel Tray Ukuran 200 x 100 mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Tray 200 x 100 mm m 1 192,000.00 192,000.00
Support unit 1 10,500.00 10,500.00
Material & Alat bantu 5% 192,000.00 9,600.00
JUMLAH HARGA BAHAN 212,100.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 249,600.00


D Overhead & Profit 10% 24,960.00
E Harga Satuan Pekerjaan (C+D) 274,560.00

Empiris. Kabel Tray Ukuran 100 x 100 mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Tray 100 x 100 mm m 1 168,000.00 168,000.00
Support unit 1 10,500.00 10,500.00
Material & Alat bantu 5% 168,000.00 8,400.00
JUMLAH HARGA BAHAN 186,900.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 224,400.00


D Overhead & Profit 10% 22,440.00
E Harga Satuan Pekerjaan (C+D) 246,840.00

Empiris. Kabel NYY 4 x 240 mm²+ BC 120 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 240 mm² m 1 1,530,000.00 1,530,000.00
BC 120 mm² m 1 113,500.00 113,500.00
Material & Alat bantu 5% 1,643,500.00 82,175.00
JUMLAH HARGA BAHAN 1,725,675.00
B PERALATAN
Upah OH 1 54,000.00 54,000.00
JUMLAH HARGA ALAT 54,000.00

C Jumlah (A+B) 1,779,675.00


D Overhead & Profit 10% 177,967.50
E Harga Satuan Pekerjaan (C+D) 1,957,642.50

Empiris. Kabel NYY 4 x 120 mm²+ BC 120 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 120 mm² m 1 764,000.00 764,000.00
BC 120 mm² m 1 113,500.00 113,500.00
Material & Alat bantu 5% 877,500.00 43,875.00
JUMLAH HARGA BAHAN 921,375.00
B PERALATAN
Upah OH 1 30,000.00 30,000.00
JUMLAH HARGA ALAT 30,000.00

C Jumlah (A+B) 951,375.00


D Overhead & Profit 10% 95,137.50
E Harga Satuan Pekerjaan (C+D) 1,046,512.50

Empiris. Kabel NYY 4 x 4 mm²+ BC 4 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 4 mm² m 1 58,000.00 58,000.00
BC 4 mm² m 1 5,700.00 5,700.00
Material & Alat bantu 5% 63,700.00 3,185.00
JUMLAH HARGA BAHAN 66,885.00
B PERALATAN
Upah OH 1 1,000.00 1,000.00
JUMLAH HARGA ALAT 1,000.00

C Jumlah (A+B) 67,885.00


D Overhead & Profit 10% 6,788.50
E Harga Satuan Pekerjaan (C+D) 74,673.50

Empiris. Kabel NYY 4 x 6 mm²+ BC 6 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 6 mm² m 1 72,000.00 72,000.00
BC 6 mm² m 1 7,050.00 7,050.00
Material & Alat bantu 5% 79,050.00 3,952.50
JUMLAH HARGA BAHAN 83,002.50
B PERALATAN
Upah OH 1 1,500.00 1,500.00
JUMLAH HARGA ALAT 1,500.00

C Jumlah (A+B) 84,502.50


D Overhead & Profit 10% 8,450.25
E Harga Satuan Pekerjaan (C+D) 92,952.75

Empiris. Kabel NYY 4 x 16 mm²+ BC 16 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 16 mm² m 1 111,000.00 111,000.00
BC 16 mm² m 1 16,650.00 16,650.00
Material & Alat bantu 5% 127,650.00 6,382.50
JUMLAH HARGA BAHAN 134,032.50
B PERALATAN
Upah OH 1 4,000.00 4,000.00
JUMLAH HARGA ALAT 4,000.00

C Jumlah (A+B) 138,032.50


D Overhead & Profit 10% 13,803.25
E Harga Satuan Pekerjaan (C+D) 151,835.75

Empiris. Kabel NYY 4 x 25 mm²+ BC 25 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 25 mm² m 1 197,500.00 197,500.00
BC 25 mm² m 1 39,500.00 39,500.00
Material & Alat bantu 5% 237,000.00 11,850.00
JUMLAH HARGA BAHAN 248,850.00
B PERALATAN
Upah OH 1 4,000.00 4,000.00
JUMLAH HARGA ALAT 4,000.00

C Jumlah (A+B) 252,850.00


D Overhead & Profit 10% 25,285.00
E Harga Satuan Pekerjaan (C+D) 278,135.00

Empiris. Kabel NYY 4 x 95 mm²+ BC 95 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 95 mm² m 1 610,000.00 610,000.00
BC 95 mm² m 1 98,750.00 98,750.00
Material & Alat bantu 5% 708,750.00 35,437.50
JUMLAH HARGA BAHAN 744,187.50
B PERALATAN
Upah OH 1 23,750.00 23,750.00
JUMLAH HARGA ALAT 23,750.00

C Jumlah (A+B) 767,937.50


D Overhead & Profit 10% 76,793.75
E Harga Satuan Pekerjaan (C+D) 844,731.25

Empiris. Kabel NYY 4 x 50 mm²+ BC 50 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 50 mm² m 1 314,000.00 314,000.00
BC 50 mm² m 1 36,700.00 36,700.00
Material & Alat bantu 5% 350,700.00 17,535.00
JUMLAH HARGA BAHAN 368,235.00
B PERALATAN
Upah OH 1 12,500.00 12,500.00
JUMLAH HARGA ALAT 12,500.00

C Jumlah (A+B) 380,735.00


D Overhead & Profit 10% 38,073.50
E Harga Satuan Pekerjaan (C+D) 418,808.50

Empiris. Kabel NYY 4 x 10 mm²+ BC 10 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 10 mm² m 1 98,000.00 98,000.00
BC 10 mm² m 1 11,400.00 11,400.00
Material & Alat bantu 5% 109,400.00 5,470.00
JUMLAH HARGA BAHAN 114,870.00
B PERALATAN
Upah OH 1 2,500.00 2,500.00
JUMLAH HARGA ALAT 2,500.00

C Jumlah (A+B) 117,370.00


D Overhead & Profit 10% 11,737.00
E Harga Satuan Pekerjaan (C+D) 129,107.00

Empiris. Kabel NYY 4 x 10 mm²+ BC 10 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 10 mm² m 1 98,000.00 98,000.00
BC 10 mm² m 1 11,400.00 11,400.00
Material & Alat bantu 5% 109,400.00 5,470.00
JUMLAH HARGA BAHAN 114,870.00
B PERALATAN
Upah OH 1 2,500.00 2,500.00
JUMLAH HARGA ALAT 2,500.00

C Jumlah (A+B) 117,370.00


D Overhead & Profit 10% 11,737.00
E Harga Satuan Pekerjaan (C+D) 129,107.00

Empiris. Kabel NYY 4 x 185 mm²+ BC 120 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 185 mm² m 1 1,169,000.00 1,169,000.00
BC 120 mm² m 1 113,500.00 113,500.00
Material & Alat bantu 5% 1,282,500.00 64,125.00
JUMLAH HARGA BAHAN 1,346,625.00
B PERALATAN
Upah OH 1 43,000.00 43,000.00
JUMLAH HARGA ALAT 43,000.00

C Jumlah (A+B) 1,389,625.00


D Overhead & Profit 10% 138,962.50
E Harga Satuan Pekerjaan (C+D) 1,528,587.50

Empiris. Kabel NYY 4 x 185 mm²+ BC 120 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 185 mm² m 1 1,169,000.00 1,169,000.00
BC 120 mm² m 1 113,500.00 113,500.00
Material & Alat bantu 5% 1,282,500.00 64,125.00
JUMLAH HARGA BAHAN 1,346,625.00
B PERALATAN
Upah OH 1 43,000.00 43,000.00
JUMLAH HARGA ALAT 43,000.00

C Jumlah (A+B) 1,389,625.00


D Overhead & Profit 10% 138,962.50
E Harga Satuan Pekerjaan (C+D) 1,528,587.50

Empiris. Kabel NYY 4 x 2.5 mm²+ BC 2.5 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 2.5 mm² m 1 40,000.00 40,000.00
BC 2.5 mm² m 1 4,125.00 4,125.00
Material & Alat bantu 5% 44,125.00 2,206.25
JUMLAH HARGA BAHAN 46,331.25
B PERALATAN
Upah OH 1 625.00 625.00
JUMLAH HARGA ALAT 625.00

C Jumlah (A+B) 46,956.25


D Overhead & Profit 10% 4,695.63
E Harga Satuan Pekerjaan (C+D) 51,651.88

Empiris. Kabel NYY 5 x 2.5 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 5 x 2.5 mm² m 1 50,000.00 50,000.00
Material & Alat bantu 5% 50,000.00 2,500.00
JUMLAH HARGA BAHAN 52,500.00
B PERALATAN
Upah OH 1 625.00 625.00
JUMLAH HARGA ALAT 625.00

C Jumlah (A+B) 53,125.00


D Overhead & Profit 10% 5,312.50
E Harga Satuan Pekerjaan (C+D) 58,437.50

Empiris. Kabel NYY 4 x 95 mm²+ NYA 70 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 95 mm² m 1 610,000.00 610,000.00
NYA 70 mm² m 1 54,000.00 54,000.00
Material & Alat bantu 5% 664,000.00 33,200.00
JUMLAH HARGA BAHAN 697,200.00
B PERALATAN
Upah OH 1 27,250.00 27,250.00
JUMLAH HARGA ALAT 27,250.00

C Jumlah (A+B) 724,450.00


D Overhead & Profit 10% 72,445.00
E Harga Satuan Pekerjaan (C+D) 796,895.00

Empiris. Kabel NYY 4 x 70 mm²+ NYA 50 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 70 mm² m 1 444,000.00 444,000.00
NYA 50 mm² m 1 54,000.00 54,000.00
Material & Alat bantu 5% 498,000.00 24,900.00
JUMLAH HARGA BAHAN 522,900.00
B PERALATAN
Upah OH 1 20,000.00 20,000.00
JUMLAH HARGA ALAT 20,000.00

C Jumlah (A+B) 542,900.00


D Overhead & Profit 10% 54,290.00
E Harga Satuan Pekerjaan (C+D) 597,190.00

Empiris. Kabel NYY 4 x 70 mm²+ NYA 50 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYY 4 x 70 mm² m 1 444,000.00 444,000.00
NYA 50 mm² m 1 54,000.00 54,000.00
Material & Alat bantu 5% 498,000.00 24,900.00
JUMLAH HARGA BAHAN 522,900.00
B PERALATAN
Upah OH 1 20,000.00 20,000.00
JUMLAH HARGA ALAT 20,000.00

C Jumlah (A+B) 542,900.00


D Overhead & Profit 10% 54,290.00
E Harga Satuan Pekerjaan (C+D) 597,190.00

Empiris. Kabel NYFGBY 4 x 6 mm²+ BC 6 mm²


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYFGBY 4 x 6 mm² m 1 55,000.00 55,000.00
BC 6 mm² m 1 7,050.00 7,050.00
Material & Alat bantu 5% 62,050.00 3,102.50
JUMLAH HARGA BAHAN 65,152.50
B PERALATAN
Upah OH 1 1,500.00 1,500.00
JUMLAH HARGA ALAT 1,500.00

C Jumlah (A+B) 66,652.50


D Overhead & Profit 10% 6,665.25
E Harga Satuan Pekerjaan (C+D) 73,317.75

Empiris. Kabel NYFGBY 4 x 16 mm²+ BC 16 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYFGBY 4 x 16 mm² m 1 108,375.00 108,375.00
BC 16 mm² m 1 16,650.00 16,650.00
Material & Alat bantu 5% 125,025.00 6,251.25
JUMLAH HARGA BAHAN 131,276.25
B PERALATAN
Upah OH 1 4,000.00 4,000.00
JUMLAH HARGA ALAT 4,000.00

C Jumlah (A+B) 135,276.25


D Overhead & Profit 10% 13,527.63
E Harga Satuan Pekerjaan (C+D) 148,803.88

Empiris. Kabel FRC 4 x 95 mm²+ BC 70 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
FRC 4 x 95 mm² m 1 650,000.00 650,000.00
BC 70 mm² m 1 53,600.00 53,600.00
Material & Alat bantu 5% 703,600.00 35,180.00
JUMLAH HARGA BAHAN 738,780.00
B PERALATAN
Upah OH 1 22,500.00 22,500.00
JUMLAH HARGA ALAT 22,500.00

