HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
TENAGA
1 Pekerja hari 103,000.00
2 Tukang Ledeng hari 109,000.00
3 Kepala Tukang hari 147,000.00
4 Mandor hari 116,000.00
PVC AW
1 Pipa PVC AW 1/2” m1 7,000.00
2 Pipa PVC AW 3/4” m1 10,000.00
3 Pipa PVC AW 1” m1 11,000.00
4 Pipa PVC AW 1 1/4” m1 16,200.00
5 Pipa PVC AW 1 1/2” m1 18,600.00
6 Pipa PVC AW 2” m1 18,000.00
7 Pipa PVC AW 2 1/2” m1 34,725.00
8 Pipa PVC AW 3” m1 31,000.00
9 Pipa PVC AW 4” m1 50,000.00
10 Pipa PVC AW 6" m1 180,050.00
11 Pipa PVC AW 8" m1 302,150.00
12 Tee PVC AW Ø 150 mm m1 260,900.00
13 Elbow PVC AW Ø 150 mm m1 205,400.00
PVC D
1 Pipa PVC D 1 1/4” m1 10,175.00
2 Pipa PVC D 1 1/2” m1 11,500.00
3 Pipa PVC D 2” m1 14,750.00
4 Pipa PVC D 2 1/2" m1 19,925.00
5 Pipa PVC D 3" m1 26,450.00
6 Pipa PVC D 4” m1 41,600.00
PIPA BS SCH 40
1 Pipa BS SCH 40 8" m1 692,083.33
2 Pipa BS SCH 40 6" m1 685,166.67
3 Pipa BS SCH 40 5" m1 530,166.67
4 Pipa BS SCH 40 4" m1 391,833.33
5 Pipa BS SCH 40 3" m1 312,541.67
6 Pipa BS SCH 40 2,5" m1 211,166.67
7 Pipa BS SCH 40 2" m1 132,500.00
8 Pipa BS SCH 40 1 1/2" m1 99,166.67
9 Pipa BS SCH 40 ø 1 1/4" m1 83,500.00
10 Pipa BS SCH 40 ø 1" m1 61,166.67
11 Pipa BS SCH 40 ø 3/4" m1 41,333.33
12 Pipa BS SCH 40 ø 1/2" m1 32,541.67
13 Tee BS SCH 40 Ø 125 mm bh 635,000.00
14 Elbow BS SCH40 Ø 125 mm bh 203,000.00
15 Tee BS SCH 40 Ø 150 mm bh 780,000.00
16 Elbow BS SCH 40 Ø 150 mm 6" bh 265,000.00
PIPA LAIN
1 Pipa PVC Conduit HIC dia 20 mm m1 5,000.00
2 Pipa Metal Conduit HIC dia 25 mm m1 45,000.00
3 Pipa Tembaga 1/4" m1 14,500.00
4 Pipa Tembaga 3/8" m1 22,400.00
5 Pipa Tembaga 1/2" m1 33,000.00
6 Pipa Tembaga 5/8" m1 50,000.00
7 Pipa Tembaga 3/4" m1 78,000.00
8 Pipa Tembaga 1" m1 95,000.00
9 Pipa Tembaga 1 1/4" m1 112,000.00
10 Pipa Tembaga 1 1/2" m1 125,000.00
11 Pipa Tembaga 2" m1 185,000.00
12 Pipa Tembaga 2 1/2" m1 225,000.00
13 Pipa Tembaga 3" m1 245,000.00
6 Valve Ø 4" bh 2,454,000.00
7 Valve Ø 6" bh 4,737,000.00
ISOLASI PIPA
1 Isolasi Pipa Refrigerant 1/4" m1 12,000.00
2 Isolasi Pipa Refrigerant 3/8" m1 13,000.00
3 Isolasi Pipa Refrigerant 1/2" m1 18,000.00
4 Isolasi Pipa Tembaga m1 28,300.00
ELEKTRICAL
1 Box Panel bh 1,500,000.00
2 Box Panel bh 500,000.00
3 Box Panel (TYPE OUTDOOR IP 65) bh 850,000.00
4 MCCB 3 Phase 400-500 A 25 Ka c/w Proteksi Motor Micrologic 2 bh 14,036,000.00
5 MCCB 3 Phase 63 A 18 kA bh 980,100.00
6 MCCB 3 Phase 40 A 18 kA bh 980,100.00
7 MCCB 3 Phase 30 A 18 kA bh 980,100.00
8 MCCB 3 Phase 25 A 18 kA bh 980,100.00
9 MCCB 3 Phase 20 A 18 kA bh 980,100.00
10 MCCB 3 Phase 10A 18 kA bh 980,100.00
11 MCCB 3 Phase 250-300A 25 kA c/w Proteksi Motor Micrologic 2 bh 10,961,500.00
12 MCCB 3 Phase 63 A 16 kA bh 980,100.00
13 MCCB 3 Phase 40 A 16 kA bh 980,100.00
14 MCCB 3 Phase 30 A 16 kA bh 980,100.00
15 MCCB 3 Phase 25 A 16 kA bh 980,100.00
16 MCCB 3 Phase 10 A 16 kA bh 980,100.00
17 MCCB 3 Phase 75A 16 kA c/w Proteksi Motor Micrologic bh 10,327,900.00
18 MCB 3 Phase 40 A 16 kA bh 980,100.00
19 MCB 3 Phase 16 A 16 kA bh 980,100.00
20 MCCB 3 Phase 450-500A 25 kA c/w Proteksi Motor Micrologic bh 6,671,500.00
21 MCCB 3 Phase 250A 16 Ka bh 1,685,200.00
22 MCCB 3 Phase 150A 16 Ka bh 1,685,200.00
23 MCCB 3 Phase 400-450A 25 kA c/w Proteksi Motor Micrologic bh 6,671,500.00
24 MCB 1 Phase 16 A 6 kA bh 93,610.00
25 MCB 1 Phase 10 A 6 kA bh 93,610.00
26 MCB 1 Phase 16 A 6 kA bh 93,610.00
27 MCB 1 Phase 16 A 16 Ka bh 232,870.00
28 MCB 1 Phase 6 A 6 kA bh 93,610.00
29 CONTACTOR 3PH 16 A bh 164,000.00
30 CONTACTOR 3PH 32 A bh 325,000.00
31 WLC bh 450,000.00
32 Switch Auto Manual bh 91,200.00
33 Switch On-Off bh 91,200.00
34 ELCB 2 Phase 10 A 30mA bh 577,500.00
35 ELCB 2 Phase 40 A 30mA bh 748,550.00
36 ELCB 2 Phase 63 A 30mA bh 748,550.00
37 ELCB 2 Phase 25 A 30mA bh 748,550.00
38 Pilot Lamp bh 22,500.00
39 Fuse bh 25,000.00
40 Voltage Selector bh 70,500.00
41 Voltmeter bh 250,000.00
42 Amperemeter bh 288,000.00
43 Bus bar lot 450,000.00
44 Terminal Blok lot 500,000.00
45 Wiring & Accessories lot 150,000.00
SEWA ALAT
1 handle crane 2 T hari 25,000.00
2 Peralatan potong pipa T2/mekanik / cilinder saw hari 100,000.00
3 watt hari 150,000.00
4 Submersible 3m3/h hari 75,000.00
LAIN-LAIN
1 Besi Siku 5cm x 5cm x 6m m1 75,666.67
2 Besi polos 8 mm m1 42,000.00
3 Pasir pasang m3 165,000.00
4 Pasir urug m3 157,400.00
5 Waterheater 15l bh 1,832,600.00
6 Kran Taman bh 325,000.00
7 Vent Cap diameter 2" bh 45,000.00
8 Roofdrain (cast iron tipe meshroom) 4" bh 121,000.00
9 Pressure Tank 200Lt bh 10,625,000.00
10 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 8,120,000.00
11 Unit AC Wall Split 1/2 PK unit 3,564,000.00
12 Unit AC Wall Split 3/4 PK unit 3,707,000.00
13 Unit AC Wall Split 1 PK unit 3,872,000.00
14 Unit AC Wall Split 1 1/2 PK unit 4,840,000.00
15 Unit AC Wall Split 2 PK unit 6,413,000.00
16 Unit AC Wall Split 2 1/2 PK unit 9,108,000.00
17 Unit AC Ceiling Cassete 2 1/2 PK unit 18,491,000.00
18 Unit AC Ceiling Cassete 3 PK unit 24,002,000.00
19 Unit AC Ceiling Cassete 4 PK unit 31,999,000.00
20 Unit AC Ceiling Cassete 5 PK unit 37,488,000.00
21 Unit AC Ceiling Cassete 6 PK unit 46,387,000.00
22 Unit AC Split Duct 9.000 BTUH unit 7,216,000.00
23 Unit AC Split Duct 13.000 BTUH unit 8,240,980.00
24 Unit AC Split Duct 18.000 BTUH unit 12,089,000.00
25 Unit AC Split Duct 21.000 BTUH unit 15,906,000.00
26 Unit AC Split Duct 26.000 BTUH unit 22,200,000.00
27 Unit AC Split Duct 48.000 BTUH unit 37,345,000.00
28 Unit AC Ceiling Duct middle static 54600 Btuh unit 26,609,000.00
29 Unit AC Outdoor 54.600 Btuh VRV unit 81,664,000.00
30 Unit AC Split Wall 7500 Btuh INDOOR VRV unit 11,814,000.00
31 Unit AC Split Wall 9600 Btuh INDOOR VRV unit 12,309,000.00
32 Unit AC Ceiling Cassete 12300 Btuh INDOOR VRV unit 12,804,000.00
33 Unit AC Ceiling Cassete 15400 Btuh INDOOR VRV unit 13,640,000.00
34 Unit AC Ceiling Cassete 19100 Btuh INDOOR VRV unit 15,972,000.00
35 Unit AC Ceiling Cassete 24200 Btuh INDOOR VRV unit 16,797,000.00
36 Unit AC Ceiling Cassete 30700 Btuh INDOOR VRV unit 24,871,000.00
37 Unit AC Ceiling Cassete 38200 Btuh INDOOR VRV unit 25,036,000.00
38 Unit AC Ceiling Duct 24.200 BTUH INDOOR VRV unit 16,797,000.00
39 Unit AC Ceiling Duct 54.600 BTUH INDOOR VRV unit 25,278,000.00
40 Wall Fan 70 Watt, 63 m3/m, 16" c/w Switch unit 650,000.00
41 Unit AC Outdoor 324.000 Btuh VRV unit 332,640,000.00
42 Unit AC Outdoor 341.000 Btuh VRV unit 339,966,000.00
43 Exhaust Toilet Fan Type Wall 50 cfm, 30 cm unit 705,000.00
44 Head Pendant Sprinkler unit 56,500.00
45 Indor Hydran BOX unit 4,504,700.00
46 Kabel BC 2.5 mm2 m 4,125.00
47 Kabel BC 4 mm2 m 5,700.00
48 Kabel BC 6 mm2 m 7,050.00
49 Kabel BC 10 mm2 m 11,400.00
50 Kabel BC 16 mm2 m 16,650.00
51 Kabel BC 25 mm2 m 39,500.00
52 Kabel BC 35 mm2 m 30,450.00
53 Kabel BC 50 mm2 m 36,700.00
54 Kabel BC 70 mm2 m 53,600.00
55 Kabel BC 95 mm2 m 98,750.00
56 Kabel BC 120 mm2 m 113,500.00
57 Kabel BC 150 mm2 m 173,000.00
58 Kabel BC 185 mm2 m 254,800.00
59 Kabel BC 240 mm2 m 295,000.00
60 Kabel NYY 4 x 2.5 mm² m 40,000.00
61 Kabel NYY 4 x 4 mm² m 58,000.00
62 Kabel NYY 4 x 6 mm² m 72,000.00
63 Kabel NYY 4 x 10 mm² m 98,000.00
64 Kabel NYY 4 x 16 mm² m 111,000.00
65 Kabel NYY 4 x 25 mm² m 197,500.00
66 Kabel NYY 4 x 35 mm² m 231,000.00
67 Kabel NYY 4 x 50 mm² m 314,000.00
68 Kabel NYY 4 x 70 mm² m 444,000.00
69 Kabel NYY 4 x 95 mm² m 610,000.00
70 Kabel NYY 4 x 120 mm² m 764,000.00
71 Kabel NYY 4 x 150 mm² m 940,000.00
72 Kabel NYY 4 x 185 mm² m 1,169,000.00
73 Kabel NYY 4 x 240 mm² m 1,530,000.00
74 Kabel NYY 4 x 300 mm² m 1,903,000.00
75 Kabel NYY 5 x 2.5 mm² m 50,000.00
76 Kabel NYA 1 x 50 mm² m 38,000.00
77 Kabel NYA 1 x 70 mm² m 54,000.00
78 Kabel NYFGBY 4 x 6 mm² m 55,000.00
79 Kabel NYFGBY 4 x 16 mm² m 108,375.00
80 Kabel FRC 4 x 4 mm² m 63,000.00
80 Kabel FRC 4 x 16 mm² m 226,500.00
81 Kabel FRC 4 x 95 mm² m 650,000.00
82 Tray 500 x 100 mm m 460,000.00
