(4,01m+2,72m+2,91m+2,60m+1,97m+1,80m+1,45m+2,30m+2,40m+2,40m+2,40m+2,83m+2,83m+3
,65m+2,23m+1,25m+1,25m+1,40m+1,76m+1,15m+1,65m+1,15m+3,80m+1,30m+0,90m+2,54m+1,4
1m+1,40m+1,25m+1,22m+1,85m+1,80m+4,00m+2,40m+2,40m+2,40m+2,97m+1,76m+30,5m+2,89
m+2,40m+2,90m+2,47m+1,76m+2,06m+3,05m+1,85m+1,76m+0,61m+1,62m+0,12m+2,10m+2,10m
+2,70m+1,20m+2,60m+1,70m+2,40m+2,32m+1,70m+1,70m+1,06m+1,07m) x (0,14x0,35) =
132,46m x 0,049m² =
Vigas (0,14x0,45):
(4,83m+4,38m+3,25m+4,23m+4,29m+4,33m+4,37m) x (0,14x0,45) =
= 29,68m x 0,063m² =
MEMÓRIA DE CÁLCULO:
117,02m x 0,049m² =
MEMÓRIA DE CÁLCULO:
Vigas Hozizontais - 2º Pavimento:
90,44m x 0,049m² =
Vigas (0,14x0,45):
(4,05m+3,97m) x (0,14x0,45)=
8,02m x 0,063m² =
Vigas (0,14x0,50):
5,05m x 0,07m²=
MEMÓRIA DE CÁLCULO:
Vigas verticais - 2º pavimento:
Trecho cobertura - área 1 (0,14x0,20):
(2,32m+2,32m+2,91m+2,55m+2,05m) x (0,14x0,20) =
12,15m x 0,028m² =
89,14 x 0,049m² =
Vigas (0,14x0,45):
(4,23m+4,25m+4,23m+4,25m) x (0,14x0,45)=
16,96m x 0,063m²
MEMÓRIA DE CÁLCULO:
Vigas - cobertura:
Vigas - horizontais:
Vigas (0,14x0,20):
(2,11m+2,10m+2,10m+2,34m+2,10m+2,10m+2,10m+2,10m+2,25m+2,05m+2,25m+0,60m+2,05m+2
,05m+2,05m+2,24m+2,05m+2,05m+2,05m+2,45m+2,45m+2,51m+2,46m) x (0,14x0,20)=
48,61m x 0,028m³ =
Vigas verticais:
Vigas (0,14x0,20):
(1,58m+1,50m+1,45m+1,57m+1,74m+1,66m+1,42m+2,91m+2,13m+2,05m+2,05m+2,05m +2,12m) x
(0,14mx0,20) =
24,23m x 0,028m² =
Total das vigas da cobertura:
1,361m³ + 0,678m³ = 2,039m³
MEMÓRIA DE CÁLCULO:
Cinta horizontais:
Cintas - trecho 1 (0,14x0,35):
(206m+2,35m+3,05m+1,25m+2,55m) x (0,14x0,35)=
11,26m x 0,049m² =
132,46m x 0,049m²=
Cintas (0,14x0,45):
(4,83m+4,38m+3,25m+4,23m+4,29m+4,33m+4,37m) x (0,14x0,45) =
29,68m x 0,063m² =
Cintas (0,14x0,70):
6,09m x 0,098m² =
MEMÓRIA DE CÁLCULO
Cintas verticais:
cintas (0,14x0,35)
(2,33m+2,32m+3,06m+2,55m+2,33m+3,06m+2,55m+1,55m+3,06m+3,50m+1,55m+0,83m+3,82m+2
,42m+1,13m+3,06m+2,55m+3,55m+2,05m+1,44m+1,44m+1,57m+1,70m+2,27m+3,40m+3,55m+3,6
0m+3,55m+3,60m+3,60m+3,55m+3,55m+3,60m+3,55m+3,60m+3,55m+3,60m+3,51m+1,84m+1,81
m+3,49m+1,74m+1,84m+1,81m+1,77m) x (0,41x0,35) =
122,12m x 0,049m²
Cintas (0,14x0,45):
(3,70m+3,90m+3,85m+2,56m+405m+4,05m+4,05m+4,05m+4,05m) x (0,14x0,45) =
34,26m x 0,063m²
4, 5, 6 ,7, 8, 9, 10, 11, 12, 18, 20, 21, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 46 , 47, 48,
49, 50 , 51, 52, 53, 58, 59, 61, 62, 63 ,64, 65, 66, 67, 68, 69, 70, 71, 73, 74, 75, 76, 77, 78, 79, 80.