C Jumlah (A+B) 761,280.00


D Overhead & Profit 10% 76,128.00
E Harga Satuan Pekerjaan (C+D) 837,408.00

Empiris. Kabel FRC 4 x 4 mm²+ BC 4 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
FRC 4 x 4 mm² m 1 63,000.00 63,000.00
BC 4 mm² m 1 5,700.00 5,700.00
Material & Alat bantu 5% 68,700.00 3,435.00
JUMLAH HARGA BAHAN 72,135.00
B PERALATAN
Upah OH 1 1,000.00 1,000.00
JUMLAH HARGA ALAT 1,000.00

C Jumlah (A+B) 73,135.00


D Overhead & Profit 10% 7,313.50
E Harga Satuan Pekerjaan (C+D) 80,448.50
Empiris. Kabel FRC 4 x 16 mm²+ BC 16 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
FRC 4 x 16 mm² m 1 226,500.00 226,500.00
BC 4 mm² m 1 5,700.00 5,700.00
Material & Alat bantu 5% 232,200.00 11,610.00
JUMLAH HARGA BAHAN 243,810.00
B PERALATAN
Upah OH 1 1,000.00 1,000.00
JUMLAH HARGA ALAT 1,000.00

C Jumlah (A+B) 244,810.00


D Overhead & Profit 10% 24,481.00
E Harga Satuan Pekerjaan (C+D) 269,291.00

Empiris. Kabel Backbone Data UTP Cat6

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel Backbone Data UTP Cat6 m 1 5,566.67 5,566.67
Conduit 20mm btg 0.37 10,500.00 3,885.00
Material & Alat bantu 5% 9,451.67 472.58
JUMLAH HARGA BAHAN 9,924.25
B PERALATAN
Upah OH 1 7,000.00 7,000.00
JUMLAH HARGA ALAT 7,000.00

C Jumlah (A+B) 16,924.25


D Overhead & Profit 10% 1,692.43
E Harga Satuan Pekerjaan (C+D) 18,616.68

Empiris. Coaxial cable RG 11 dlm PVC Conduit HI Ø 20mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Coaxial cable RG 11 m 1 6,800.00 6,800.00
Conduit 20mm btg 0.37 10,500.00 3,885.00
Material & Alat bantu 5% 10,685.00 534.25
JUMLAH HARGA BAHAN 11,219.25
B PERALATAN
Upah OH 1 7,000.00 7,000.00
JUMLAH HARGA ALAT 7,000.00

C Jumlah (A+B) 18,219.25


D Overhead & Profit 10% 1,821.93
E Harga Satuan Pekerjaan (C+D) 20,041.18

Empiris. Kabel NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
NYMHY 3x2.5 mm² m 1 6,200.00 6,200.00
Conduit 20mm btg 0.37 10,500.00 3,885.00
Material & Alat bantu 5% 10,085.00 504.25
JUMLAH HARGA BAHAN 10,589.25
B PERALATAN
Upah OH 1 7,000.00 7,000.00
JUMLAH HARGA ALAT 7,000.00

C Jumlah (A+B) 17,589.25


D Overhead & Profit 10% 1,758.93
E Harga Satuan Pekerjaan (C+D) 19,348.18

Empiris. Kabel Ladder W:400mm H:100mm, tebal plat 2mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel Ladder W=400 H=100 m 1 178,000.00 178,000.00
Material & Alat bantu 5% 178,000.00 8,900.00
JUMLAH HARGA BAHAN 186,900.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 224,400.00


D Overhead & Profit 10% 22,440.00
E Harga Satuan Pekerjaan (C+D) 246,840.00

Empiris. Kabel Ladder W:600mm H:100mm, tebal plat 2mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel Ladder W=600 H=100 m 1 206,000.00 206,000.00
Material & Alat bantu 5% 206,000.00 10,300.00
JUMLAH HARGA BAHAN 216,300.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 253,800.00


D Overhead & Profit 10% 25,380.00
E Harga Satuan Pekerjaan (C+D) 279,180.00

Empiris. Kabel Ladder W:800mm H:100mm, tebal plat 2mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel Ladder W=800 H=100 m 1 250,000.00 250,000.00
Material & Alat bantu 5% 250,000.00 12,500.00
JUMLAH HARGA BAHAN 262,500.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 300,000.00


D Overhead & Profit 10% 30,000.00
E Harga Satuan Pekerjaan (C+D) 330,000.00

Empiris. Kabel Ladder W:1000mm H:100mm, tebal plat 2mm

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel Ladder W=1000 H=100 m 1 260,000.00 260,000.00
Material & Alat bantu 5% 260,000.00 13,000.00
JUMLAH HARGA BAHAN 273,000.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 310,500.00


D Overhead & Profit 10% 31,050.00
E Harga Satuan Pekerjaan (C+D) 341,550.00

Empiris. Kabel NYY 4 x 185 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel NYY 4 x 185 mm² m 1 1,169,000.00 1,169,000.00
Material & Alat bantu 5% 1,169,000.00 58,450.00
JUMLAH HARGA BAHAN 1,227,450.00
B PERALATAN
Upah OH 1 37,000.00 37,000.00
JUMLAH HARGA ALAT 37,000.00

C Jumlah (A+B) 1,264,450.00


D Overhead & Profit 10% 126,445.00
E Harga Satuan Pekerjaan (C+D) 1,390,895.00

Empiris. Kabel N2XSY 3 x 95 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel N2XSY 3 x 95 mm² m 1 497,000.00 497,000.00
Material & Alat bantu 5% 497,000.00 24,850.00
JUMLAH HARGA BAHAN 521,850.00
B PERALATAN
Upah OH 1 14,250.00 14,250.00
JUMLAH HARGA ALAT 14,250.00

C Jumlah (A+B) 536,100.00


D Overhead & Profit 10% 53,610.00
E Harga Satuan Pekerjaan (C+D) 589,710.00

Empiris. Kabel N2XSEBY 3 x 120 mm²

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Kabel N2XSEBY 3 x 120 mm² m 1 548,000.00 548,000.00
Material & Alat bantu 5% 548,000.00 27,400.00
JUMLAH HARGA BAHAN 575,400.00
B PERALATAN
Upah OH 1 18,000.00 18,000.00
JUMLAH HARGA ALAT 18,000.00

C Jumlah (A+B) 593,400.00


D Overhead & Profit 10% 59,340.00
E Harga Satuan Pekerjaan (C+D) 652,740.00

Empiris. Pipa Tembaga Diameter 1/4 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 1/4 " m1 1.2 14,500.00 17,400.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 51,360.00 10,272.00
JUMLAH HARGA BAHAN 61,632.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 121,632.00


D Overhead & Profit 10% 12,163.20
E Harga Satuan Pekerjaan (C+D) 133,795.20

Empiris. Pipa Tembaga Diameter 3/8 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 3/8 " m1 1.2 22,400.00 26,880.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 60,840.00 12,168.00
JUMLAH HARGA BAHAN 73,008.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 133,008.00


D Overhead & Profit 10% 13,300.80
E Harga Satuan Pekerjaan (C+D) 146,308.80

Empiris. Pipa Tembaga Diameter 1/2 "


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 1/2 " m1 1.2 33,000.00 39,600.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 73,560.00 14,712.00
JUMLAH HARGA BAHAN 88,272.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 148,272.00


D Overhead & Profit 10% 14,827.20
E Harga Satuan Pekerjaan (C+D) 163,099.20

Empiris. Pipa Tembaga Diameter 5/8 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 5/8 " m1 1.2 50,000.00 60,000.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 93,960.00 18,792.00
JUMLAH HARGA BAHAN 112,752.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 172,752.00


D Overhead & Profit 10% 17,275.20
E Harga Satuan Pekerjaan (C+D) 190,027.20

Empiris. Pipa Tembaga Diameter 3/4 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 3/4 " m1 1.2 78,000.00 93,600.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 127,560.00 25,512.00
JUMLAH HARGA BAHAN 153,072.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 213,072.00


D Overhead & Profit 10% 21,307.20
E Harga Satuan Pekerjaan (C+D) 234,379.20

Empiris. Pipa Tembaga Diameter 1 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 1 " m1 1.2 95,000.00 114,000.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 147,960.00 29,592.00
JUMLAH HARGA BAHAN 177,552.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 237,552.00


D Overhead & Profit 10% 23,755.20
E Harga Satuan Pekerjaan (C+D) 261,307.20

Empiris. Pipa Tembaga Diameter 1 1/4 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 1 1/4 " m1 1.2 112,000.00 134,400.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 168,360.00 33,672.00
JUMLAH HARGA BAHAN 202,032.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 262,032.00


D Overhead & Profit 10% 26,203.20
E Harga Satuan Pekerjaan (C+D) 288,235.20

Empiris. Pipa Tembaga Diameter 1 1/2 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 1 1/2 " m1 1.2 125,000.00 150,000.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 183,960.00 36,792.00
JUMLAH HARGA BAHAN 220,752.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 280,752.00


D Overhead & Profit 10% 28,075.20
E Harga Satuan Pekerjaan (C+D) 308,827.20

Empiris. Pipa Tembaga Diameter 2 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 2 " m1 1.2 185,000.00 222,000.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 255,960.00 51,192.00
JUMLAH HARGA BAHAN 307,152.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 367,152.00


D Overhead & Profit 10% 36,715.20
E Harga Satuan Pekerjaan (C+D) 403,867.20

Empiris. Pipa Tembaga Diameter 2 1/2 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 2 1/2 " m1 1.2 225,000.00 270,000.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 303,960.00 60,792.00
JUMLAH HARGA BAHAN 364,752.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 424,752.00


D Overhead & Profit 10% 42,475.20
E Harga Satuan Pekerjaan (C+D) 467,227.20

Empiris. Pipa Tembaga Diameter 3 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Pipa tembaga dia. 3 " m1 1.2 245,000.00 294,000.00
Isolasi Pipa Tembaga m1 1.2 28,300.00 33,960.00
Material & Alat bantu 20% 327,960.00 65,592.00
JUMLAH HARGA BAHAN 393,552.00
B PERALATAN
Upah OH 1 60,000.00 60,000.00
JUMLAH HARGA ALAT 60,000.00

C Jumlah (A+B) 453,552.00


D Overhead & Profit 10% 45,355.20
E Harga Satuan Pekerjaan (C+D) 498,907.20

Empiris. Head Sprinkler up Right, Pendant, Side Wall

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Head Sprinkler unit 1 56,500.00 56,500.00
Material & Alat bantu 10% 56,500.00 5,650.00
JUMLAH HARGA BAHAN 62,150.00
B TENAGA
Upah OH 1 15000 15,000.00
JUMLAH HARGA ALAT 15,000.00

C Jumlah (A+B) 77,150.00


D Overhead & Profit 10% 7,715.00
E Harga Satuan Pekerjaan (C+D) 84,865.00

Empiris. Indor Hydran BOX

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Indor Hydran BOX unit 1 4,504,700.00 4,504,700.00
Material & Alat bantu 15% 4,504,700.00 675,705.00
JUMLAH HARGA BAHAN 5,180,405.00
B TENAGA
Upah OH 1 250000 250,000.00
JUMLAH HARGA ALAT 250,000.00

C Jumlah (A+B) 5,430,405.00


D Overhead & Profit 10% 543,040.50
E Harga Satuan Pekerjaan (C+D) 5,973,445.50

Empiris. Gate Valve 1"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 1" unit 1 180,000.00 180,000.00
Material & Alat bantu 5% 180,000.00 9,000.00
JUMLAH HARGA BAHAN 189,000.00
B TENAGA
Upah OH 1 25000 25,000.00
JUMLAH HARGA ALAT 25,000.00

C Jumlah (A+B) 214,000.00


D Overhead & Profit 10% 21,400.00
E Harga Satuan Pekerjaan (C+D) 235,400.00

Empiris. Gate Valve 1 1/4"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 1 1/4" unit 1 201,000.00 201,000.00
Material & Alat bantu 5% 201,000.00 10,050.00
JUMLAH HARGA BAHAN 211,050.00
B TENAGA
Upah OH 1 31250 31,250.00
JUMLAH HARGA ALAT 31,250.00