82 Tray 300 x 100 mm m 240,000.00
83 Tray 200 x 100 mm m 192,000.00
84 Tray 100 x 100 mm m 168,000.00
85 Support unit 10,500.00
86 Kabel Backbone Data UTP Cat6 m 5,566.67
87 Coaxial cable RG 11 m 6,800.00
88 NYMHY 3x2.5 mm² m 6,200.00
89 Conduit 20mm btg 10,500.00
90 Kabel Ladder W=400 H=100 m 10,500.00
91 Kabel Ladder W=600 H=100 m 10,500.00
92 Kabel Ladder W=800 H=100 m 10,500.00
93 Kabel Ladder W=1000 H=100 m 10,500.00
94 Kabel N2XSY 3 x 95 mm² m 497,000.00
95 Kabel N2XSEBY 3 x 120 mm² m 548,000.00
96 Gate Valve 1" bh 180,000.00
97 Gate Valve 1 1/4" bh 201,000.00
98 Gate Valve 1 1/2" bh 355,000.00
99 Gate Valve 2" bh 702,000.00
100 Gate Valve 2 1/2" bh 1,375,000.00
101 Gate Valve 3" bh 1,641,000.00
102 Gate Valve 4" bh 2,490,000.00
103 Gate Valve 5" bh 3,680,000.00
104 Gate Valve 6" bh 4,670,000.00
105 Strainer 2" bh 425,800.00
106 Strainer 2 1/2" bh 935,100.00
107 Strainer 3" bh 1,590,000.00
108 Strainer 6" bh 4,410,000.00
109 Flexible Joint 1 1/2" bh 625,000.00
110 Flexible Joint 2" bh 748,000.00
111 Flexible Joint 2 1/2" bh 975,000.00
112 Flexible Joint 3" bh 1,425,000.00
113 Flexible Joint 5" bh 2,500,000.00
114 Flexible Joint 6" bh 3,075,000.00
115 Check Valve 1 1/2" bh 1,860,000.00
116 Check Valve 2" bh 2,170,000.00
117 Check Valve 2 1/2" bh 3,725,000.00
118 Check Valve 5" bh 7,045,000.00
119 Float Valve 2" bh 2,145,000.00
120 Foot Valve 3" bh 3,250,000.00
121 Safety Valve 4" bh 7,885,000.00
122 Clean Out diameter 4" bh 255,000.00
123 Clean Out diameter 6" bh 315,000.00
PEKERJAAN MEKANIKAL:
PEKERJAAN DEEP WELL
Pompa Deep Well 35,000,000.00
Screen Stainless Steel 950,000.00
Pengeboran termasuk pengisian kerikil 29,160,000.00
Pipa instalasi dari pompa s/d water meter dg pipa Galvanis Medium 135,000.00
Gate Valve 700,000.00
Bak kontrol ukuran (60 x 80) cm dengan tutup chequer plate 750,000.00
WLC u/Sumur dalam + Pengkabelan 850,000.00
Biaya Geolistrik 20,000,000.00
Biaya perijinan termasuk water meter 65 mm 7,000,000.00
Testing Commissioning 5,000,000.00
PEKERJAAN MEKANIKAL:
PEKERJAAN TRANSFORMATOR DAYA DAN SUPLAI TEGANGAN MENENGAH
Transformer 150,000,000.00
Incoming Cubicle PUTM Type DM-1A 215,000,000.00
Outgoing Cubicle DM (lihat Spesifikasi Teknis) 65,800,000.00
1 titik Instalasi AC 1 PH
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PVC AW 3/4” M 1.2 10,000.00 12,000.00
Perlengkapan % 35% 10,000.00 3,500.00
JUMLAH HARGA BAHAN 15,500.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PVC AW 1” M 1.2 11,000.00 13,200.00
Perlengkapan % 35% 11,000.00 3,850.00
JUMLAH HARGA BAHAN 17,050.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC AW 1 1/4” M 1.2 16,200.00 19,440.00
Perlengkapan % 35% 16,200.00 5,670.00
JUMLAH HARGA BAHAN 25,110.00
C PERALATAN 0.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC AW 1 1/2” M 1.2 18,600.00 22,320.00
Perlengkapan % 35% 18,600.00 6,510.00
JUMLAH HARGA BAHAN 28,830.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC D 1 1/4” M 1.2 10,175.00 12,210.00
Perlengkapan % 35% 10,175.00 3,561.25
JUMLAH HARGA BAHAN 15,771.25
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC D 1 1/2” M 1.2 11,500.00 13,800.00
Perlengkapan % 35% 11,500.00 4,025.00
JUMLAH HARGA BAHAN 17,825.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PVC AW 2” M 1.2 18,000.00 21,600.00
Perlengkapan % 35% 18,000.00 6,300.00
JUMLAH HARGA BAHAN 27,900.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 2” Bh 1.1 18,000.00 19,800.00
Perlengkapan % 35% 18,000.00 6,300.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 47,025.60
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC AW 2 1/2” M 1.2 34,725.00 41,670.00
Perlengkapan % 35% 34,725.00 12,153.75
JUMLAH HARGA BAHAN 53,823.75
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 2 1/2” M 1.1 34,725.00 38,197.50
Perlengkapan % 35% 34,725.00 12,153.75
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 71,276.85
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC AW 3” M 1.2 31,000.00 37,200.00
Perlengkapan % 35% 31,000.00 10,850.00
JUMLAH HARGA BAHAN 48,050.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 3” m 1.1 31,000.00 34,100.00
Perlengkapan % 35% 31,000.00 10,850.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 65,875.60
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC D 4” M 1.2 41,600.00 49,920.00
Perlengkapan % 35% 41,600.00 14,560.00
JUMLAH HARGA BAHAN 64,480.00
C PERALATAN
A.5.1.1 32. Pemasangan 1 titik pipa PVC tipe D diameter 4” untuk EXHAUST FAN TOILET
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC D 4” M 7.5 41,600.00 312,000.00
Perlengkapan % 35% 41,600.00 14,560.00
Flexible dan accessories % 20% 41,600.00 8,320.00
JUMLAH HARGA BAHAN 334,880.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PVC AW 4” M 1.2 50,000.00 60,000.00
Perlengkapan % 35% 50,000.00 17,500.00
JUMLAH HARGA BAHAN 77,500.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 4” Bh 1.1 50,000.00 55,000.00
Perlengkapan % 35% 50,000.00 17,500.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 93,425.60
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.118 103,000.00 12,154.00
Tukang pipa L.02 OH 0.059 109,000.00 6,431.00
Mandor L.04 OH 0.012 116,000.00 1,392.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PVC AW 6” Bh 1 180,050.00 180,050.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 200,975.60
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 1/2” M 1.2 12,039.50 14,447.40
Perlengkapan % 35% 12,039.50 4,213.83
JUMLAH HARGA BAHAN 18,661.23
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 3/4” M 1.2 15,760.25 18,912.30
Perlengkapan % 35% 15,760.25 5,516.09
JUMLAH HARGA BAHAN 24,428.39
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 3/4” M 1.2 15,760.25 18,912.30
Perlengkapan % 35% 15,760.25 5,516.09
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 45,353.99
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 1” M 1.2 25,349.50 30,419.40
Perlengkapan % 35% 25,349.50 8,872.33
JUMLAH HARGA BAHAN 39,291.73
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 10 1” M 1.2 25,349.50 30,419.40
Perlengkapan % 35% 25,349.50 8,872.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 60,217.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 10 11/4” M 1.2 40,172.00 48,206.40
Perlengkapan % 35% 40,172.00 14,060.20
JUMLAH HARGA BAHAN 62,266.60
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 10 1 1/2” M 1.2 62,315.00 74,778.00
Perlengkapan % 35% 62,315.00 21,810.25
JUMLAH HARGA BAHAN 96,588.25
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PPR PN 10 DIA 1 1/2” Bh 1.2 62,315.00 74,778.00
Perlengkapan % 35% 62,315.00 21,810.25
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 117,513.85
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PPR PN 10 2” Bh 1.2 98,645.25 118,374.30
Perlengkapan % 35% 98,645.25 34,525.84
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 173,825.74
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PPR PN 10 2 1/2” M 1.2 138,030.75 165,636.90
Perlengkapan % 35% 138,030.75 48,310.76
JUMLAH HARGA BAHAN 213,947.66
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PPR PN 10 3” M 1.2 199,226.50 239,071.80
Perlengkapan % 35% 199,226.50 69,729.28
JUMLAH HARGA BAHAN 308,801.08
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 103,000.00 8,343.00
Tukang Pipa L.02 OH 0.135 109,000.00 14,715.00
Kepala tukang L.03 OH 0.0135 147,000.00 1,984.50
Mandor L.04 OH 0.004 116,000.00 464.00
JUMLAH TENAGA KERJA 25,506.50
B BAHAN
Pipa PPR PN 10 4” M 1.2 295,875.25 355,050.30
Perlengkapan % 35% 295,875.25 103,556.34
JUMLAH HARGA BAHAN 458,606.64
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa PPR PN 10 4” Bh 1.2 295,875.25 355,050.30
Perlengkapan % 35% 295,875.25 103,556.34
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 479,532.24
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 20 1/2” M 1.2 16,698.00 20,037.60
Perlengkapan % 35% 16,698.00 5,844.30
JUMLAH HARGA BAHAN 25,881.90
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 20 3/4” M 1.2 25,621.75 30,746.10
Perlengkapan % 35% 25,621.75 8,967.61
JUMLAH HARGA BAHAN 39,713.71
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 103,000.00 3,708.00
Tukang Pipa L.02 OH 0.06 109,000.00 6,540.00
Kepala tukang L.03 OH 0.006 147,000.00 882.00
Mandor L.04 OH 0.002 116,000.00 232.00
JUMLAH TENAGA KERJA 11,362.00
B BAHAN
Pipa PPR PN 20 1” M 1.2 42,138.25 50,565.90
Perlengkapan % 35% 42,138.25 14,748.39
JUMLAH HARGA BAHAN 65,314.29
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 20 1 1/2” M 1.2 101,549.25 121,859.10
Perlengkapan % 35% 101,549.25 35,542.24
JUMLAH HARGA BAHAN 157,401.34
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.003 116,000.00 348.00
JUMLAH TENAGA KERJA 17,043.00
B BAHAN
Pipa PPR PN 20 2” M 1.2 160,899.75 193,079.70
Perlengkapan % 35% 160,899.75 56,314.91
JUMLAH HARGA BAHAN 249,394.61
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa galvanis ½” M 1.2 42,000.00 50,400.00
Perlengkapan Ls 35% 42,000.00 14,700.00
JUMLAH HARGA BAHAN 65,100.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa galvanis 3/4” M 1.2 54,000.00 64,800.00
Perlengkapan % 35% 54,000.00 18,900.00
JUMLAH HARGA BAHAN 83,700.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa galvanis 1” M 1.2 82,833.33 99,400.00
Perlengkapan % 35% 82,833.33 28,991.67
JUMLAH HARGA BAHAN 128,391.67
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa galvanis 1 1/4” M 1.2 109,333.33 131,200.00
Perlengkapan % 35% 109,333.33 38,266.67
JUMLAH HARGA BAHAN 169,466.67
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa galvanis 1 1/2” M 1.2 125,666.67 150,800.00
Perlengkapan % 35% 125,666.67 43,983.33
JUMLAH HARGA BAHAN 194,783.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis 2.5” M 1.2 218,833.33 262,600.00
Perlengkapan % 35% 218,833.33 76,591.67
JUMLAH HARGA BAHAN 339,191.67
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis 3” M 1.2 282,666.67 339,200.00
Perlengkapan % 35% 98,933.33 98,933.33
JUMLAH HARGA BAHAN 438,133.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa galvanis Medium 4” M 1.2 409,166.67 491,000.00
Perlengkapan % 35% 409,166.67 143,208.33
JUMLAH HARGA BAHAN 634,208.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa GIP Medium 4” Bh 1.2 409,166.67 491,000.00
Perlengkapan % 35% 409,166.67 143,208.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 655,133.93
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T
JUMLAH HARGA ALAT 700.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.506 103,000.00 52,118.00
Tukang pipa L.02 OH 0.253 109,000.00 27,577.00
Mandor L.04 OH 0.051 116,000.00 5,916.00
JUMLAH TENAGA KERJA 85,611.00
B BAHAN
Pipa GIP Ø 150 mm 6" m 1 655,500.00 655,500.00
JUMLAH HARGA BAHAN 655,500.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.028 25,000.00 700.00
handle crane 2 T
JUMLAH HARGA ALAT 700.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
A.5.1.1.36. Pemasangan 1 m’ pipa GIP MEDIUM Underground diameter 150 cm/6 "
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.506 103,000.00 52,118.00
Tukang Pipa L.02 OH 0.253 109,000.00 27,577.00
Kepala tukang L.03 OH 0.051 147,000.00 7,497.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 89,396.00
B BAHAN
Pipa GIP Medium 6” Bh 1 655,500.00 655,500.00
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 676,425.60
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa BS SCH 40 ½” M 1.2 32,541.67 39,050.00
Perlengkapan Ls 35% 32,541.67 11,389.58
JUMLAH HARGA BAHAN 50,439.58
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa BS SCH 40 3/4” M 1.2 41,333.33 49,600.00
Perlengkapan % 35% 41,333.33 14,466.67
JUMLAH HARGA BAHAN 64,066.67
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 103,000.00 5,562.00
Tukang Pipa L.02 OH 0.09 109,000.00 9,810.00
Kepala tukang L.03 OH 0.009 147,000.00 1,323.00
Mandor L.04 OH 0.027 116,000.00 3,132.00
JUMLAH TENAGA KERJA 19,827.00
B BAHAN
Pipa BS SCH 40 1” M 1.2 61,166.67 73,400.00
Perlengkapan % 35% 61,166.67 21,408.33
JUMLAH HARGA BAHAN 94,808.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa BS SCH 40 1 1/4” M 1.2 83,500.00 100,200.00
Perlengkapan % 35% 83,500.00 29,225.00
JUMLAH HARGA BAHAN 129,425.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 103,000.00 11,124.00
Tukang Pipa L.02 OH 0.18 109,000.00 19,620.00
Kepala tukang L.03 OH 0.018 147,000.00 2,646.00
Mandor L.04 OH 0.005 116,000.00 580.00
JUMLAH TENAGA KERJA 33,970.00
B BAHAN
Pipa BS SCH 40 1 1/2” M 1.2 99,166.67 119,000.00
Perlengkapan % 35% 99,166.67 34,708.33
JUMLAH HARGA BAHAN 153,708.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 2” M 1.2 132,500.00 159,000.00
Perlengkapan % 35% 132,500.00 46,375.00
JUMLAH HARGA BAHAN 205,375.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 2.5” M 1.2 211,166.67 253,400.00
Perlengkapan % 35% 211,166.67 73,908.33
JUMLAH HARGA BAHAN 327,308.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 4” M 1.2 391,833.33 470,200.00
Perlengkapan % 35% 391,833.33 137,141.67
JUMLAH HARGA BAHAN 607,341.67
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 5” M 1.2 530,166.67 636,200.00
Perlengkapan % 35% 530,166.67 185,558.33
JUMLAH HARGA BAHAN 821,758.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 103,000.00 13,905.00
Tukang Pipa L.02 OH 0.225 109,000.00 24,525.00
Kepala tukang L.03 OH 0.023 147,000.00 3,381.00
Mandor L.04 OH 0.007 116,000.00 812.00
JUMLAH TENAGA KERJA 42,623.00
B BAHAN
Pipa BS SCH 40 6” M 1.2 685,166.67 822,200.00
Perlengkapan % 35% 685,166.67 239,808.33
JUMLAH HARGA BAHAN 1,062,008.33
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.38 103,000.00 39,140.00
Tukang Pipa L.02 OH 0.19 109,000.00 20,710.00
Kepala tukang L.03 OH 0.019 147,000.00 2,793.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 64,847.00
B BAHAN
Pipa BS SCH 40 4” Bh 1.2 391,833.33 470,200.00
Perlengkapan % 35% 137,141.67 47,999.58
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 539,125.18
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.648 103,000.00 66,744.00
Tukang pipa L.02 OH 0.13 109,000.00 14,170.00
Mandor L.04 OH 0.065 116,000.00 7,540.00
JUMLAH TENAGA KERJA 88,454.00
B BAHAN
Pipa Baja Ø 125 mm m 1.2 530,166.67 636,200.00
JUMLAH TENAGA KERJA 636,200.00
C PERALATAN
Sewa Tripot/Tackel & hari 0.004 25,000.00 100.00
handle crane 2 T
JUMLAH HARGA ALAT 100.00
D Jumlah (A+B+C) 724,754.00
E Overhead & Profit (Contoh 15 %) 10% 72,475.40
F Harga Satuan Pekerjaan (D+E) 797,229.40
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.648 103,000.00 66,744.00
Tukang Pipa L.02 OH 0.13 109,000.00 14,170.00
Kepala tukang L.03 OH 0.065 147,000.00 9,555.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 92,673.00
B BAHAN
Pipa BS SCH 40 5” Bh 1.1 530,166.67 583,183.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 604,108.93
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.708 103,000.00 72,924.00
Tukang pipa L.02 OH 0.142 109,000.00 15,478.00
Mandor L.04 OH 0.071 116,000.00 8,236.00
JUMLAH TENAGA KERJA 96,638.00
B BAHAN
Pipa Baja Ø 150 mm 6" m 1 685,166.67 685,166.67
JUMLAH TENAGA KERJA 685,166.67
C PERALATAN
Sewa Tripot/Tackel & hari 0.004 25,000.00 100.00
handle crane 2 T
JUMLAH HARGA ALAT 100.00
D Jumlah (A+B+C) 781,904.67
E Overhead & Profit (Contoh 15 %) 10% 78,190.47
F Harga Satuan Pekerjaan (D+E) 860,095.13
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.106 103,000.00 10,918.00
Tukang pipa L.02 OH 0.053 109,000.00 5,777.00
Mandor L.04 OH 0.011 116,000.00 1,276.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.708 103,000.00 72,924.00
Tukang Pipa L.02 OH 0.142 109,000.00 15,478.00
Kepala tukang L.03 OH 0.071 147,000.00 10,437.00
Mandor L.04 OH 0.019 116,000.00 2,204.00
JUMLAH TENAGA KERJA 101,043.00
B BAHAN
Pipa BS SCH 40 DIA 6” Bh 1.1 685,166.67 753,683.33