C Jumlah (A+B) 242,300.00


D Overhead & Profit 10% 24,230.00
E Harga Satuan Pekerjaan (C+D) 266,530.00

Empiris. Gate Valve 1 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 1 1/2" unit 1 355,000.00 355,000.00
Material & Alat bantu 5% 355,000.00 17,750.00
JUMLAH HARGA BAHAN 372,750.00
B TENAGA
Upah OH 1 37500 37,500.00
JUMLAH HARGA ALAT 37,500.00

C Jumlah (A+B) 410,250.00


D Overhead & Profit 10% 41,025.00
E Harga Satuan Pekerjaan (C+D) 451,275.00

Empiris. Gate Valve 2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 2" unit 1 702,000.00 702,000.00
Material & Alat bantu 5% 702,000.00 35,100.00
JUMLAH HARGA BAHAN 737,100.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 787,100.00


D Overhead & Profit 10% 78,710.00
E Harga Satuan Pekerjaan (C+D) 865,810.00

Empiris. Gate Valve 2 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 2 1/2" unit 1 1,375,000.00 1,375,000.00
Material & Alat bantu 5% 1,375,000.00 68,750.00
JUMLAH HARGA BAHAN 1,443,750.00
B TENAGA
Upah OH 1 62500 62,500.00
JUMLAH HARGA ALAT 62,500.00

C Jumlah (A+B) 1,506,250.00


D Overhead & Profit 10% 150,625.00
E Harga Satuan Pekerjaan (C+D) 1,656,875.00

Empiris. Gate Valve 3"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 3" unit 1 1,641,000.00 1,641,000.00
Material & Alat bantu 5% 1,641,000.00 82,050.00
JUMLAH HARGA BAHAN 1,723,050.00
B TENAGA
Upah OH 1 75000 75,000.00
JUMLAH HARGA ALAT 75,000.00

C Jumlah (A+B) 1,798,050.00


D Overhead & Profit 10% 179,805.00
E Harga Satuan Pekerjaan (C+D) 1,977,855.00

Empiris. Gate Valve 4"


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 4" unit 1 2,490,000.00 2,490,000.00
Material & Alat bantu 5% 2,490,000.00 124,500.00
JUMLAH HARGA BAHAN 2,614,500.00
B TENAGA
Upah OH 1 100000 100,000.00
JUMLAH HARGA ALAT 100,000.00

C Jumlah (A+B) 2,714,500.00


D Overhead & Profit 10% 271,450.00
E Harga Satuan Pekerjaan (C+D) 2,985,950.00

Empiris. Gate Valve 5"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 5" unit 1 3,680,000.00 3,680,000.00
Material & Alat bantu 5% 3,680,000.00 184,000.00
JUMLAH HARGA BAHAN 3,864,000.00
B TENAGA
Upah OH 1 125000 125,000.00
JUMLAH HARGA ALAT 125,000.00

C Jumlah (A+B) 3,989,000.00


D Overhead & Profit 10% 398,900.00
E Harga Satuan Pekerjaan (C+D) 4,387,900.00

Empiris. Gate Valve 6"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Gate valve 6" unit 1 4,670,000.00 4,670,000.00
Material & Alat bantu 5% 4,670,000.00 233,500.00
JUMLAH HARGA BAHAN 4,903,500.00
B TENAGA
Upah OH 1 150000 150,000.00
JUMLAH HARGA ALAT 150,000.00

C Jumlah (A+B) 5,053,500.00


D Overhead & Profit 10% 505,350.00
E Harga Satuan Pekerjaan (C+D) 5,558,850.00

Empiris. Strainer 2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Strainer 2" unit 1 425,800.00 425,800.00
Material & Alat bantu 1% 425,800.00 4,258.00
JUMLAH HARGA BAHAN 430,058.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 480,058.00


D Overhead & Profit 10% 48,005.80
E Harga Satuan Pekerjaan (C+D) 528,063.80

Empiris. Strainer 2 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Strainer 2 1/2" unit 1 935,100.00 935,100.00
Material & Alat bantu 1% 935,100.00 9,351.00
JUMLAH HARGA BAHAN 944,451.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 994,451.00


D Overhead & Profit 10% 99,445.10
E Harga Satuan Pekerjaan (C+D) 1,093,896.10

Empiris. Strainer 3"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Strainer 3" unit 1 1,590,000.00 1,590,000.00
Material & Alat bantu 1% 1,590,000.00 15,900.00
JUMLAH HARGA BAHAN 1,605,900.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 1,655,900.00


D Overhead & Profit 10% 165,590.00
E Harga Satuan Pekerjaan (C+D) 1,821,490.00

Empiris. Strainer 6"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Strainer 6" unit 1 4,410,000.00 4,410,000.00
Material & Alat bantu 1% 4,410,000.00 44,100.00
JUMLAH HARGA BAHAN 4,454,100.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 4,504,100.00


D Overhead & Profit 10% 450,410.00
E Harga Satuan Pekerjaan (C+D) 4,954,510.00

Empiris. Flexible Joint 1 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Flexible Joint 1 1/2" unit 1 625,000.00 625,000.00
Material & Alat bantu 1% 625,000.00 6,250.00
JUMLAH HARGA BAHAN 631,250.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 681,250.00


D Overhead & Profit 10% 68,125.00
E Harga Satuan Pekerjaan (C+D) 749,375.00

Empiris. Flexible Joint 2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Flexible Joint 2" unit 1 748,000.00 748,000.00
Material & Alat bantu 1% 748,000.00 7,480.00
JUMLAH HARGA BAHAN 755,480.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 805,480.00


D Overhead & Profit 10% 80,548.00
E Harga Satuan Pekerjaan (C+D) 886,028.00
Empiris. Flexible Joint 2 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Flexible Joint 2 1/2" unit 1 975,000.00 975,000.00
Material & Alat bantu 1% 975,000.00 9,750.00
JUMLAH HARGA BAHAN 984,750.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 1,034,750.00


D Overhead & Profit 10% 103,475.00
E Harga Satuan Pekerjaan (C+D) 1,138,225.00

Empiris. Flexible Joint 3"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Flexible Joint 3" unit 1 1,425,000.00 1,425,000.00
Material & Alat bantu 1% 1,425,000.00 14,250.00
JUMLAH HARGA BAHAN 1,439,250.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 1,489,250.00


D Overhead & Profit 10% 148,925.00
E Harga Satuan Pekerjaan (C+D) 1,638,175.00

Empiris. Flexible Joint 5"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Flexible Joint 5" unit 1 2,500,000.00 2,500,000.00
Material & Alat bantu 1% 2,500,000.00 25,000.00
JUMLAH HARGA BAHAN 2,525,000.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 2,575,000.00


D Overhead & Profit 10% 257,500.00
E Harga Satuan Pekerjaan (C+D) 2,832,500.00

Empiris. Flexible Joint 6"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Flexible Joint 6" unit 1 3,075,000.00 3,075,000.00
Material & Alat bantu 1% 3,075,000.00 30,750.00
JUMLAH HARGA BAHAN 3,105,750.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 3,155,750.00


D Overhead & Profit 10% 315,575.00
E Harga Satuan Pekerjaan (C+D) 3,471,325.00

Empiris. Ceck Valve 1 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Ceck Valve 1 1/2" unit 1 1,860,000.00 1,860,000.00
Material & Alat bantu 1% 1,860,000.00 18,600.00
JUMLAH HARGA BAHAN 1,878,600.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 1,928,600.00


D Overhead & Profit 10% 192,860.00
E Harga Satuan Pekerjaan (C+D) 2,121,460.00

Empiris. Ceck Valve 2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Ceck Valve 2" unit 1 2,170,000.00 2,170,000.00
Material & Alat bantu 1% 2,170,000.00 21,700.00
JUMLAH HARGA BAHAN 2,191,700.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 2,241,700.00


D Overhead & Profit 10% 224,170.00
E Harga Satuan Pekerjaan (C+D) 2,465,870.00

Empiris. Ceck Valve 2 1/2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Ceck Valve 2 1/2" unit 1 3,725,000.00 3,725,000.00
Material & Alat bantu 1% 3,725,000.00 37,250.00
JUMLAH HARGA BAHAN 3,762,250.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 3,812,250.00


D Overhead & Profit 10% 381,225.00
E Harga Satuan Pekerjaan (C+D) 4,193,475.00

Empiris. Ceck Valve 5"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Ceck Valve 5" unit 1 7,045,000.00 7,045,000.00
Material & Alat bantu 1% 7,045,000.00 70,450.00
JUMLAH HARGA BAHAN 7,115,450.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 7,165,450.00


D Overhead & Profit 10% 716,545.00
E Harga Satuan Pekerjaan (C+D) 7,881,995.00

Empiris. Float Valve 2"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Foot Valve 2" unit 1 2,145,000.00 2,145,000.00
Material & Alat bantu 1% 2,145,000.00 21,450.00
JUMLAH HARGA BAHAN 2,166,450.00
B TENAGA
Upah OH 1 65000 65,000.00
JUMLAH HARGA ALAT 65,000.00
C Jumlah (A+B) 2,231,450.00
D Overhead & Profit 10% 223,145.00
E Harga Satuan Pekerjaan (C+D) 2,454,595.00

Empiris. Foot Valve 3"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Foot Valve 3" unit 1 3,250,000.00 3,250,000.00
Material & Alat bantu 1% 3,250,000.00 32,500.00
JUMLAH HARGA BAHAN 3,282,500.00
B TENAGA
Upah OH 1 65000 65,000.00
JUMLAH HARGA ALAT 65,000.00

C Jumlah (A+B) 3,347,500.00


D Overhead & Profit 10% 334,750.00
E Harga Satuan Pekerjaan (C+D) 3,682,250.00

Empiris. Safety Valve 4"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Safety valve 4" unit 1 7,885,000.00 7,885,000.00
Material & Alat bantu 5% 7,885,000.00 394,250.00
JUMLAH HARGA BAHAN 8,279,250.00
B TENAGA
Upah OH 1 250000 250,000.00
JUMLAH HARGA ALAT 250,000.00

C Jumlah (A+B) 8,529,250.00


D Overhead & Profit 10% 852,925.00
E Harga Satuan Pekerjaan (C+D) 9,382,175.00

Empiris. Clean Out 4"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Clean Out 4" unit 1 255,000.00 255,000.00
Material & Alat bantu 1% 255,000.00 2,550.00
JUMLAH HARGA BAHAN 257,550.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 307,550.00


D Overhead & Profit 10% 30,755.00
E Harga Satuan Pekerjaan (C+D) 338,305.00

Empiris. Clean Out 6"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A BAHAN
Clean Out 6" unit 1 315,000.00 315,000.00
Material & Alat bantu 1% 315,000.00 3,150.00
JUMLAH HARGA BAHAN 318,150.00
B TENAGA
Upah OH 1 50000 50,000.00
JUMLAH HARGA ALAT 50,000.00

C Jumlah (A+B) 368,150.00


D Overhead & Profit 10% 36,815.00
E Harga Satuan Pekerjaan (C+D) 404,965.00
SUB REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
SUB PAKET : MEKANIKAL & ELEKTRIKAL
PEKERJAAN : JASA LAYANAN KONSULTAN PENYUSUNAN DOKUMEN DETAIL ENGINEERING DESIGN RUMAH SAKIT UMUM DAERAH KABUPATEN TAPIN
LOKASI : RSUD DATU SANGGUL RANTAU
GEDUNG : C

No. ITEM URAIAN PEKERJAAN SUB TOTAL TOTAL

03. PEKERJAAN MEKANIKAL ELEKTRIKAL

01 PEKERJAAN MEKANIKAL Rp 6,065,444,980.28


02 PEKERJAAN ELEKTRIKAL Rp 3,793,105,096.63
03 PEKERJAAN SELASAR Rp 27,171,110.00

TOTAL 03. PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 9,885,721,186.91


RENCANA ANGGARAN BIAYA (RAB)
SUB PAKET : MEKANIKAL & ELEKTRIKAL
PEKERJAAN : JASA LAYANAN KONSULTAN PENYUSUNAN DOKUMEN DETAIL ENGINEERING DESIGN RUMAH SAKIT UMUM DAERAH KABUPATEN TAPIN
LOKASI : RSUD DATU SANGGUL RANTAU
GEDUNG : C

HARGA SATUAN JUMLAH HARGA


NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

01 MEKANIKAL

01 01 PEKERJAAN SISTEM AIR BERSIH

PERPIPAAN AIR BERSIH


Pengadaan dan pemasangan sistem perpipaan Air Bersih Dingin, pemipaan dengan bahan
pipa PVC AW, lengkap terpasang dengan asesoris yang diperlukan sesuai dengan gambar
perencanaan dan spesifikasi teknis serta testing sistem terpasang.

ROOF/ATAP
1 Pompa Booster set 1.00 25,000,000.00 25,000,000.00
- Pompa 2kW / 3ph / 220V/380V / 50 Hz / 2900 rpm (1 set = 2 unit)
- Head = 12 meter / Q = 200 Lt/mnt
- Panel, kabel power & control WLC
- Fitting, valve, pressure gauge, header, pressure switch, Pressure tank 170 Liter
- Assesoris standar & material bantu lengkap 1 set
- Testing & Commissioning
2 Rooftank FRP kapasitas 66 m³ Tirta Plaza unit 1.00 323,100,000.00 323,100,000.00
3 Float Valve 2" Empiris bh 1.00 2,454,595.00 2,454,595.00
4 Gate Valve 3" Empiris bh 2.00 1,977,855.00 3,955,710.00
5 Gate Valve 2" Empiris bh 2.00 865,810.00 1,731,620.00
6 Pipa GIP Medium dia. 3" A.5.1.1.23 m' 1.90 528,831.97 1,004,780.74
7 Pipa GIP Medium dia. 2" A.5.1.1.23 m' 0.50 339,292.80 169,646.40
8 Pipa PPR PN-10 dia. 3" A.5.1.1.31 m' 1.80 367,738.33 661,929.00
9 Pipa PVC AW dia. 2" A.5.1.1.29 m' 439.60 49,437.30 21,732,637.08

INSTALASI SHAFT
1 Pipa PVC AW dia. 2,5" (Inlet ke Rooftank) A.5.1.1.29 m' 35.00 87,263.28 3,054,214.63
2 Pipa PVC AW dia. 2.5" (Inlet Underground) ke Ground Tank Utama A.5.1.1.29 m' 103.74 149,736.24 15,533,637.02
3 Pipa PVC AW dia. 2" (Shaft) A.5.1.1.29 m' 154.00 49,437.30 7,613,344.20
4 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.00 50,460.30 756,904.50
5 Pipa PVC AW dia. 1 1/4" A.5.1.1.28 m' 22.00 46,368.30 1,020,102.60
6 Pipa PVC AW dia. 1" A.5.1.1 27 m' 15.00 31,253.20 468,798.00

LANTAI 1
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 10.40 50,460.30 524,787.12
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 44.30 46,368.30 2,054,115.69
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 116.50 31,253.20 3,640,997.80
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 299.20 29,548.20 8,840,821.44
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 67.00 24,433.20 1,637,024.40
6 Gate Valve 2" Empiris bh 3.00 702,000.00 2,106,000.00
7 Gate Valve 1 1/2" Empiris bh 6.00 355,000.00 2,130,000.00
8 Gate Valve 1 1/4" Empiris bh 18.00 266,530.00 4,797,540.00
9 Kran Taman LS bh 4.00 325,000.00 1,300,000.00
10 Waterheater 15 L LS bh 4.00 1,832,600.00 7,330,400.00
11 Waterheater 30 L LS bh 8.00 2,566,200.00 20,529,600.00
12 Waterheater 50 L LS bh 24.00 3,688,000.00 88,512,000.00
13 Pipa PPR PN-20 dia. 3/4" m' 171.50 56,183.28 9,635,433.16

LANTAI 2
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.30 50,460.30 772,042.59
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 40.30 46,368.30 1,868,642.49
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 110.10 31,253.20 3,440,977.32
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 515.40 29,548.20 15,229,142.28
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 77.00 24,433.20 1,881,356.40
6 Gate Valve 2" Empiris bh 4.00 748,000.00 2,992,000.00
7 Gate Valve 1 1/2" Empiris bh 6.00 355,000.00 2,130,000.00
8 Gate Valve 1 1/4" Empiris bh 18.00 266,530.00 4,797,540.00
9 Waterheater 15 L LS bh 4.00 1,832,600.00 7,330,400.00
10 Waterheater 30 L LS bh 11.00 2,566,200.00 28,228,200.00
11 Waterheater 50 L LS bh 23.00 3,680,000.00 84,640,000.00
12 Pipa PPR PN-20 dia. 3/4" m' 108.00 56,183.28 6,067,794.65

Sub.jumlah PEKERJAAN SISTEM AIR BERSIH 720,674,734.50

01 02 PEKERJAAN SISTEM AIR BEKAS & AIR KOTOR


Pengadaan dan pemasangan pipa Air Bekas, Vent dan Air Kotor, bahan pipa PVC AW,
dan pipa Vent bahan pipa PVC D, lengkap terpasang dengan asesoris yang diperlukan sesuai dengan
gambar perencanaan dan spesifikasi teknis serta testing sistem terpasang.

PERALATAN UTAMA

SHAFT
1 Pipa PVC AW dia. 4"(shaft) A.5.1.1.36 m' 154.00 113,307.15 17,449,301.10

LANTAI 1
1 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph LS unit 2.00 20,000,000.00 40,000,000.00
c/w guide rel, chain,automatic level switch, Control Panel & Kabel
2 Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 m' 38.00 292,404.86 11,111,384.68
3 Fitting Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 bh 320.00 307,528.10 98,408,992.00
4 Pipa PVC AW dia. 4" A.5.1.1.36 m' 168.60 113,307.15 19,103,585.49
5 Pipa PVC AW dia. 3" A.5.1.1.36 m' 346.90 143,794.86 49,882,436.93
6 Pipa PVC AW dia. 2" A.5.1.1.29 m' 80.20 49,437.30 3,964,871.46
7 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 23.00 46,368.30 1,066,470.90
8 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 324.60 36,095.68 11,716,656.11
9 CO dia. 4" Empiris bh 2.00 338,305.00 676,610.00
10 CO dia. 6" Empiris bh 36.00 404,965.00 14,578,740.00
11 Vent Cap dia. 2" LS bh 16.00 45,000.00 720,000.00
13 Bak Kontrol Uk. 75x75x75 cm³ Tebal 10 cm LS unit 2.00 935,607.49 1,871,214.98
14 Septic Tank Uk. 12 m³ Tirta Plaza LS unit 1.00 128,500,000.00 128,500,000.00
include: FRP tank, screen, tank anaerob, sedimentation device

LANTAI 2
1 Pipa PVC AW dia. 4" A.5.1.1.36 m' 153.46 113,307.15 17,388,115.24
2 Pipa PVC AW dia. 3" A.5.1.1.36 m' 339.10 143,794.86 48,760,837.03
3 Pipa PVC AW dia. 2" A.5.1.1.29 m' 75.60 49,437.30 3,737,459.88
4 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 22.50 46,368.30 1,043,286.75
5 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 302.50 36,095.68 10,918,941.69
6 CO dia. 4" Empiris bh 4.00 338,305.00 1,353,220.00

Sub.jumlah PEKERJAAN SISTEM AIR BEKAS & AIR KOTOR 482,252,124.24


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
01 03 PEKERJAAN SISTEM AIR HUJAN
Pengadaan dan pemasangan sistem air hujan, lengkap terpasang
dengan asesoris yang diperlukan sesuai dengan gambar perencanaan dan spesifikasi teknis.
serta testing sistem terpasang.

BANGUNAN UTAMA
1 Pipa air hujan PVC AW dia.4" A.5.1.1 32 m' 642.00 113,307.15 72,743,190.30
2 Roofdrain (cast iron tipe meshroom) 4" bh 45.00 121,000.00 5,445,000.00
3 Gutter 30x30 cm2 Empiris m' 50.00 434,944.84 21,747,242.00
4 Bak Kontrol Uk. 75x75x75 cm³ LS unit 4.00 935,607.49 3,742,429.97
5 Sumur Resapan uk. 3 m3 (bangunan) LS unit 4.00 3,082,784.29 12,331,137.18
6 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph Ex Grundfos LS unit 4.00 20,000,000.00 80,000,000.00
c/w guide rel, chain,automatic level switch, Control Panel & Kabel

Sub.jumlah PEKERJAAN SISTEM AIR HUJAN 196,008,999.44

01 04 PEKERJAAN SISTEM FIRE FIGHTING


Pengadaan dan pemasangan sistem Hidrant & Sprinkler, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
Pipa hydrant menggunakan pipa Black Steel sch. 40

SHAFT HYDRANT & SPRINKLER


1 Pipa GIP Medium A dia 3" (Drain) A.5.1.1.23 m' 68.58 528,831.97 36,267,296.27
2 Pipa BS sch.40 dia 6" (Hydrant) A.5.1.1.24 m' 205.00 963,217.13 197,459,510.97
3 Pipa BS sch.40 dia 6" (Sprinkler) A.5.1.1.24 m' 110.00 963,217.13 105,953,883.93
4 Pipa BS sch.40 dia 6" (Siamese) A.5.1.1.24 m' 85.00 963,217.13 81,873,455.77
5 AAV 4" unit 1.00 3,675,000.00 3,675,000.00

LANTAI 1
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 579,768.84 33,394,685.28
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 5,973,445.50 23,893,782.00
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”

LANTAI 2
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 579,768.84 33,394,685.28
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 5,973,445.50 23,893,782.00
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”

LANTAI 1
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 714,961.13 20,018,911.73
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 579,768.84 26,263,528.53
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 66.20 406,924.47 26,938,399.69
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 52.10 272,797.80 14,212,765.38
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 86.72 206,446.17 17,903,011.57
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 97.20 179,734.50 17,470,193.40
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 371.60 126,098.87 46,858,338.85
8 Head Pendant Sprinkler Empiris unit 136.00 84,865.00 11,541,640.00
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 8,120,000.00 8,120,000.00
10 Siamese Connectiom bh 2.00 2,365,000.00 4,730,000.00

LANTAI 2
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 714,961.13 20,018,911.73
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 579,768.84 26,263,528.53
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 37.70 406,924.47 15,341,052.39
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 39.60 272,797.80 10,802,792.88
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 42.00 206,446.17 8,670,739.00
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 103.30 179,734.50 18,566,573.85
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 347.70 126,098.87 43,844,575.94
8 Head Pendant Sprinkler Empiris unit 143.00 84,865.00 12,135,695.00
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 8,120,000.00 8,120,000.00

FIRE EXTINGUISHER
Pengadaan dan pemasangan fire extinguisher Dry Chemical kapasitas 3 kg,
lengkap terpasang dengan alat bantu dan accessories lain yang diperlukan
serta testing sistem terpasang.

LANTAI 1
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 6.00 838,000.00 5,028,000.00

LANTAI 2
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 5.00 838,000.00 4,190,000.00

Sub.Jumlah PEKERJAAN SISTEM FIRE FIGHTING 906,844,739.99

01 05 PEKERJAAN TATA UDARA (VAC)


Pengadaan dan pemasangan sistem tata udara meliputi AC & Fan lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis serta testing sistem terpasang.

1 Unit AC Split Wall 5.000 Btuh R-32 INDOOR unit 14.00 4,037,000.00 56,518,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 14.00 2,036,592.25 28,512,291.50
2 Unit AC Split Wall 7.100 Btuh R-32 INDOOR unit 1.00 4,191,000.00 4,191,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 2,036,592.25 2,036,592.25
3 Unit AC Split Wall 11.100 Btuh R-32 INDOOR unit 6.00 5,456,000.00 32,736,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 6.00 2,036,592.25 12,219,553.50
4 Unit AC Split Wall 17.100 Btuh R-32 INDOOR unit 109.00 7,260,000.00 791,340,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 109.00 2,398,107.25 261,393,690.25
5 Unit AC low static duct 9.000 Btuh R-410A unit 2.00 7,216,000.00 14,432,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 2.00 2,398,107.25 4,796,214.50
6 Unit AC mid static duct 30.000 Btuh R-410A (3 ph) unit 2.00 22,022,000.00 44,044,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 2.00 2,398,107.25 4,796,214.50
7 Unit AC packaged duct 50.000 Btuh R-410A unit 16.00 39,644,000.00 634,304,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 16.00 2,398,107.25 38,369,716.00
8 Unit AC packaged duct 60.000 Btuh R-410A unit 1.00 49,434,000.00 49,434,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 2,398,107.25 2,398,107.25
9 Unit AC packaged duct 80.000 Btuh R-410A unit 1.00 61,226,000.00 61,226,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 2,398,107.25 2,398,107.25
10 Pekerjaan Ducting ls 22.00 7,000,000.00 154,000,000.00
11 Exhaust Toilet Fan Type Wall 50 cfm, 30 cm unit 136.00 705,000.00 95,880,000.00

Sub.jumlah PEKERJAAN TATA UDARA (VAC) 2,295,025,487.00

01 06 PEKERJAAN SISTEM GAS MEDIS


Pengadaan dan pemasangan sistem gas medis, lengkap terpasang dengan asesoris yang diperlukan
sesuai dengan gambar perencanaan dan spesifikasi teknis.