Pasir pasang M3 0.061 165,000.00 10,065.00
Pasir urug M3 0.069 157,400.00 10,860.60
JUMLAH HARGA BAHAN 774,608.93
C PERALATAN
0.00
JUMLAH HARGA ALAT 0
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.096 103,000.00 215,888.00
Tukang pipa L.02 OH 1.048 109,000.00 114,232.00
Mandor L.04 OH 0.21 116,000.00 24,360.00
PENAMBAHAN
01 MEKANIKAL
ROOF/ATAP
1 Pompa Booster set 1.00 25,000,000.00 25,000,000.00
- Pompa 2kW / 3ph / 220V/380V / 50 Hz / 2900 rpm (1 set = 2 unit)
- Head = 12 meter / Q = 200 Lt/mnt
- Panel, kabel power & control WLC
- Fitting, valve, pressure gauge, header, pressure switch, Pressure tank 170 Liter
- Assesoris standar & material bantu lengkap 1 set
- Testing & Commissioning
2 Rooftank FRP kapasitas 66 m³ Tirta Plaza unit 1.00 323,100,000.00 323,100,000.00
3 Float Valve 2" Empiris bh 1.00 2,454,595.00 2,454,595.00
4 Gate Valve 3" Empiris bh 2.00 1,977,855.00 3,955,710.00
5 Gate Valve 2" Empiris bh 2.00 865,810.00 1,731,620.00
6 Pipa GIP Medium dia. 3" A.5.1.1.23 m' 1.90 528,831.97 1,004,780.74
7 Pipa GIP Medium dia. 2" A.5.1.1.23 m' 0.50 339,292.80 169,646.40
8 Pipa PPR PN-10 dia. 3" A.5.1.1.31 m' 1.80 367,738.33 661,929.00
9 Pipa PVC AW dia. 2" A.5.1.1.29 m' 439.60 49,437.30 21,732,637.08
INSTALASI SHAFT
1 Pipa PVC AW dia. 2,5" (Inlet ke Rooftank) A.5.1.1.29 m' 35.00 87,263.28 3,054,214.63
2 Pipa PVC AW dia. 2.5" (Inlet Underground) ke Ground Tank Utama A.5.1.1.29 m' 103.74 149,736.24 15,533,637.02
3 Pipa PVC AW dia. 2" (Shaft) A.5.1.1.29 m' 154.00 49,437.30 7,613,344.20
4 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.00 50,460.30 756,904.50
5 Pipa PVC AW dia. 1 1/4" A.5.1.1.28 m' 22.00 46,368.30 1,020,102.60
6 Pipa PVC AW dia. 1" A.5.1.1 27 m' 15.00 31,253.20 468,798.00
LANTAI 1
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 10.40 50,460.30 524,787.12
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 44.30 46,368.30 2,054,115.69
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 116.50 31,253.20 3,640,997.80
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 299.20 29,548.20 8,840,821.44
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 67.00 24,433.20 1,637,024.40
6 Gate Valve 2" Empiris bh 3.00 702,000.00 2,106,000.00
7 Gate Valve 1 1/2" Empiris bh 6.00 355,000.00 2,130,000.00
8 Gate Valve 1 1/4" Empiris bh 18.00 266,530.00 4,797,540.00
9 Kran Taman LS bh 4.00 325,000.00 1,300,000.00
10 Waterheater 15 L LS bh 4.00 1,832,600.00 7,330,400.00
11 Waterheater 30 L LS bh 8.00 2,566,200.00 20,529,600.00
12 Waterheater 50 L LS bh 24.00 3,688,000.00 88,512,000.00
13 Pipa PPR PN-20 dia. 3/4" m' 171.50 56,183.28 9,635,433.16
LANTAI 2
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.30 50,460.30 772,042.59
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 40.30 46,368.30 1,868,642.49
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 110.10 31,253.20 3,440,977.32
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 515.40 29,548.20 15,229,142.28
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 77.00 24,433.20 1,881,356.40
6 Gate Valve 2" Empiris bh 4.00 748,000.00 2,992,000.00
7 Gate Valve 1 1/2" Empiris bh 6.00 355,000.00 2,130,000.00
8 Gate Valve 1 1/4" Empiris bh 18.00 266,530.00 4,797,540.00
9 Waterheater 15 L LS bh 4.00 1,832,600.00 7,330,400.00
10 Waterheater 30 L LS bh 11.00 2,566,200.00 28,228,200.00
11 Waterheater 50 L LS bh 23.00 3,680,000.00 84,640,000.00
12 Pipa PPR PN-20 dia. 3/4" m' 108.00 56,183.28 6,067,794.65
PERALATAN UTAMA
SHAFT
1 Pipa PVC AW dia. 4"(shaft) A.5.1.1.36 m' 154.00 113,307.15 17,449,301.10
LANTAI 1
1 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph LS unit 2.00 20,000,000.00 40,000,000.00
c/w guide rel, chain,automatic level switch, Control Panel & Kabel
2 Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 m' 38.00 292,404.86 11,111,384.68
3 Fitting Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 bh 320.00 307,528.10 98,408,992.00
4 Pipa PVC AW dia. 4" A.5.1.1.36 m' 168.60 113,307.15 19,103,585.49
5 Pipa PVC AW dia. 3" A.5.1.1.36 m' 346.90 143,794.86 49,882,436.93
6 Pipa PVC AW dia. 2" A.5.1.1.29 m' 80.20 49,437.30 3,964,871.46
7 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 23.00 46,368.30 1,066,470.90
8 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 324.60 36,095.68 11,716,656.11
9 CO dia. 4" Empiris bh 2.00 338,305.00 676,610.00
10 CO dia. 6" Empiris bh 36.00 404,965.00 14,578,740.00
11 Vent Cap dia. 2" LS bh 16.00 45,000.00 720,000.00
13 Bak Kontrol Uk. 75x75x75 cm³ Tebal 10 cm LS unit 2.00 935,607.49 1,871,214.98
14 Septic Tank Uk. 12 m³ Tirta Plaza LS unit 1.00 128,500,000.00 128,500,000.00
include: FRP tank, screen, tank anaerob, sedimentation device
LANTAI 2
1 Pipa PVC AW dia. 4" A.5.1.1.36 m' 153.46 113,307.15 17,388,115.24
2 Pipa PVC AW dia. 3" A.5.1.1.36 m' 339.10 143,794.86 48,760,837.03
3 Pipa PVC AW dia. 2" A.5.1.1.29 m' 75.60 49,437.30 3,737,459.88
4 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 22.50 46,368.30 1,043,286.75
5 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 302.50 36,095.68 10,918,941.69
6 CO dia. 4" Empiris bh 4.00 338,305.00 1,353,220.00
BANGUNAN UTAMA
1 Pipa air hujan PVC AW dia.4" A.5.1.1 32 m' 642.00 113,307.15 72,743,190.30
2 Roofdrain (cast iron tipe meshroom) 4" bh 45.00 121,000.00 5,445,000.00
3 Gutter 30x30 cm2 Empiris m' 50.00 434,944.84 21,747,242.00
4 Bak Kontrol Uk. 75x75x75 cm³ LS unit 4.00 935,607.49 3,742,429.97
5 Sumur Resapan uk. 3 m3 (bangunan) LS unit 4.00 3,082,784.29 12,331,137.18
6 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph Ex Grundfos LS unit 4.00 20,000,000.00 80,000,000.00
c/w guide rel, chain,automatic level switch, Control Panel & Kabel
LANTAI 1
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 579,768.84 33,394,685.28
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 5,973,445.50 23,893,782.00
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”
LANTAI 2
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 579,768.84 33,394,685.28
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 5,973,445.50 23,893,782.00
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”
LANTAI 1
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 714,961.13 20,018,911.73
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 579,768.84 26,263,528.53
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 66.20 406,924.47 26,938,399.69
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 52.10 272,797.80 14,212,765.38
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 86.72 206,446.17 17,903,011.57
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 97.20 179,734.50 17,470,193.40
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 371.60 126,098.87 46,858,338.85
8 Head Pendant Sprinkler Empiris unit 136.00 84,865.00 11,541,640.00
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 8,120,000.00 8,120,000.00
10 Siamese Connectiom bh 2.00 2,365,000.00 4,730,000.00
LANTAI 2
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 714,961.13 20,018,911.73
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 579,768.84 26,263,528.53
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 37.70 406,924.47 15,341,052.39
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 39.60 272,797.80 10,802,792.88
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 42.00 206,446.17 8,670,739.00
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 103.30 179,734.50 18,566,573.85
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 347.70 126,098.87 43,844,575.94
8 Head Pendant Sprinkler Empiris unit 143.00 84,865.00 12,135,695.00
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 8,120,000.00 8,120,000.00
FIRE EXTINGUISHER
Pengadaan dan pemasangan fire extinguisher Dry Chemical kapasitas 3 kg,
lengkap terpasang dengan alat bantu dan accessories lain yang diperlukan
serta testing sistem terpasang.
LANTAI 1
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 6.00 838,000.00 5,028,000.00
LANTAI 2
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 5.00 838,000.00 4,190,000.00
1 Unit AC Split Wall 5.000 Btuh R-32 INDOOR unit 14.00 4,037,000.00 56,518,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 14.00 2,036,592.25 28,512,291.50
2 Unit AC Split Wall 7.100 Btuh R-32 INDOOR unit 1.00 4,191,000.00 4,191,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 2,036,592.25 2,036,592.25
3 Unit AC Split Wall 11.100 Btuh R-32 INDOOR unit 6.00 5,456,000.00 32,736,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 6.00 2,036,592.25 12,219,553.50
4 Unit AC Split Wall 17.100 Btuh R-32 INDOOR unit 109.00 7,260,000.00 791,340,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 109.00 2,398,107.25 261,393,690.25
5 Unit AC low static duct 9.000 Btuh R-410A unit 2.00 7,216,000.00 14,432,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 2.00 2,398,107.25 4,796,214.50
6 Unit AC mid static duct 30.000 Btuh R-410A (3 ph) unit 2.00 22,022,000.00 44,044,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 2.00 2,398,107.25 4,796,214.50
7 Unit AC packaged duct 50.000 Btuh R-410A unit 16.00 39,644,000.00 634,304,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 16.00 2,398,107.25 38,369,716.00
8 Unit AC packaged duct 60.000 Btuh R-410A unit 1.00 49,434,000.00 49,434,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 2,398,107.25 2,398,107.25
9 Unit AC packaged duct 80.000 Btuh R-410A unit 1.00 61,226,000.00 61,226,000.00
- Instalasi pipa Refrigerant, drain & Kabel Kontrol IU-OU Empiris ls 1.00 2,398,107.25 2,398,107.25
10 Pekerjaan Ducting ls 22.00 7,000,000.00 154,000,000.00
11 Exhaust Toilet Fan Type Wall 50 cfm, 30 cm unit 136.00 705,000.00 95,880,000.00
LANTAI 1
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 72.00 2,185,800.00 157,377,600.00
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 72.00 2,185,800.00 157,377,600.00
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 11.00 2,185,800.00 24,043,800.00
4 Instalasi Pipa Gas Medis :
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 72.92 261,307.20 19,054,521.02
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 158.14 234,379.20 37,064,726.69
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 494.80 190,027.20 94,025,458.56
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 612.06 163,099.20 99,826,496.35
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 337.23 146,308.80 49,339,716.62
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 22,210,000.00 22,210,000.00
6 Ball Valve 1/2" set 1.00 133,600.00 133,600.00
7 Ball Valve 3/4" set 1.00 176,900.00 176,900.00
8 Ball Valve 1" set 1.00 215,000.00 215,000.00
LANTAI 2
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 93.00 2,185,800.00 203,279,400.00
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 93.00 2,185,800.00 203,279,400.00
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 3.00 2,185,800.00 6,557,400.00
4 Instalasi Pipa Gas Medis :
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 74.90 261,307.20 19,571,909.28
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 177.90 234,379.20 41,696,059.68
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 491.22 190,027.20 93,345,161.18
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 576.61 163,099.20 94,044,629.71
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 333.07 146,308.80 48,731,072.02
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 22,210,000.00 22,210,000.00
6 Ball Valve 1/2" set 1.00 133,600.00 133,600.00
7 Ball Valve 3/4" set 1.00 176,900.00 176,900.00
8 Ball Valve 1" set 1.00 215,000.00 215,000.00
02 ELEKTRIKAL
1 Kabel dari SDP 3 ke LP.C1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 278,135.00 834,405.00
2 Kabel dari SDP 3 ke PP.AC-C1; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 5.00 151,835.75 759,178.75
3 Kabel dari SDP 3 ke LP.C2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 278,135.00 834,405.00
4 Kabel dari SDP 3 ke PP.AC-C2; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 10.00 151,835.75 1,518,357.50
5 Kabel dari SDP 3 ke PP.WH1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 278,135.00 834,405.00
6 Kabel dari SDP 3 ke PP.WH2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 8.00 278,135.00 2,225,080.00
7 Kabel dari SDP 3 ke LP.Atap; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 30.00 74,673.50 2,240,205.00
8 Kabel dari PUTR ke CP.LIFT; menggunakan kabel FRC 4 x 16 mm²+ BC 16 mm² Empiris m' 130.00 269,291.00 35,007,830.00
9 Kabel dari PP.ATAP ke CP.BOOSTER PUMP; menggunakan kabel NYY 5 x 2.5 mm² Empiris m' 20.00 58,437.50 1,168,750.00
10 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-27; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 74,673.50 4,480,410.00
11 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-28; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
12 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 74,673.50 5,227,145.00
13 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 74,673.50 5,227,145.00
14 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-51; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
15 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-52; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 50.00 74,673.50 3,733,675.00
16 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 74,673.50 4,480,410.00
17 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 74,673.50 2,986,940.00
18 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-57; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
19 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-58; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
20 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-59; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 55.00 74,673.50 4,107,042.50
21 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-60; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 74,673.50 4,480,410.00
22 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-61; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
23 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-11; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
24 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-18; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
25 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-23; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 74,673.50 2,986,940.00
26 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-42; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
27 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 74,673.50 3,360,307.50
28 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 74,673.50 4,853,777.50
29 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 74,673.50 2,986,940.00
30 Kabel dari PP.POMPA ke POMPA TRANSFER 1; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 92,952.75 929,527.50
31 Kabel dari PP.POMPA ke POMPA TRANSFER 2; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 92,952.75 929,527.50
RISER
1 Kabel Ladder Lantai 1 W:400mm H:100mm, tebal plat 2mm Empiris m' 16.00 246,840.00 3,949,440.00
2 Kabel Tray Lantai 1 W:300mm H:100mm, tebal plat 2mm Empiris m' 16.00 330,000.00 5,280,000.00
3 Material bantu & aksesoris ls 1.00 3,230,304.00 3,230,304.00
Lantai 1
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 460,000.00 9,200,000.00
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 330,000.00 49,500,000.00
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 274,560.00 10,982,400.00
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 246,840.00 2,715,240.00
5 Material bantu & aksesoris ls 1.00 2,931,000.00 2,931,000.00
Lantai 2
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 460,000.00 9,200,000.00
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 330,000.00 49,500,000.00
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 274,560.00 10,982,400.00
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 246,840.00 2,715,240.00
5 Material bantu & aksesoris ls 1.00 2,931,000.00 2,931,000.00
Lantai ATAP
1 Kabel Tray Lantai 1 W:200mm H:100mm, tebal plat 2mm Empiris m' 20.00 274,560.00 5,491,200.00
2 Material bantu & aksesoris ls 1.00 637,500.00 637,500.00
LANTAI 1
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 560,000.00 2,240,000.00
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 124.00 475,200.00 58,924,800.00
3 TL 1x36W, BL Type LS unit 2.00 178,750.00 357,500.00
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 261.00 196,900.00 51,390,900.00
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 12.00 596,900.00 7,162,800.00
6 TLC 22W, armatur Baret Square LS unit 5.00 226,600.00 1,133,000.00
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 5.00 720,500.00 3,602,500.00
8 Instalasi Penerangan Empiris titik 413.00 246,510.00 101,808,630.00
9 Instalasi Power AC Empiris titik 82.00 467,610.00 38,344,020.00
10 Saklar tunggal inbow 10 A LS unit 165.00 32,500.00 5,362,500.00
11 Saklar ganda inbow 10 A LS unit 75.00 58,500.00 4,387,500.00
12 Saklar Hotel Tunggal inbow LS unit 5.00 85,000.00 425,000.00
13 Stop kontak 1 ph Inbow Single LS unit 266.00 45,500.00 12,103,000.00
14 Stop kontak 1 ph Outbow Single LS unit 8.00 45,500.00 364,000.00
15 Instalasi Stop Kontak 1ph, Single Empiris titik 274.00 305,272.00 83,644,528.00
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 72.00 3,318,900.00 238,960,800.00
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
LANTAI 2
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 560,000.00 2,240,000.00