SHAFT GAS MEDIS


- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 90.00 234,379.20 21,094,128.00
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 90.00 261,307.20 23,517,648.00
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1 1/4" Empiris m' 90.00 288,235.20 25,941,168.00

LANTAI 1
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 72.00 2,185,800.00 157,377,600.00
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 72.00 2,185,800.00 157,377,600.00
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 11.00 2,185,800.00 24,043,800.00
4 Instalasi Pipa Gas Medis :
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 72.92 261,307.20 19,054,521.02
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 158.14 234,379.20 37,064,726.69
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 494.80 190,027.20 94,025,458.56
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 612.06 163,099.20 99,826,496.35
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 337.23 146,308.80 49,339,716.62
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 22,210,000.00 22,210,000.00
6 Ball Valve 1/2" set 1.00 133,600.00 133,600.00
7 Ball Valve 3/4" set 1.00 176,900.00 176,900.00
8 Ball Valve 1" set 1.00 215,000.00 215,000.00

LANTAI 2
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 93.00 2,185,800.00 203,279,400.00
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 93.00 2,185,800.00 203,279,400.00
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 3.00 2,185,800.00 6,557,400.00
4 Instalasi Pipa Gas Medis :
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 74.90 261,307.20 19,571,909.28
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 177.90 234,379.20 41,696,059.68
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 491.22 190,027.20 93,345,161.18
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 576.61 163,099.20 94,044,629.71
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 333.07 146,308.80 48,731,072.02
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 22,210,000.00 22,210,000.00
6 Ball Valve 1/2" set 1.00 133,600.00 133,600.00
7 Ball Valve 3/4" set 1.00 176,900.00 176,900.00
8 Ball Valve 1" set 1.00 215,000.00 215,000.00

Sub.jumlah PEKERJAAN SISTEM GAS MEDIS 1,464,638,895.12

JUMLAH 01 MEKANIKAL 6,065,444,980.28


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

02 ELEKTRIKAL

02 01 PEKERJAAN PANEL-PANEL LISTRIK TEGANGAN RENDAH & GROUNDING


Wall mounted cubicle, steel sheet metal ( 2 mm min), cat bakar. Komponen sesuai dengan
diagram satu garis pada gambar rencana lengkap dengan grounding panel (netral & bodi)
dan Grounding Elektrikal dan Elektronik lengkap dengan titik grounding, bak kontrol dan
kabel grounding sesuai gambar serta testing sistem terpasang.

1 Panel SDP-3 unit 1.00 42,376,400.00 42,376,400.00


2 Panel LP-C 1 unit 1.00 8,608,424.00 8,608,424.00
3 Panel LP-C 2 unit 1.00 8,679,935.00 8,679,935.00
4 Panel LP-ATAP unit 1.00 6,881,633.00 6,881,633.00
5 Panel PP.AC-C1 unit 1.00 19,358,064.00 19,358,064.00
6 Panel PP.AC-C2 unit 1.00 15,906,055.00 15,906,055.00
7 Panel PP-WH C1 unit 1.00 10,367,291.00 10,367,291.00
8 Panel PP-WH C2 unit 1.00 10,470,262.00 10,470,262.00
9 Panel EC unit 1.00 6,034,149.00 6,034,149.00

Sub.jumlah PEKERJAAN PANEL-PANEL LISTRIK TEGANGAN RENDAH & GROUNDING 128,682,213.00

02 02 PEKERJAAN PENGKABELAN KABEL DAYA LISTRIK TEGANGAN RENDAH


Pengadaan dan pemasangan kabel daya tegangan rendah, lengkap terpasang dengan material pendukung,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

1 Kabel dari SDP 3 ke LP.C1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 278,135.00 834,405.00
2 Kabel dari SDP 3 ke PP.AC-C1; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 5.00 151,835.75 759,178.75
3 Kabel dari SDP 3 ke LP.C2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 278,135.00 834,405.00
4 Kabel dari SDP 3 ke PP.AC-C2; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 10.00 151,835.75 1,518,357.50
5 Kabel dari SDP 3 ke PP.WH1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 278,135.00 834,405.00
6 Kabel dari SDP 3 ke PP.WH2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 8.00 278,135.00 2,225,080.00
7 Kabel dari SDP 3 ke LP.Atap; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 30.00 74,673.50 2,240,205.00
8 Kabel dari PUTR ke CP.LIFT; menggunakan kabel FRC 4 x 16 mm²+ BC 16 mm² Empiris m' 130.00 269,291.00 35,007,830.00
9 Kabel dari PP.ATAP ke CP.BOOSTER PUMP; menggunakan kabel NYY 5 x 2.5 mm² Empiris m' 20.00 58,437.50 1,168,750.00
10 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-27; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 74,673.50 4,480,410.00
11 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-28; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
12 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 74,673.50 5,227,145.00
13 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 74,673.50 5,227,145.00
14 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-51; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
15 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-52; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 50.00 74,673.50 3,733,675.00
16 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 74,673.50 4,480,410.00
17 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 74,673.50 2,986,940.00
18 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-57; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
19 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-58; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
20 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-59; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 55.00 74,673.50 4,107,042.50
21 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-60; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 74,673.50 4,480,410.00
22 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-61; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
23 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-11; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
24 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-18; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
25 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-23; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 74,673.50 2,986,940.00
26 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-42; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
27 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
28 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
29 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 74,673.50 2,986,940.00
30 Kabel dari PP.POMPA ke POMPA TRANSFER 1; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 92,952.75 929,527.50
31 Kabel dari PP.POMPA ke POMPA TRANSFER 2; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 92,952.75 929,527.50

Sub.jumlah PEKERJAAN PENGKABELAN KABEL DAYA LISTRIK TEGANGAN RENDAH 129,049,153.75

02 03 PEKERJAAN KABEL LADDER & TRAY


Pengadaan dan pemasangan kabel ladder & kabel tray, lengkap terpasang dengan material pendukung,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.

RISER
1 Kabel Ladder Lantai 1 W:400mm H:100mm, tebal plat 2mm Empiris m' 16.00 246,840.00 3,949,440.00
2 Kabel Tray Lantai 1 W:300mm H:100mm, tebal plat 2mm Empiris m' 16.00 330,000.00 5,280,000.00
3 Material bantu & aksesoris ls 1.00 3,230,304.00 3,230,304.00

Lantai 1
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 460,000.00 9,200,000.00
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 330,000.00 49,500,000.00
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 274,560.00 10,982,400.00
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 246,840.00 2,715,240.00
5 Material bantu & aksesoris ls 1.00 2,931,000.00 2,931,000.00

Lantai 2
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 460,000.00 9,200,000.00
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 330,000.00 49,500,000.00
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 274,560.00 10,982,400.00
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 246,840.00 2,715,240.00
5 Material bantu & aksesoris ls 1.00 2,931,000.00 2,931,000.00

Lantai ATAP
1 Kabel Tray Lantai 1 W:200mm H:100mm, tebal plat 2mm Empiris m' 20.00 274,560.00 5,491,200.00
2 Material bantu & aksesoris ls 1.00 637,500.00 637,500.00

Sub.jumlah PEKERJAAN KABEL LADDER & TRAY 169,245,724.00

02 04 PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK


Pengadaan dan pemasangan instalasi Penerangan & Stop Kontak, lengkap terpasang dengan saklar,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

LANTAI 1
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 560,000.00 2,240,000.00
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 124.00 475,200.00 58,924,800.00
3 TL 1x36W, BL Type LS unit 2.00 178,750.00 357,500.00
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 261.00 196,900.00 51,390,900.00
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 12.00 596,900.00 7,162,800.00
6 TLC 22W, armatur Baret Square LS unit 5.00 226,600.00 1,133,000.00
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 5.00 720,500.00 3,602,500.00
8 Instalasi Penerangan Empiris titik 413.00 246,510.00 101,808,630.00
9 Instalasi Power AC Empiris titik 82.00 467,610.00 38,344,020.00
10 Saklar tunggal inbow 10 A LS unit 165.00 32,500.00 5,362,500.00
11 Saklar ganda inbow 10 A LS unit 75.00 58,500.00 4,387,500.00
12 Saklar Hotel Tunggal inbow LS unit 5.00 85,000.00 425,000.00
13 Stop kontak 1 ph Inbow Single LS unit 266.00 45,500.00 12,103,000.00
14 Stop kontak 1 ph Outbow Single LS unit 8.00 45,500.00 364,000.00
15 Instalasi Stop Kontak 1ph, Single Empiris titik 274.00 305,272.00 83,644,528.00
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 72.00 3,318,900.00 238,960,800.00
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

LANTAI 2
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 560,000.00 2,240,000.00
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 122.00 475,200.00 57,974,400.00
3 TL 1x36W, BL Type LS unit 2.00 178,750.00 357,500.00
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 S unit 226.00 196,900.00 44,499,400.00
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 13.00 596,900.00 7,759,700.00
6 TLC 22W, armatur Baret Square LS unit 27.00 226,600.00 6,118,200.00
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 4.00 720,500.00 2,882,000.00
8 Instalasi Penerangan Empiris titik 398.00 246,510.00 98,110,980.00
9 Instalasi Power AC Empiris titik 77.00 467,610.00 36,005,970.00
10 Saklar tunggal inbow 10 A LS unit 142.00 32,500.00 4,615,000.00
11 Saklar ganda inbow 10 A LS unit 77.00 58,500.00 4,504,500.00
12 Saklar Hotel Tunggal inbow LS unit 5.00 85,000.00 425,000.00
13 Stop kontak 1 ph Inbow Single LS unit 248.00 45,500.00 11,284,000.00
14 Stop kontak 1 ph Outbow Single LS unit 10.00 45,500.00 455,000.00
15 Instalasi Stop Kontak 1ph, Single Empiris titik 258.00 305,272.00 78,760,176.00
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 93.00 3,318,900.00 308,657,700.00

LANTAI ATAP
1 TL 1x36W, Balk Type LS unit 4.00 178,750.00 715,000.00
2 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 1.00 196,900.00 196,900.00
3 TLC 22W, armatur Baret Square LS unit 1.00 226,600.00 226,600.00
4 Instalasi Penerangan Empiris titik 6.00 246,510.00 1,479,060.00
5 Saklar tunggal inbow 10 A LS unit 1.00 32,500.00 32,500.00
6 Saklar ganda inbow 10 A LS unit 1.00 58,500.00 58,500.00
7 Saklar Hotel Tunggal inbow LS unit 1.00 85,000.00 85,000.00
8 Stop kontak 1 ph Inbow Single LS unit 2.00 45,500.00 91,000.00
9 Instalasi Stop Kontak 1ph, Single Empiris titik 2.00 305,272.00 610,544.00
10 Stop kontak 3 ph 2200 Watt LS unit 6.00 133,900.00 803,400.00
11 Instalasi Stop Kontak 3ph, 2200 Watt Empiris titik 6.00 2,646,196.67 15,877,180.00

Sub.Jumlah PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK 1,295,036,688.00

02 05 PEKERJAAN SISTEM FIRE ALARM


Pengadaan dan pemasangan sistem fire alarm , lengkap terpasang dengan alat bantu
dan accessories lain yang diperlukan sesuai gambar dan spesifikasi teknis.