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 122.00 475,200.00 57,974,400.00
3 TL 1x36W, BL Type LS unit 2.00 178,750.00 357,500.00
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 S unit 226.00 196,900.00 44,499,400.00
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 13.00 596,900.00 7,759,700.00
6 TLC 22W, armatur Baret Square LS unit 27.00 226,600.00 6,118,200.00
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 4.00 720,500.00 2,882,000.00
8 Instalasi Penerangan Empiris titik 398.00 246,510.00 98,110,980.00
9 Instalasi Power AC Empiris titik 77.00 467,610.00 36,005,970.00
10 Saklar tunggal inbow 10 A LS unit 142.00 32,500.00 4,615,000.00
11 Saklar ganda inbow 10 A LS unit 77.00 58,500.00 4,504,500.00
12 Saklar Hotel Tunggal inbow LS unit 5.00 85,000.00 425,000.00
13 Stop kontak 1 ph Inbow Single LS unit 248.00 45,500.00 11,284,000.00
14 Stop kontak 1 ph Outbow Single LS unit 10.00 45,500.00 455,000.00
15 Instalasi Stop Kontak 1ph, Single Empiris titik 258.00 305,272.00 78,760,176.00
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 93.00 3,318,900.00 308,657,700.00
LANTAI ATAP
1 TL 1x36W, Balk Type LS unit 4.00 178,750.00 715,000.00
2 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 1.00 196,900.00 196,900.00
3 TLC 22W, armatur Baret Square LS unit 1.00 226,600.00 226,600.00
4 Instalasi Penerangan Empiris titik 6.00 246,510.00 1,479,060.00
5 Saklar tunggal inbow 10 A LS unit 1.00 32,500.00 32,500.00
6 Saklar ganda inbow 10 A LS unit 1.00 58,500.00 58,500.00
7 Saklar Hotel Tunggal inbow LS unit 1.00 85,000.00 85,000.00
8 Stop kontak 1 ph Inbow Single LS unit 2.00 45,500.00 91,000.00
9 Instalasi Stop Kontak 1ph, Single Empiris titik 2.00 305,272.00 610,544.00
10 Stop kontak 3 ph 2200 Watt LS unit 6.00 133,900.00 803,400.00
11 Instalasi Stop Kontak 3ph, 2200 Watt Empiris titik 6.00 2,646,196.67 15,877,180.00
LANTAI 1
1 ROR Temperature Heat Detector Konvensional bh 108.00 210,900.00 22,777,200.00
2 Manual Call Point bh 1.00 225,000.00 225,000.00
3 Indicator Lamp bh 1.00 562,000.00 562,000.00
4 Alarm Bell bh 1.00 433,000.00 433,000.00
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 108.00 176,770.00 19,091,160.00
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 458,370.00 916,740.00
7 End Of Line bh 2.00 60,500.00 121,000.00
8 TBFA 1 bh 1.00 4,000,000.00 4,000,000.00
LANTAI 2
1 ROR Temperature Heat Detector Konvensional bh 103.00 210,900.00 21,722,700.00
2 Manual Call Point bh 1.00 225,000.00 225,000.00
3 Indicator Lamp bh 1.00 562,000.00 562,000.00
4 Alarm Bell bh 1.00 433,000.00 433,000.00
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 103.00 176,770.00 18,207,310.00
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 458,370.00 916,740.00
7 End Of Line bh 2.00 60,500.00 121,000.00
8 TBFA 1 bh 1.00 4,000,000.00 4,000,000.00
INSTALASI TELEPHONE
LANTAI 1
1 TBT - 1 unit 1.00 350,000.00 350,000.00
2 Outlet Telephone Extension tipe wall mounted LS bh 7.00 65,000.00 455,000.00
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 7.00 876,810.00 6,137,670.00
4 Single Line Telephone LS bh 8.00 375,000.00 3,000,000.00
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 1,650,000.00 1,650,000.00
LANTAI 2
1 TBT - 2 unit 1.00 350,000.00 350,000.00
2 Outlet Telephone Extension tipe wall mounted LS bh 8.00 65,000.00 520,000.00
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 8.00 876,810.00 7,014,480.00
4 Single Line Telephone LS bh 9.00 375,000.00 3,375,000.00
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 1,650,000.00 1,650,000.00
KABEL FEEDER
1 Kabel Feeder dari peralatan utama ke TBS-1 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 50.00 19,348.18 967,408.75
2 Kabel Feeder dari peralatan utama ke TBS-2 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 55.00 19,348.18 1,064,149.63
INSTALASI SPEAKER
LANTAI 1
1 TBS-1 unit 1.00 380,000.00 380,000.00
2 Ceilling Speaker 6 W TOA bh 20.00 102,000.00 2,040,000.00
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 20.00 224,730.00 4,494,600.00
LANTAI 2
1 TBS-1 unit 1.00 380,000.00 380,000.00
2 Ceilling Speaker 6 W TOA bh 17.00 102,000.00 1,734,000.00
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 17.00 224,730.00 3,820,410.00
PERALATAN UTAMA
Lantai 1
1 Splitter 2 Way unit 2.00 250,000.00 500,000.00
2 Splitter 4 Way unit 2.00 261,000.00 522,000.00
3 Coupler 2 Way unit 1.00 300,000.00 300,000.00
4 Coupler 4 Way unit 12.00 338,000.00 4,056,000.00
5 Outlet MATV unit 55.00 36,500.00 2,007,500.00
6 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 55.00 247,170.00 13,594,350.00
Lantai 2
1 Splitter 2 Way unit 3.00 250,000.00 750,000.00
2 Splitter 4 Way unit 1.00 261,000.00 261,000.00
3 Coupler 4 Way unit 12.00 338,000.00 4,056,000.00
4 Outlet MATV unit 49.00 36,500.00 1,788,500.00
5 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 49.00 247,170.00 12,111,330.00
RISER
1 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 1 LS m' 80.00 18,616.68 1,489,334.00
2 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 2 LS m' 90.00 18,616.68 1,675,500.75
LANTAI 1
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 2,000,000.00 2,000,000.00
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 10.00 1,000,000.00 10,000,000.00
3 Outlet data kabel LS bh 10.00 150,000.00 1,500,000.00
4 empiris 11 ttk 20.00 491,370.00 9,827,400.00
LANTAI 2
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 2,000,000.00 2,000,000.00
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 8.00 1,000,000.00 8,000,000.00
3 Outlet data kabel LS bh 9.00 150,000.00 1,350,000.00
4 empiris 11 ttk 17.00 491,370.00 8,353,290.00
LANTAI 1
1 Master Station unit 2.00 107,000,000.00 214,000,000.00
2 Display Anunciator unit 1.00 30,800,000.00 30,800,000.00
3 Call Report Software bh 1.00 6,160,000.00 6,160,000.00
4 Nurse call Console (connect with bead head) bh 72.00 2,070,000.00 149,040,000.00
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 1,232,000.00 68,992,000.00
6 Emergency Button (Toilet) bh 56.00 1,629,000.00 91,224,000.00
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 111,540.00 6,246,240.00
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 72.00 594,440.00 42,799,680.00
LANTAI 2
1 Master Station unit 2.00 107,000,000.00 214,000,000.00
2 Display Anunciator unit 1.00 30,800,000.00 30,800,000.00
3 Call Report Software bh 1.00 6,160,000.00 6,160,000.00
4 Nurse call Console (connect with bead head) bh 93.00 2,070,000.00 192,510,000.00
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 1,232,000.00 68,992,000.00
6 Emergency Button (Toilet) bh 56.00 1,629,000.00 91,224,000.00
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 111,540.00 6,246,240.00
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 93.00 594,440.00 55,282,920.00
03 SELASAR
1 Downlight E-27 23 Watt, armatur Down Light outbouw LS unit 38.00 196,900.00 7,482,200.00
2 Downlight E-27 23 Watt, armatur Down Light outbouw c/w Battery LS unit 9.00 596,900.00 5,372,100.00
3 Instalasi Penerangan Empiris titik 47.00 246,510.00 11,585,970.00
4 Saklar ganda inbow 10 A LS unit 2.00 58,500.00 117,000.00
01 PEKERJAAN MEKANIKAL Rp -
02 PEKERJAAN ELEKTRIKAL Rp -
03 PEKERJAAN SELASAR Rp -
01 MEKANIKAL
ROOF/ATAP
1 Pompa Booster set 1.00 -
- Pompa 2kW / 3ph / 220V/380V / 50 Hz / 2900 rpm (1 set = 2 unit)
- Head = 12 meter / Q = 200 Lt/mnt
- Panel, kabel power & control WLC
- Fitting, valve, pressure gauge, header, pressure switch, Pressure tank 170 Liter
- Assesoris standar & material bantu lengkap 1 set
- Testing & Commissioning
2 Rooftank FRP kapasitas 66 m³ Tirta Plaza unit 1.00 -
3 Float Valve 2" Empiris bh 1.00 -
4 Gate Valve 3" Empiris bh 2.00 -
5 Gate Valve 2" Empiris bh 2.00 -
6 Pipa GIP Medium dia. 3" A.5.1.1.23 m' 1.90 -
7 Pipa GIP Medium dia. 2" A.5.1.1.23 m' 0.50 -
8 Pipa PPR PN-10 dia. 3" A.5.1.1.31 m' 1.80 -
9 Pipa PVC AW dia. 2" A.5.1.1.29 m' 439.60 -
INSTALASI SHAFT
1 Pipa PVC AW dia. 2,5" (Inlet ke Rooftank) A.5.1.1.29 m' 35.00 -
2 Pipa PVC AW dia. 2.5" (Inlet Underground) ke Ground Tank Utama A.5.1.1.29 m' 103.74 -
3 Pipa PVC AW dia. 2" (Shaft) A.5.1.1.29 m' 154.00 -
4 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.00 -
5 Pipa PVC AW dia. 1 1/4" A.5.1.1.28 m' 22.00 -
6 Pipa PVC AW dia. 1" A.5.1.1 27 m' 15.00 -
LANTAI 1
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 10.40 -
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 44.30 -
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 116.50 -
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 299.20 -
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 67.00 -
6 Gate Valve 2" Empiris bh 3.00 -
7 Gate Valve 1 1/2" Empiris bh 6.00 -
8 Gate Valve 1 1/4" Empiris bh 18.00 -
9 Kran Taman LS bh 4.00 -
10 Waterheater 15 L LS bh 4.00 -
11 Waterheater 30 L LS bh 8.00 -
12 Waterheater 50 L LS bh 24.00 -
13 Pipa PPR PN-20 dia. 3/4" m' 171.50 -
LANTAI 2
1 Pipa PVC AW dia. 1 1/2" A.5.1.1.28 m' 15.30 -
2 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 40.30 -
3 Pipa PVC AW dia. 1" A.5.1.1 27 m' 110.10 -
4 Pipa PVC AW dia. 3/4" A.5.1.1 26 m' 515.40 -
5 Pipa PVC AW dia. 1/2" A.5.1.1 25 m' 77.00 -
6 Gate Valve 2" Empiris bh 4.00 -
7 Gate Valve 1 1/2" Empiris bh 6.00 -
8 Gate Valve 1 1/4" Empiris bh 18.00 -
9 Waterheater 15 L LS bh 4.00 -
10 Waterheater 30 L LS bh 11.00 -
11 Waterheater 50 L LS bh 23.00 -
12 Pipa PPR PN-20 dia. 3/4" m' 108.00 -
PERALATAN UTAMA
SHAFT
1 Pipa PVC AW dia. 4"(shaft) A.5.1.1.36 m' 154.00 -
LANTAI 1
1 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph LS unit 2.00 -
c/w guide rel, chain,automatic level switch, Control Panel & Kabel
2 Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 m' 38.00 -
3 Fitting Pipa PVC AW dia. 6" (Underground) A.5.1.1.36 bh 320.00 -
4 Pipa PVC AW dia. 4" A.5.1.1.36 m' 168.60 -
5 Pipa PVC AW dia. 3" A.5.1.1.36 m' 346.90 -
6 Pipa PVC AW dia. 2" A.5.1.1.29 m' 80.20 -
7 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 23.00 -
8 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 324.60 -
9 CO dia. 4" Empiris bh 2.00 -
10 CO dia. 6" Empiris bh 36.00 -
11 Vent Cap dia. 2" LS bh 16.00 -
13 Bak Kontrol Uk. 75x75x75 cm³ Tebal 10 cm LS unit 2.00 -
14 Septic Tank Uk. 12 m³ Tirta Plaza LS unit 1.00 -
include: FRP tank, screen, tank anaerob, sedimentation device
LANTAI 2
1 Pipa PVC AW dia. 4" A.5.1.1.36 m' 153.46 -
2 Pipa PVC AW dia. 3" A.5.1.1.36 m' 339.10 -
3 Pipa PVC AW dia. 2" A.5.1.1.29 m' 75.60 -
4 Pipa PVC AW dia. 1 1/4" A.5.1.1 28 m' 22.50 -
5 Pipa PVC D dia. 1 1/4" A.5.1.1 28 m' 302.50 -
6 CO dia. 4" Empiris bh 4.00 -
BANGUNAN UTAMA
1 Pipa air hujan PVC AW dia.4" A.5.1.1 32 m' 642.00 -
2 Roofdrain (cast iron tipe meshroom) 4" bh 45.00 -
3 Gutter 30x30 cm2 Empiris m' 50.00 -
4 Bak Kontrol Uk. 75x75x75 cm³ LS unit 4.00 -
5 Sumur Resapan uk. 3 m3 (bangunan) LS unit 4.00 -
6 Pompa Sumpit (2 bh) 100 Lpm, 10m, 0.75 k, 380V,3ph Ex Grundfos LS unit 4.00 -
c/w guide rel, chain,automatic level switch, Control Panel & Kabel
LANTAI 1
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 -
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 -
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”
LANTAI 2
1 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 57.60 -
2 Box Hydrant Indoor (IHB) lengkap dengan ( Hydrant Valve Machino cpl 10k 1,5” x 30 mtr); Empiris unit 4.00 -
Hydrant Valve, VDH Coupling 10K ø 2 1/2", Branchpipe c/w Straight Tip Nozzle ø 1 1/2",
Hose Rack 24 Comb 1,5”
LANTAI 1
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 -
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 -
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 66.20 -
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 52.10 -
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 86.72 -
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 97.20 -
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 371.60 -
8 Head Pendant Sprinkler Empiris unit 136.00 -
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 -
10 Siamese Connectiom bh 2.00 -
LANTAI 2
1 Pipa BS sch.40 dia 4" A.5.1.1.24 m' 28.00 -
2 Pipa BS sch.40 dia 3" A.5.1.1.23 m' 45.30 -
3 Pipa BS sch.40 dia 2,5" A.5.1.1.23 m' 37.70 -
4 Pipa BS sch.40 dia 2" A.5.1.1.23 m' 39.60 -
5 Pipa BS sch.40 dia 1 1/2" A.5.1.1.22 m' 42.00 -
6 Pipa BS sch.40 dia 1 1/4" A.5.1.1.22 m' 103.30 -
7 Pipa BS sch.40 dia 1" A.5.1.1.21 m' 347.70 -
8 Head Pendant Sprinkler Empiris unit 143.00 -
9 Branch Control Valve 4" (c/w Flowswitch TDV + Sight Glass) bh 1.00 -
FIRE EXTINGUISHER
Pengadaan dan pemasangan fire extinguisher Dry Chemical kapasitas 3 kg,
lengkap terpasang dengan alat bantu dan accessories lain yang diperlukan
serta testing sistem terpasang.
LANTAI 1
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 6.00 -
LANTAI 2
1 Portable fire extinguisher Dry Chemical kap. 3 kg LS unit 5.00 -
LANTAI 1
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 72.00 -
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 72.00 -
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 11.00 -
4 Instalasi Pipa Gas Medis :
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 72.92 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 158.14 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 494.80 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 612.06 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 337.23 -
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 -
6 Ball Valve 1/2" set 1.00 -
7 Ball Valve 3/4" set 1.00 -
8 Ball Valve 1" set 1.00 -
LANTAI 2
1 Pengadaan dan Pasang Multipoint/ Outlet Oksigen ( O2 ) Type Bedhead Wall bh 93.00 -
2 Pengadaan dan Pasang Multipoint/ Outlet Air Vacuum (Udara Vacuum) Type Bedhead Wall bh 93.00 -
3 Pengadaan dan Pasang Multipoint/ Outlet Compressed Air ( CA ) Type Bedhead Wall bh 3.00 -
4 Instalasi Pipa Gas Medis :
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1" Empiris m' 74.90 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/4" Empiris m' 177.90 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 5/8" Empiris m' 491.22 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 1/2" Empiris m' 576.61 -
- Pipa Tembaga ( Cooper Tube ) type – L ,ASTM B88 diameter 3/8" Empiris m' 333.07 -
5 Pengadaan dan Pasang Box Valve dan Zone Alarm set 1.00 -
6 Ball Valve 1/2" set 1.00 -
7 Ball Valve 3/4" set 1.00 -
8 Ball Valve 1" set 1.00 -
JUMLAH 01 MEKANIKAL -
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
02 ELEKTRIKAL
1 Kabel dari SDP 3 ke LP.C1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 -
2 Kabel dari SDP 3 ke PP.AC-C1; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 5.00 -
3 Kabel dari SDP 3 ke LP.C2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 -
4 Kabel dari SDP 3 ke PP.AC-C2; menggunakan kabel NYY 4 x 16 mm²+ BC 16mm² Empiris m' 10.00 -
5 Kabel dari SDP 3 ke PP.WH1; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 3.00 -
6 Kabel dari SDP 3 ke PP.WH2; menggunakan kabel NYY 4 x 25 mm² + BC 25mm² Empiris m' 8.00 -
7 Kabel dari SDP 3 ke LP.Atap; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 30.00 -
8 Kabel dari PUTR ke CP.LIFT; menggunakan kabel FRC 4 x 16 mm²+ BC 16 mm² Empiris m' 130.00 -
9 Kabel dari PP.ATAP ke CP.BOOSTER PUMP; menggunakan kabel NYY 5 x 2.5 mm² Empiris m' 20.00 -
10 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-27; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 -
11 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-28; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
12 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 -
13 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-35B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 70.00 -
14 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-51; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
15 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-52; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 50.00 -
16 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 -
17 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 -
18 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-57; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
19 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-58; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
20 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-59; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 55.00 -
21 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-60; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 60.00 -
22 Kabel dari PP.VAC C1 ke Unit Indoor VAC C1-61; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
23 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-11; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
24 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-18; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
25 Kabel dari PP.VAC C2 ke Unit Indoor VAC C2-23; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 -
26 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-42; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
27 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-56; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 45.00 -
28 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60A; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 65.00 -
29 Kabel dari PP.VAC C2 ke Unit Indoor VAC C1-60B; menggunakan kabel NYY 4 x 4 mm²+ BC 4 mm² Empiris m' 40.00 -
30 Kabel dari PP.POMPA ke POMPA TRANSFER 1; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 -
31 Kabel dari PP.POMPA ke POMPA TRANSFER 2; menggunakan kabel NYY 4 x 6 mm²+ BC 6mm² Empiris m' 10.00 -
RISER
1 Kabel Ladder Lantai 1 W:400mm H:100mm, tebal plat 2mm Empiris m' 16.00 -
2 Kabel Tray Lantai 1 W:300mm H:100mm, tebal plat 2mm Empiris m' 16.00 -
3 Material bantu & aksesoris ls 1.00 -
Lantai 1
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 -
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 -
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 -
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 -
5 Material bantu & aksesoris ls 1.00 -
Lantai 2
1 Kabel Tray W:500mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 20.00 -
2 Kabel Tray W:300mm H:100mm, tebal plat 2mm (Elektrikal) Empiris m' 150.00 -
3 Kabel Tray W:200mm H:100mm, tebal plat 2mm (Elektronik) Empiris m' 40.00 -
4 Kabel Tray W:100mm H:100mm, tebal plat 2mm Empiris m' 11.00 -
5 Material bantu & aksesoris ls 1.00 -
Lantai ATAP
1 Kabel Tray Lantai 1 W:200mm H:100mm, tebal plat 2mm Empiris m' 20.00 -
2 Material bantu & aksesoris ls 1.00 -
LANTAI 1
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 -
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 124.00 -
3 TL 1x36W, BL Type LS unit 2.00 -
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 261.00 -
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 12.00 -
6 TLC 22W, armatur Baret Square LS unit 5.00 -
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 5.00 -
8 Instalasi Penerangan Empiris titik 413.00 -
9 Instalasi Power AC Empiris titik 82.00 -
10 Saklar tunggal inbow 10 A LS unit 165.00 -
11 Saklar ganda inbow 10 A LS unit 75.00 -
12 Saklar Hotel Tunggal inbow LS unit 5.00 -
13 Stop kontak 1 ph Inbow Single LS unit 266.00 -
14 Stop kontak 1 ph Outbow Single LS unit 8.00 -
15 Instalasi Stop Kontak 1ph, Single Empiris titik 274.00 -
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 72.00 -
HARGA SATUAN JUMLAH HARGA
NO. ITEM URAIAN PEKERJAAN ANALISA SAT. VOLUME
(Rp.) (Rp.)