INSTALASI FIRE ALARM

LANTAI 1
1 ROR Temperature Heat Detector Konvensional bh 108.00 210,900.00 22,777,200.00
2 Manual Call Point bh 1.00 225,000.00 225,000.00
3 Indicator Lamp bh 1.00 562,000.00 562,000.00
4 Alarm Bell bh 1.00 433,000.00 433,000.00
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 108.00 176,770.00 19,091,160.00
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 458,370.00 916,740.00
7 End Of Line bh 2.00 60,500.00 121,000.00
8 TBFA 1 bh 1.00 4,000,000.00 4,000,000.00

LANTAI 2
1 ROR Temperature Heat Detector Konvensional bh 103.00 210,900.00 21,722,700.00
2 Manual Call Point bh 1.00 225,000.00 225,000.00
3 Indicator Lamp bh 1.00 562,000.00 562,000.00
4 Alarm Bell bh 1.00 433,000.00 433,000.00
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 103.00 176,770.00 18,207,310.00
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 458,370.00 916,740.00
7 End Of Line bh 2.00 60,500.00 121,000.00
8 TBFA 1 bh 1.00 4,000,000.00 4,000,000.00

Sub.jumlah PEKERJAAN SISTEM FIRE ALARM 94,313,850.00

02 06 PEKERJAAN SISTEM TELEPON


Pengadaan dan pemasangan Sistem Telepon, lengkap terpasang dengan alat bantu
dan accessories lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

INSTALASI TELEPHONE

LANTAI 1
1 TBT - 1 unit 1.00 350,000.00 350,000.00
2 Outlet Telephone Extension tipe wall mounted LS bh 7.00 65,000.00 455,000.00
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 7.00 876,810.00 6,137,670.00
4 Single Line Telephone LS bh 8.00 375,000.00 3,000,000.00
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 1,650,000.00 1,650,000.00

LANTAI 2
1 TBT - 2 unit 1.00 350,000.00 350,000.00
2 Outlet Telephone Extension tipe wall mounted LS bh 8.00 65,000.00 520,000.00
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 8.00 876,810.00 7,014,480.00
4 Single Line Telephone LS bh 9.00 375,000.00 3,375,000.00
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 1,650,000.00 1,650,000.00

Sub.Jumlah PEKERJAAN SISTEM TELEPON 24,502,150.00

02 07 PEKERJAAN SISTEM TATA SUARA


Pengadaan dan pemasangan Sistem Tata Suara, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
Instalasi fixture-fixture sound system menggunakan kabel NYMHY 3x2,5 mm² dalam PVC Conduit Ø 20 mm

PERALATAN UTAMA (R. KONTROL)


1 Mixer Amplifier 10 channel c/w Modul unit 1.00 3,500,000.00 3,500,000.00
2 Selector Switch min. 8 Zone bh 1.00 185,000.00 185,000.00
3 Dynamic Microphone bh 4.00 466,800.00 1,867,200.00
4 CD/VCD/DVD/MP3 Player bh 1.00 1,500,000.00 1,500,000.00
5 Consumable Material termasuk rak besi. ls 1.00 5,000,000.00 5,000,000.00
6 Wiring & Tescomm ls 1.00 2,000,000.00 2,000,000.00

KABEL FEEDER
1 Kabel Feeder dari peralatan utama ke TBS-1 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 50.00 19,348.18 967,408.75
2 Kabel Feeder dari peralatan utama ke TBS-2 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 55.00 19,348.18 1,064,149.63

INSTALASI SPEAKER

LANTAI 1
1 TBS-1 unit 1.00 380,000.00 380,000.00
2 Ceilling Speaker 6 W TOA bh 20.00 102,000.00 2,040,000.00
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 20.00 224,730.00 4,494,600.00

LANTAI 2
1 TBS-1 unit 1.00 380,000.00 380,000.00
2 Ceilling Speaker 6 W TOA bh 17.00 102,000.00 1,734,000.00
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 17.00 224,730.00 3,820,410.00

Testing commissioning ls 1.00 1,000,000.00 1,000,000.00

Sub.jumlah PEKERJAAN SISTEM TATA SUARA 29,932,768.38


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

02 08 PEKERJAAN SISTEM MATV


Pengadaan dan pemasangan Peralatan MATV, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis

PERALATAN UTAMA

KABEL FEEDER MATV


1 Kabel Feeder dari MDFTV ke LT-1, coaxial cable RG 11 dlm PVC Conduit HI Ø 20mm m' 80.00 20,041.18 1,603,294.00
2 Kabel Feeder dari LT-1 ke LT-2, coaxial cable RG 11 dlm PVC Conduit HI Ø 20mm m' 90.00 20,041.18 1,803,705.75

Lantai 1
1 Splitter 2 Way unit 2.00 250,000.00 500,000.00
2 Splitter 4 Way unit 2.00 261,000.00 522,000.00
3 Coupler 2 Way unit 1.00 300,000.00 300,000.00
4 Coupler 4 Way unit 12.00 338,000.00 4,056,000.00
5 Outlet MATV unit 55.00 36,500.00 2,007,500.00
6 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 55.00 247,170.00 13,594,350.00

Lantai 2
1 Splitter 2 Way unit 3.00 250,000.00 750,000.00
2 Splitter 4 Way unit 1.00 261,000.00 261,000.00
3 Coupler 4 Way unit 12.00 338,000.00 4,056,000.00
4 Outlet MATV unit 49.00 36,500.00 1,788,500.00
5 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 49.00 247,170.00 12,111,330.00

Testing commissioning ls 1.00 2,000,000.00 2,000,000.00

Sub.jumlah PEKERJAAN SISTEM MATV 45,353,679.75

02 09 PEKERJAAN SISTEM DATA


Pengadaan dan pemasangan Peralatan Utama dan Instalasi Data, lengkap terpasang
dengan alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

RISER
1 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 1 LS m' 80.00 18,616.68 1,489,334.00
2 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 2 LS m' 90.00 18,616.68 1,675,500.75

LANTAI 1
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 2,000,000.00 2,000,000.00
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 10.00 1,000,000.00 10,000,000.00
3 Outlet data kabel LS bh 10.00 150,000.00 1,500,000.00
4 empiris 11 ttk 20.00 491,370.00 9,827,400.00

LANTAI 2
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 2,000,000.00 2,000,000.00
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 8.00 1,000,000.00 8,000,000.00
3 Outlet data kabel LS bh 9.00 150,000.00 1,350,000.00
4 empiris 11 ttk 17.00 491,370.00 8,353,290.00

Sub.Jumlah PEKERJAAN SISTEM DATA 46,195,524.75

02 10 PEKERJAAN SISTEM CCTV


Pengadaan dan pemasangan Peralatan CCTV sistem addressable, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis

Kamera CCTV LANTAI 1


1 Indoor CCTV DS-2CD1123G0E-I Hikvision IP Camera CCTV Indoor 2MP unit 3.00 650,000.00 1,950,000.00
2 Outdoor CCTV Hikvision IP PTZ Full HD 2 MP DS-2DE4225IW-DE unit 4.00 4,650,000.00 18,600,000.00
3 Instalasi Camera CCTV, menggunakan kabel UTP CAT 5E dalam PVC conduit HI Ø 20mm titik 7.00 1,063,920.00 7,447,440.00

Kamera CCTV LANTAI 2


1 Indoor CCTV DS-2CD1123G0E-I Hikvision IP Camera CCTV Indoor 2MP unit 3.00 650,000.00 1,950,000.00
2 Instalasi Camera CCTV, menggunakan kabel UTP CAT 5E dalam PVC conduit HI Ø 20mm titik 3.00 1,063,920.00 3,191,760.00

Testing & Commissioning ls 1.00 2,000,000.00 2,000,000.00

Sub.jumlah PEKERJAAN SISTEM CCTV 35,139,200.00

02 11 PEKERJAAN SISTEM NURSE CALL


Pengadaan dan pemasangan Peralatan Utama dan instalasi Nurse Call, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.

LANTAI 1
1 Master Station unit 2.00 107,000,000.00 214,000,000.00
2 Display Anunciator unit 1.00 30,800,000.00 30,800,000.00
3 Call Report Software bh 1.00 6,160,000.00 6,160,000.00
4 Nurse call Console (connect with bead head) bh 72.00 2,070,000.00 149,040,000.00
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 1,232,000.00 68,992,000.00
6 Emergency Button (Toilet) bh 56.00 1,629,000.00 91,224,000.00
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 111,540.00 6,246,240.00
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 72.00 594,440.00 42,799,680.00

LANTAI 2
1 Master Station unit 2.00 107,000,000.00 214,000,000.00
2 Display Anunciator unit 1.00 30,800,000.00 30,800,000.00
3 Call Report Software bh 1.00 6,160,000.00 6,160,000.00
4 Nurse call Console (connect with bead head) bh 93.00 2,070,000.00 192,510,000.00
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 1,232,000.00 68,992,000.00
6 Emergency Button (Toilet) bh 56.00 1,629,000.00 91,224,000.00
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 111,540.00 6,246,240.00
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 93.00 594,440.00 55,282,920.00

Testing & Commissioning ls 1.00 2,000,000.00 2,000,000.00

Sub.jumlah PEKERJAAN SISTEM NURSE CALL 1,276,477,080.00


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

02 12 PEKERJAAN SISTEM TRANSPORTASI VERTIKAL (LIFT)


Pengadaan dan pemasangan Sistem Transportasi Vertikal Elevator / Lift , lengkap terpasang
dengan alat bantu dan accessories lain yang diperlukan sesuai gambar dan spesifikasi teknis

1 Hospital Bed Elevator unit 1.00 519,177,065.00 519,177,065.00


Jenis : With Mesin Lift
Type : 2/2 stop/opening
Kapasitas : 1000 Kg
Back up power : ARD (UPS system)
Kecepatan : 60 m/min
Lintasan : Lantai 1 s.d. Lantai 2
Finishing : stainlees steel
Material Bantu

Sub.jumlah PEKERJAAN SISTEM TRANSPORTASI VERTIKAL (LIFT) 519,177,065.00

JUMLAH 02 ELEKTRIKAL 3,793,105,096.63

03 SELASAR

03 01 PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK


Pengadaan dan pemasangan instalasi Penerangan & Stop Kontak, lengkap terpasang dengan saklar,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

1 Downlight E-27 23 Watt, armatur Down Light outbouw LS unit 38.00 196,900.00 7,482,200.00
2 Downlight E-27 23 Watt, armatur Down Light outbouw c/w Battery LS unit 9.00 596,900.00 5,372,100.00
3 Instalasi Penerangan Empiris titik 47.00 246,510.00 11,585,970.00
4 Saklar ganda inbow 10 A LS unit 2.00 58,500.00 117,000.00

03 02 PEKERJAAN SISTEM TATA SUARA


Pengadaan dan pemasangan Sistem Tata Suara, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
Instalasi fixture-fixture sound system menggunakan kabel NYMHY 3x2,5 mm² dalam PVC Conduit Ø 20 mm

1 Ceilling Speaker 6 W TOA bh 8.00 102,000.00 816,000.00


Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
2 titik 8.00 224,730.00 1,797,840.00

JUMLAH 03 SELASAR 27,171,110.00


SUB REKAPITULASI
BILL OF QUANTITY (BQ)
SUB PAKET : MEKANIKAL & ELEKTRIKAL
PEKERJAAN : JASA LAYANAN KONSULTAN PENYUSUNAN DOKUMEN DETAIL ENGINEERING DESIGN RUMAH SAKIT UMUM DAERAH KABUPATEN TAPIN
LOKASI : RSUD DATU SANGGUL RANTAU
GEDUNG : C

No. ITEM URAIAN PEKERJAAN SUB TOTAL TOTAL

03. PEKERJAAN MEKANIKAL ELEKTRIKAL

01 PEKERJAAN MEKANIKAL Rp -
02 PEKERJAAN ELEKTRIKAL Rp -
03 PEKERJAAN SELASAR Rp -

TOTAL 03. PEKERJAAN MEKANIKAL ELEKTRIKAL Rp -


BILL OF QUANTITY (BQ)
SUB PAKET : MEKANIKAL & ELEKTRIKAL
PEKERJAAN : JASA LAYANAN KONSULTAN PENYUSUNAN DOKUMEN DETAIL ENGINEERING DESIGN RUMAH SAKIT UMUM DAERAH KABUPATEN TAPIN
LOKASI : RSUD DATU SANGGUL RANTAU
GEDUNG : C

HARGA SATUAN JUMLAH HARGA


NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

01 MEKANIKAL

01 01 PEKERJAAN SISTEM AIR BERSIH

PERPIPAAN AIR BERSIH


Pengadaan dan pemasangan sistem perpipaan Air Bersih Dingin, pemipaan dengan bahan
pipa PVC AW, lengkap terpasang dengan asesoris yang diperlukan sesuai dengan gambar
perencanaan dan spesifikasi teknis serta testing sistem terpasang.