LANTAI 2
1 TL 2x36W, armatur inbouw RM 300 ALML(M2) LS unit 4.00 -
2 TL 2x18W, armatur inbouw RM 300 ALML(M2) LS unit 122.00 -
3 TL 1x36W, BL Type LS unit 2.00 -
4 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 S unit 226.00 -
5 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 13.00 -
6 TLC 22W, armatur Baret Square LS unit 27.00 -
7 EXIT Lamp (Sign) 18 Watt c/w Battery LS unit 4.00 -
8 Instalasi Penerangan Empiris titik 398.00 -
9 Instalasi Power AC Empiris titik 77.00 -
10 Saklar tunggal inbow 10 A LS unit 142.00 -
11 Saklar ganda inbow 10 A LS unit 77.00 -
12 Saklar Hotel Tunggal inbow LS unit 5.00 -
13 Stop kontak 1 ph Inbow Single LS unit 248.00 -
14 Stop kontak 1 ph Outbow Single LS unit 10.00 -
15 Instalasi Stop Kontak 1ph, Single Empiris titik 258.00 -
16 Bed Head Wall c/w (inc: 6 buah stop kontak, 1 lampu T5 14 watt, saklar, lubang gas, lubang nurse call) + Instalasi unit 93.00 -
LANTAI ATAP
1 TL 1x36W, Balk Type LS unit 4.00 -
2 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 1.00 -
3 TLC 22W, armatur Baret Square LS unit 1.00 -
4 Instalasi Penerangan Empiris titik 6.00 -
5 Saklar tunggal inbow 10 A LS unit 1.00 -
6 Saklar ganda inbow 10 A LS unit 1.00 -
7 Saklar Hotel Tunggal inbow LS unit 1.00 -
8 Stop kontak 1 ph Inbow Single LS unit 2.00 -
9 Instalasi Stop Kontak 1ph, Single Empiris titik 2.00 -
10 Stop kontak 3 ph 2200 Watt LS unit 6.00 -
11 Instalasi Stop Kontak 3ph, 2200 Watt Empiris titik 6.00 -
LANTAI 1
1 ROR Temperature Heat Detector Konvensional bh 108.00 -
2 Manual Call Point bh 1.00 -
3 Indicator Lamp bh 1.00 -
4 Alarm Bell bh 1.00 -
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 108.00 -
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 -
7 End Of Line bh 2.00 -
8 TBFA 1 bh 1.00 -
LANTAI 2
1 ROR Temperature Heat Detector Konvensional bh 103.00 -
2 Manual Call Point bh 1.00 -
3 Indicator Lamp bh 1.00 -
4 Alarm Bell bh 1.00 -
5 Instalasi titik detector, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 103.00 -
6 Instalasi titik Breakglass, indicator lamp dan alarm bell, 2 x NYA 1,5 mm² dlm PVC Conduit Ø 20 mm² ttk 2.00 -
7 End Of Line bh 2.00 -
8 TBFA 1 bh 1.00 -
INSTALASI TELEPHONE
LANTAI 1
1 TBT - 1 unit 1.00 -
2 Outlet Telephone Extension tipe wall mounted LS bh 7.00 -
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 7.00 -
4 Single Line Telephone LS bh 8.00 -
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 -
LANTAI 2
1 TBT - 2 unit 1.00 -
2 Outlet Telephone Extension tipe wall mounted LS bh 8.00 -
3 Instalasi Telepon, Kabel ITC 2 x 0,6 mm² dlm PVC Conduit HI Ø20mm Empiris ttk 8.00 -
4 Single Line Telephone LS bh 9.00 -
5 Mesin Fax (14.4 Kbps, 8s/page trans. Thermal, A4, Caller ID) LS bh 1.00 -
KABEL FEEDER
1 Kabel Feeder dari peralatan utama ke TBS-1 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 50.00 -
2 Kabel Feeder dari peralatan utama ke TBS-2 NYMHY 3x2.5 mm² dlm PVC Conduit HI Ø 20mm m' 55.00 -
INSTALASI SPEAKER
LANTAI 1
1 TBS-1 unit 1.00 -
2 Ceilling Speaker 6 W TOA bh 20.00 -
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 20.00 -
LANTAI 2
1 TBS-1 unit 1.00 -
2 Ceilling Speaker 6 W TOA bh 17.00 -
Instalasi ceiling speaker, NYMHY 3 x 2,5 mm² dalam conduit HI PVC ∅ 20mm
3 titik 17.00 -
PERALATAN UTAMA
Lantai 1
1 Splitter 2 Way unit 2.00 -
2 Splitter 4 Way unit 2.00 -
3 Coupler 2 Way unit 1.00 -
4 Coupler 4 Way unit 12.00 -
5 Outlet MATV unit 55.00 -
6 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 55.00 -
Lantai 2
1 Splitter 2 Way unit 3.00 -
2 Splitter 4 Way unit 1.00 -
3 Coupler 4 Way unit 12.00 -
4 Outlet MATV unit 49.00 -
5 Instalasi MATV, (termasuk Kabel Coaxial RG-6) dalam PVC conduit HI Ø 20mm titik 49.00 -
RISER
1 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 1 LS m' 80.00 -
2 Kabel Backbone Data UTP Cat 6 dari Hub Switch Sentral ke Hub Switch Lt. 2 LS m' 90.00 -
LANTAI 1
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 -
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 10.00 -
3 Outlet data kabel LS bh 10.00 -
4 empiris 11 ttk 20.00 -
LANTAI 2
1 SWITCH HUB 24 PORT RACKMOUNT CISCO MANAGED GIGABIT 10/100 Mbps LS unit 1.00 -
2 Wifi 3G/4G 600 Mbps Dual Band LS bh 8.00 -
3 Outlet data kabel LS bh 9.00 -
4 empiris 11 ttk 17.00 -
LANTAI 1
1 Master Station unit 2.00 -
2 Display Anunciator unit 1.00 -
3 Call Report Software bh 1.00 -
4 Nurse call Console (connect with bead head) bh 72.00 -
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 -
6 Emergency Button (Toilet) bh 56.00 -
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 -
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 72.00 -
LANTAI 2
1 Master Station unit 2.00 -
2 Display Anunciator unit 1.00 -
3 Call Report Software bh 1.00 -
4 Nurse call Console (connect with bead head) bh 93.00 -
(include: call cord, call button, speaker, mic, cancel button, call lamp, talk lamp, instalasi)
5 Corridor Light bh 56.00 -
6 Emergency Button (Toilet) bh 56.00 -
7 Instalasi Cabang 1 pair, Kabel ITC (2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 56.00 -
8 Instalasi Feeder Utama, Kabel ITC (2 x 2 x 0,6 mm²) dlm PVC Conduit HI Ø 20 mm ttk 93.00 -
JUMLAH 02 ELEKTRIKAL -
03 SELASAR
1 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 LS unit 38.00 -
2 DOWNLIGHT E-27 23 Watt, armatur Down Light inbouw RD150 c/w Battery LS unit 9.00 -
3 Instalasi Penerangan Empiris titik 47.00 -
4 Saklar ganda inbow 10 A LS unit 2.00 -
JUMLAH 03 SELASAR -