ROOF/ATAP
1 Pompa Booster set 1.00 -
- Pompa 2kW / 3ph / 220V/380V / 50 Hz / 2900 rpm (1 set = 2 unit)
- Head = 12 meter / Q = 200 Lt/mnt
- Panel, kabel power & control WLC
- Fitting, valve, pressure gauge, header, pressure switch, Pressure tank 170 Liter
- Assesoris standar & material bantu lengkap 1 set
- Testing & Commissioning
2 Rooftank FRP kapasitas 66 m³ Tirta Plaza unit 1.00 -
3 Float Valve 2" Empiris bh 1.00 -
4 Gate Valve 3" Empiris bh 2.00 -
5 Gate Valve 2" Empiris bh 2.00 -
6 Pipa GIP Medium dia. 3" A.5.1.1.23 m' 1.90 -
7 Pipa GIP Medium dia. 2" A.5.1.1.23 m' 0.50 -
8 Pipa PPR PN-10 dia. 3" A.5.1.1.31 m' 1.80 -
9 Pipa PVC AW dia. 2" A.5.1.1.29 m' 439.60 -

INSTALASI SHAFT
1 Pipa PVC AW dia. 2,5" (Inlet ke Rooftank) A.5.1.1.29 m' 35.00 -
2 Pipa PVC AW dia. 2.5" (Inlet Underground) ke Ground Tank Utama A.5.1.1.29 m' 103.74 -
3 Pipa PVC AW dia. 2" (Shaft) A.5.1.1.29 m' 154.00 -
4 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.00 -
5 Pipa PVC AW dia. 1 1/4" A.5.1.1.28 m' 22.00 -
6 Pipa PVC AW dia. 1" A.5.1.1 27 m' 15.00 -

LANTAI 1
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 10.40 -
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 44.30 -
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 116.50 -
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 299.20 -
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 67.00 -
6 Gate Valve 2" Empiris bh 3.00 -
7 Gate Valve 1 1/2" Empiris bh 6.00 -
8 Gate Valve 1 1/4" Empiris bh 18.00 -
9 Kran Taman LS bh 4.00 -
10 Waterheater 15 L LS bh 4.00 -
11 Waterheater 30 L LS bh 8.00 -
12 Waterheater 50 L LS bh 24.00 -
13 Pipa PPR PN-20 dia. 3/4" m' 171.50 -

LANTAI 2
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.30 -
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 40.30 -
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 110.10 -
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 515.40 -
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 77.00 -
6 Gate Valve 2" Empiris bh 4.00 -
7 Gate Valve 1 1/2" Empiris bh 6.00 -
8 Gate Valve 1 1/4" Empiris bh 18.00 -
9 Waterheater 15 L LS bh 4.00 -
10 Waterheater 30 L LS bh 11.00 -
11 Waterheater 50 L LS bh 23.00 -
12 Pipa PPR PN-20 dia. 3/4" m' 108.00 -

Sub.jumlah PEKERJAAN SISTEM AIR BERSIH -

01 02 PEKERJAAN SISTEM AIR BEKAS & AIR KOTOR


Pengadaan dan pemasangan pipa Air Bekas, Vent dan Air Kotor, bahan pipa PVC AW,
dan pipa Vent bahan pipa PVC D, lengkap terpasang dengan asesoris yang diperlukan sesuai dengan
gambar perencanaan dan spesifikasi teknis serta testing sistem terpasang.

PERALATAN UTAMA

SHAFT
1 Pipa PVC AW dia. 4"(shaft) A.5.1.1.36 m' 154.00 -

LANTAI 1
1 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph LS unit 2.00 -
c/w guide rel, chain,automatic level switch, Control Panel & Kabel
2 Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 m' 38.00 -
3 Fitting Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 bh 320.00 -
4 Pipa PVC AW dia. 4" A.5.1.1.36 m' 168.60 -
5 Pipa PVC AW dia. 3" A.5.1.1.36 m' 346.90 -
6 Pipa PVC AW dia. 2" A.5.1.1.29 m' 80.20 -
7 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 23.00 -
8 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 324.60 -
9 CO dia. 4" Empiris bh 2.00 -
10 CO dia. 6" Empiris bh 36.00 -
11 Vent Cap dia. 2" LS bh 16.00 -
13 Bak Kontrol Uk. 75x75x75 cm³ Tebal 10 cm LS unit 2.00 -
14 Septic Tank Uk. 12 m³ Tirta Plaza LS unit 1.00 -
include: FRP tank, screen, tank anaerob, sedimentation device

LANTAI 2
1 Pipa PVC AW dia. 4" A.5.1.1.36 m' 153.46 -
2 Pipa PVC AW dia. 3" A.5.1.1.36 m' 339.10 -
3 Pipa PVC AW dia. 2" A.5.1.1.29 m' 75.60 -
4 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 22.50 -
5 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 302.50 -
6 CO dia. 4" Empiris bh 4.00 -

Sub.jumlah PEKERJAAN SISTEM AIR BEKAS & AIR KOTOR -


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
01 03 PEKERJAAN SISTEM AIR HUJAN
Pengadaan dan pemasangan sistem air hujan, lengkap terpasang
dengan asesoris yang diperlukan sesuai dengan gambar perencanaan dan spesifikasi teknis.
serta testing sistem terpasang.

BANGUNAN UTAMA
1 Pipa air hujan PVC AW dia.4" A.5.1.1 32 m' 642.00 -
2 Roofdrain (cast iron tipe meshroom) 4" bh 45.00 -
3 Gutter 30x30 cm2 Empiris m' 50.00 -
4 Bak Kontrol Uk. 75x75x75 cm³ LS unit 4.00 -
5 Sumur Resapan uk. 3 m3 (bangunan) LS unit 4.00 -
6 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph Ex Grundfos LS unit 4.00 -
c/w guide rel, chain,automatic level switch, Control Panel & Kabel

Sub.jumlah PEKERJAAN SISTEM AIR HUJAN -

01 04 PEKERJAAN SISTEM FIRE FIGHTING


Pengadaan dan pemasangan sistem Hidrant & Sprinkler, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
Pipa hydrant menggunakan pipa Black Steel sch. 40

SHAFT HYDRANT & SPRINKLER


1 Pipa GIP Medium A dia 3" (Drain) A.5.1.1.23 m' 68.58 -
2 Pipa BS sch.40 dia 6" (Hydrant) A.5.1.1.24 m' 205.00 -
3 Pipa BS sch.40 dia 6" (Sprinkler) A.5.1.1.24 m' 110.00 -
4 Pipa BS sch.40 dia 6" (Siamese) A.5.1.1.24 m' 85.00 -
5 AAV 4" unit 1.00 -

LANTAI 1
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 -
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 -
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”

LANTAI 2
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 -
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 -
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”

LANTAI 1
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 -
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 -
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 66.20 -
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 52.10 -
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 86.72 -
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 97.20 -
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 371.60 -
8 Head Pendant Sprinkler Empiris unit 136.00 -
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 -
10 Siamese Connectiom bh 2.00 -

LANTAI 2
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 -
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 -
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 37.70 -
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 39.60 -
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 42.00 -
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 103.30 -
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 347.70 -
8 Head Pendant Sprinkler Empiris unit 143.00 -
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 -

FIRE EXTINGUISHER
Pengadaan dan pemasangan fire extinguisher Dry Chemical kapasitas 3 kg,
lengkap terpasang dengan alat bantu dan accessories lain yang diperlukan
serta testing sistem terpasang.

LANTAI 1
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 6.00 -

LANTAI 2
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 5.00 -

Sub.Jumlah PEKERJAAN SISTEM FIRE FIGHTING -

01 05 PEKERJAAN TATA UDARA (VAC)


Pengadaan dan pemasangan sistem tata udara meliputi AC & Fan lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis serta testing sistem terpasang.

1 Unit AC Split Wall 5.000 Btuh R-32 INDOOR unit 14.00 -


- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 14.00 -
2 Unit AC Split Wall 7.100 Btuh R-32 INDOOR unit 1.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 -
3 Unit AC Split Wall 11.100 Btuh R-32 INDOOR unit 6.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 6.00 -
4 Unit AC Split Wall 17.100 Btuh R-32 INDOOR unit 109.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 109.00 -
5 Unit AC low static duct 9.000 Btuh R-410A unit 2.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 2.00 -
6 Unit AC mid static duct 30.000 Btuh R-410A (3 ph) unit 2.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 2.00 -
7 Unit AC packaged duct 50.000 Btuh R-410A unit 16.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 16.00 -
8 Unit AC packaged duct 60.000 Btuh R-410A unit 1.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 -
9 Unit AC packaged duct 80.000 Btuh R-410A unit 1.00 -
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 -
10 Pekerjaan Ducting ls 22.00 -
11 Exhaust Toilet Fan Type Wall 50 cfm, 30 cm unit 136.00 -

Sub.jumlah PEKERJAAN TATA UDARA (VAC) -

01 06 PEKERJAAN SISTEM GAS MEDIS


Pengadaan dan pemasangan sistem gas medis, lengkap terpasang dengan asesoris yang diperlukan
sesuai dengan gambar perencanaan dan spesifikasi teknis.

SHAFT GAS MEDIS


- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 90.00 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 90.00 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1 1/4" Empiris m' 90.00 -

LANTAI 1
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 72.00 -
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 72.00 -
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 11.00 -
4 Instalasi Pipa Gas Medis :
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 72.92 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 158.14 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 494.80 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 612.06 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 337.23 -
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 -
6 Ball Valve 1/2" set 1.00 -
7 Ball Valve 3/4" set 1.00 -
8 Ball Valve 1" set 1.00 -

LANTAI 2
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 93.00 -
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 93.00 -
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 3.00 -
4 Instalasi Pipa Gas Medis :
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 74.90 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 177.90 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 491.22 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 576.61 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 333.07 -
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 -
6 Ball Valve 1/2" set 1.00 -
7 Ball Valve 3/4" set 1.00 -
8 Ball Valve 1" set 1.00 -

Sub.jumlah PEKERJAAN SISTEM GAS MEDIS -

JUMLAH 01 MEKANIKAL -
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

02 ELEKTRIKAL

02 01 PEKERJAAN PANEL-PANEL LISTRIK TEGANGAN RENDAH & GROUNDING


Wall mounted cubicle, steel sheet metal ( 2 mm min), cat bakar. Komponen sesuai dengan
diagram satu garis pada gambar rencana lengkap dengan grounding panel (netral & bodi)
dan Grounding Elektrikal dan Elektronik lengkap dengan titik grounding, bak kontrol dan
kabel grounding sesuai gambar serta testing sistem terpasang.

1 Panel SDP-3 unit 1.00 -


2 Panel LP-C 1 unit 1.00 -
3 Panel LP-C 2 unit 1.00 -
4 Panel LP-ATAP unit 1.00 -
5 Panel PP.AC-C1 unit 1.00 -
6 Panel PP.AC-C2 unit 1.00 -
7 Panel PP-WH C1 unit 1.00 -
8 Panel PP-WH C2 unit 1.00 -
9 Panel EC unit 1.00 -

Sub.jumlah PEKERJAAN PANEL-PANEL LISTRIK TEGANGAN RENDAH & GROUNDING -

02 02 PEKERJAAN PENGKABELAN KABEL DAYA LISTRIK TEGANGAN RENDAH


Pengadaan dan pemasangan kabel daya tegangan rendah, lengkap terpasang dengan material pendukung,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

1 Kabel dari SDP 3 ke LP.C1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 -
2 Kabel dari SDP 3 ke PP.AC-C1; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 5.00 -
3 Kabel dari SDP 3 ke LP.C2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 -
4 Kabel dari SDP 3 ke PP.AC-C2; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 10.00 -
5 Kabel dari SDP 3 ke PP.WH1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 -
6 Kabel dari SDP 3 ke PP.WH2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 8.00 -
7 Kabel dari SDP 3 ke LP.Atap; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 30.00 -
8 Kabel dari PUTR ke CP.LIFT; menggunakan kabel FRC 4 x 16 mm²+ BC 16 mm² Empiris m' 130.00 -
9 Kabel dari PP.ATAP ke CP.BOOSTER PUMP; menggunakan kabel NYY 5 x 2.5 mm² Empiris m' 20.00 -
10 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-27; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 -
11 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-28; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
12 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 -
13 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 -
14 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-51; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
15 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-52; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 50.00 -
16 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 -
17 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 -
18 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-57; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
19 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-58; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
20 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-59; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 55.00 -
21 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-60; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 -
22 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-61; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
23 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-11; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
24 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-18; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
25 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-23; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 -
26 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-42; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
27 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
28 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
29 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 -
30 Kabel dari PP.POMPA ke POMPA TRANSFER 1; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 -
31 Kabel dari PP.POMPA ke POMPA TRANSFER 2; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 -

Sub.jumlah PEKERJAAN PENGKABELAN KABEL DAYA LISTRIK TEGANGAN RENDAH -

02 03 PEKERJAAN KABEL LADDER & TRAY


Pengadaan dan pemasangan kabel ladder & kabel tray, lengkap terpasang dengan material pendukung,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.

RISER
1 Kabel Ladder Lantai 1 W:400mm H:100mm, tebal plat 2mm Empiris m' 16.00 -
2 Kabel Tray Lantai 1 W:300mm H:100mm, tebal plat 2mm Empiris m' 16.00 -
3 Material bantu & aksesoris ls 1.00 -

Lantai 1
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 -
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 -
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 -
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 -
5 Material bantu & aksesoris ls 1.00 -

Lantai 2
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 -
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 -
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 -
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 -
5 Material bantu & aksesoris ls 1.00 -

Lantai ATAP
1 Kabel Tray Lantai 1 W:200mm H:100mm, tebal plat 2mm Empiris m' 20.00 -
2 Material bantu & aksesoris ls 1.00 -

Sub.jumlah PEKERJAAN KABEL LADDER & TRAY -

02 04 PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK


Pengadaan dan pemasangan instalasi Penerangan & Stop Kontak, lengkap terpasang dengan saklar,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

LANTAI 1
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 -
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 124.00 -
3 TL 1x36W, BL Type LS unit 2.00 -
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 261.00 -
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 12.00 -
6 TLC 22W, armatur Baret Square LS unit 5.00 -
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 5.00 -
8 Instalasi Penerangan Empiris titik 413.00 -
9 Instalasi Power AC Empiris titik 82.00 -
10 Saklar tunggal inbow 10 A LS unit 165.00 -
11 Saklar ganda inbow 10 A LS unit 75.00 -
12 Saklar Hotel Tunggal inbow LS unit 5.00 -
13 Stop kontak 1 ph Inbow Single LS unit 266.00 -
14 Stop kontak 1 ph Outbow Single LS unit 8.00 -
15 Instalasi Stop Kontak 1ph, Single Empiris titik 274.00 -
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 72.00 -
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

LANTAI 2
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 -
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 122.00 -
3 TL 1x36W, BL Type LS unit 2.00 -
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 S unit 226.00 -
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 13.00 -
6 TLC 22W, armatur Baret Square LS unit 27.00 -
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 4.00 -
8 Instalasi Penerangan Empiris titik 398.00 -
9 Instalasi Power AC Empiris titik 77.00 -
10 Saklar tunggal inbow 10 A LS unit 142.00 -
11 Saklar ganda inbow 10 A LS unit 77.00 -
12 Saklar Hotel Tunggal inbow LS unit 5.00 -
13 Stop kontak 1 ph Inbow Single LS unit 248.00 -
14 Stop kontak 1 ph Outbow Single LS unit 10.00 -
15 Instalasi Stop Kontak 1ph, Single Empiris titik 258.00 -
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 93.00 -

LANTAI ATAP
1 TL 1x36W, Balk Type LS unit 4.00 -
2 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 1.00 -
3 TLC 22W, armatur Baret Square LS unit 1.00 -
4 Instalasi Penerangan Empiris titik 6.00 -
5 Saklar tunggal inbow 10 A LS unit 1.00 -
6 Saklar ganda inbow 10 A LS unit 1.00 -
7 Saklar Hotel Tunggal inbow LS unit 1.00 -
8 Stop kontak 1 ph Inbow Single LS unit 2.00 -
9 Instalasi Stop Kontak 1ph, Single Empiris titik 2.00 -
10 Stop kontak 3 ph 2200 Watt LS unit 6.00 -
11 Instalasi Stop Kontak 3ph, 2200 Watt Empiris titik 6.00 -

Sub.Jumlah PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK -

02 05 PEKERJAAN SISTEM FIRE ALARM


Pengadaan dan pemasangan sistem fire alarm , lengkap terpasang dengan alat bantu
dan accessories lain yang diperlukan sesuai gambar dan spesifikasi teknis.

INSTALASI FIRE ALARM

LANTAI 1
1 ROR Temperature Heat Detector Konvensional bh 108.00 -
2 Manual Call Point bh 1.00 -
3 Indicator Lamp bh 1.00 -
4 Alarm Bell bh 1.00 -
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 108.00 -
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 -
7 End Of Line bh 2.00 -
8 TBFA 1 bh 1.00 -

LANTAI 2
1 ROR Temperature Heat Detector Konvensional bh 103.00 -
2 Manual Call Point bh 1.00 -
3 Indicator Lamp bh 1.00 -
4 Alarm Bell bh 1.00 -
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 103.00 -
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 -
7 End Of Line bh 2.00 -
8 TBFA 1 bh 1.00 -

Sub.jumlah PEKERJAAN SISTEM FIRE ALARM -

02 06 PEKERJAAN SISTEM TELEPON


Pengadaan dan pemasangan Sistem Telepon, lengkap terpasang dengan alat bantu
dan accessories lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

INSTALASI TELEPHONE

LANTAI 1
1 TBT - 1 unit 1.00 -
2 Outlet Telephone Extension tipe wall mounted LS bh 7.00 -
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 7.00 -
4 Single Line Telephone LS bh 8.00 -
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 -

LANTAI 2
1 TBT - 2 unit 1.00 -
2 Outlet Telephone Extension tipe wall mounted LS bh 8.00 -
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 8.00 -
4 Single Line Telephone LS bh 9.00 -
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 -

Sub.Jumlah PEKERJAAN SISTEM TELEPON -

02 07 PEKERJAAN SISTEM TATA SUARA


Pengadaan dan pemasangan Sistem Tata Suara, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
Instalasi fixture-fixture sound system menggunakan kabel NYMHY 3x2,5 mm² dalam PVC Conduit Ø 20 mm

PERALATAN UTAMA (R. KONTROL)


1 Mixer Amplifier 10 channel c/w Modul unit 1.00 -
2 Selector Switch min. 8 Zone bh 1.00 -
3 Dynamic Microphone bh 4.00 -
4 CD/VCD/DVD/MP3 Player bh 1.00 -
5 Consumable Material termasuk rak besi. ls 1.00 -
6 Wiring & Tescomm ls 1.00 -

KABEL FEEDER
1 Kabel Feeder dari peralatan utama ke TBS-1 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 50.00 -
2 Kabel Feeder dari peralatan utama ke TBS-2 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 55.00 -

INSTALASI SPEAKER

LANTAI 1
1 TBS-1 unit 1.00 -
2 Ceilling Speaker 6 W TOA bh 20.00 -
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 20.00 -

LANTAI 2
1 TBS-1 unit 1.00 -
2 Ceilling Speaker 6 W TOA bh 17.00 -
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 17.00 -

Testing commissioning ls 1.00 -

Sub.jumlah PEKERJAAN SISTEM TATA SUARA -


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

02 08 PEKERJAAN SISTEM MATV


Pengadaan dan pemasangan Peralatan MATV, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis

PERALATAN UTAMA

KABEL FEEDER MATV


1 Kabel Feeder dari MDFTV ke LT-1, coaxial cable RG 11 dlm PVC Conduit HI Ø 20mm m' 80.00 -
2 Kabel Feeder dari LT-1 ke LT-2, coaxial cable RG 11 dlm PVC Conduit HI Ø 20mm m' 90.00 -

Lantai 1
1 Splitter 2 Way unit 2.00 -
2 Splitter 4 Way unit 2.00 -
3 Coupler 2 Way unit 1.00 -
4 Coupler 4 Way unit 12.00 -
5 Outlet MATV unit 55.00 -
6 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 55.00 -

Lantai 2
1 Splitter 2 Way unit 3.00 -
2 Splitter 4 Way unit 1.00 -
3 Coupler 4 Way unit 12.00 -
4 Outlet MATV unit 49.00 -
5 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 49.00 -

Testing commissioning ls 1.00 -

Sub.jumlah PEKERJAAN SISTEM MATV -

02 09 PEKERJAAN SISTEM DATA


Pengadaan dan pemasangan Peralatan Utama dan Instalasi Data, lengkap terpasang
dengan alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

RISER
1 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 1 LS m' 80.00 -
2 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 2 LS m' 90.00 -

LANTAI 1
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 -
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 10.00 -
3 Outlet data kabel LS bh 10.00 -
4 empiris 11 ttk 20.00 -

LANTAI 2
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 -
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 8.00 -
3 Outlet data kabel LS bh 9.00 -
4 empiris 11 ttk 17.00 -

Sub.Jumlah PEKERJAAN SISTEM DATA -

02 10 PEKERJAAN SISTEM CCTV


Pengadaan dan pemasangan Peralatan CCTV sistem addressable, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis

Kamera CCTV LANTAI 1


1 Indoor CCTV DS-2CD1123G0E-I Hikvision IP Camera CCTV Indoor 2MP unit 3.00 -
2 Outdoor CCTV Hikvision IP PTZ Full HD 2 MP DS-2DE4225IW-DE unit 4.00 -
3 Instalasi Camera CCTV, menggunakan kabel UTP CAT 5E dalam PVC conduit HI Ø 20mm titik 7.00 -

Kamera CCTV LANTAI 2


1 Indoor CCTV DS-2CD1123G0E-I Hikvision IP Camera CCTV Indoor 2MP unit 3.00 -
2 Instalasi Camera CCTV, menggunakan kabel UTP CAT 5E dalam PVC conduit HI Ø 20mm titik 3.00 -

Testing & Commissioning ls 1.00 -

Sub.jumlah PEKERJAAN SISTEM CCTV -

02 11 PEKERJAAN SISTEM NURSE CALL


Pengadaan dan pemasangan Peralatan Utama dan instalasi Nurse Call, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.

LANTAI 1
1 Master Station unit 2.00 -
2 Display Anunciator unit 1.00 -
3 Call Report Software bh 1.00 -
4 Nurse call Console (connect with bead head) bh 72.00 -
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 -
6 Emergency Button (Toilet) bh 56.00 -
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 -
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 72.00 -

LANTAI 2
1 Master Station unit 2.00 -
2 Display Anunciator unit 1.00 -
3 Call Report Software bh 1.00 -
4 Nurse call Console (connect with bead head) bh 93.00 -
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 -
6 Emergency Button (Toilet) bh 56.00 -
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 -
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 93.00 -

Testing & Commissioning ls 1.00 -

Sub.jumlah PEKERJAAN SISTEM NURSE CALL -


HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)

02 12 PEKERJAAN SISTEM TRANSPORTASI VERTIKAL (LIFT)


Pengadaan dan pemasangan Sistem Transportasi Vertikal Elevator / Lift , lengkap terpasang
dengan alat bantu dan accessories lain yang diperlukan sesuai gambar dan spesifikasi teknis

1 Hospital Bed Elevator unit 1.00 -


Jenis : With Mesin Lift
Type : 2/2 stop/opening
Kapasitas : 1000 Kg
Back up power : ARD (UPS system)
Kecepatan : 60 m/min
Lintasan : Lantai 1 s.d. Lantai 2
Finishing : stainlees steel
Material Bantu

Sub.jumlah PEKERJAAN SISTEM TRANSPORTASI VERTIKAL (LIFT) -

JUMLAH 02 ELEKTRIKAL -

03 SELASAR

03 01 PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK


Pengadaan dan pemasangan instalasi Penerangan & Stop Kontak, lengkap terpasang dengan saklar,
alat bantu dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
serta testing sistem terpasang.

1 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 38.00 -
2 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 9.00 -
3 Instalasi Penerangan Empiris titik 47.00 -
4 Saklar ganda inbow 10 A LS unit 2.00 -

03 02 PEKERJAAN SISTEM TATA SUARA


Pengadaan dan pemasangan Sistem Tata Suara, lengkap terpasang dengan alat bantu
dan asesoris lain yang diperlukan sesuai gambar dan spesifikasi teknis.
Instalasi fixture-fixture sound system menggunakan kabel NYMHY 3x2,5 mm² dalam PVC Conduit Ø 20 mm

1 Ceilling Speaker 6 W TOA bh 8.00 -


Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
2 titik 8.00 -

JUMLAH 03 SELASAR -