(1,00x1,00x1,50) x 55 unidades
1,500m³ x 55 unid. =
MEMÓRIA DE CÁLCULO:
Pilares da cobertura:
pilares P1, P2, P3, P4, P5, P6, P7,P8,P9,P10, P11, P12, P13, P14, P15, P16, P17, P18, P19, P20, P21, P22, P23,
P24, P25, P26, P27,P28, P29, P30, P31, P32, P33, P34, P35, P36, P37.
altura do pilar em si
h = 0,90m
pilares P1, P2, P3, P4, P5, P6, P7,P8,P9,P10, P11, P12, P13, P14, P15, P16, P17, P18, P19, P20, P, 21,
P22, P23, P24, P25, P26, P27,P28, P29, P30, P31, P32, P33, P34, P35, P36, P37 (0,14x0,26x0,90).
Concreto
(0,14x0,26x0,90) x 37 unidades
0,033m³ x 37 unid. =
MEMÓRIA DE CÁLCULO:
Pilares do trecho da cobertura - 2º pavimento:
pilares P1, P2, P3, P4, P13, P14, P15, P16, P17, P18, P21, P22, P26, P27, P38, P45, P55, P56, P57, P58,
P59, P63, P64, P77, P78.
altura do pilar em si
h = 0,90m
pilares P1, P2, P3, P4, P13, P14, P15, P16, P17, P18, P21, P22, P26, P27, P38, P45, P55, P56, P57, P58,
P59, P63, P64, P77, P78 (0,14x0,26x0,90).
Concreto
(0,14x0,26x0,90) x 25 unidades
0,033m³ x 25 unid. =
Pilares edificação:
pilares P5, P6, P7, P8, P9, P10, P11, P12, P19, P20, P25, P28, P29, P30, P31, P34, P35, P36, P37, P40,
P42, P46, P47, P48, P49, P52, P54, P60, P61, P62, P65, P66, P67, P68, P69, P70, P71, P72, P73, P74,
P75, P76, P78, P79, P80, P81, P82, P83, P84
altura do pilar em si
h = 3,00m
pilares P5, P6, P7, P8, P9, P10, P11, P12, P19, P20, P25, P28, P29, P30, P31, P34, P35, P36, P37, P40,
P42, P46, P47, P48, P49, P52, P54, P60, P61, P62, P65, P66, P67, P68, P69, P70, P71, P72, P73, P74,
P75, P76, P78, P79, P80, P81, P82, P83, P84 (0,14x0,26x3,00).
Concreto
(0,14x0,26x3,00) x 49 unidades -
0,109m³ x 49unid.=
Concreto
(0,20x0,20x3,00) x 05 unidades =
0,120m³ x 05 unidades =
MEMÓRIA DE CÁLCULO
Pilares do Muro
Pilares do muro P1, P2 (0,14x0,26)
pescoço
h= 0,50m
altura do pilar em si
h = 2,50m
altura toral do pilar
h= 3,00m
Pilares de Edificação:
pilares PA, PB, PC, PD (014x0,26)
pescoço
h = 0,50m
altura do pilar em si
h = 3,00m
altura total do pilar
h = 3,50m
pilares P14, P15, P16, P22, P23, P24, P25, P26, P44, P45, P56, P57, P58, P61.
pescoço
h = 0,50m
altura do pilar em si
h = 3,15m
altura total do pilar
h = 3,65m
pilares P14, P15, P16, P22, P23, P24, P25, P26, P44, P45, P56, P57, P58, P61 (0,14 x 0,26x3,65m).
concreto
(0,14x0,26x3,65) x 14 unidades =
0,133m³ x 14 unid.=
pilares P1, P2, P3, P4, P5, ,P7, P8, P9, P10, P11 ,P12 ,P13, P17, P18, P19, P27, P28, P29, P32, P33,
P34, P35, P36, P37, P38, P39, P40, P41, P42, P43, P46, P48, P49, P50, P51, P52, P53, P54, P55, P59,
P60, P61, P62, P63, P64, P65, P66. P67, P68, P69, P70, P71, P72, P73, P75, P76, P77, P80.
pesçoço
h = 0,50m
altura em si
h = 3,00m
altura do pilar
h = 3,50m
pilares P1, P2, P3, P5, P6, P7, P8, P9, P10, P11, P12, P13, P17, P18, P19, P27, P28, P29, P32, P33,
P34, P35, P36, P37, P38, P39, P40, P41, P42, P43, P46, P48, P49, P 50, P51, P52, P53, P54, P55, P59,
P60, P61, P62, P63, P64, P65, P66, P67, P68, P69, P70, P71, P72, P73, P75, P76, P77, P80
(0,14X0,26X3,50)
concreto
(0,14 x 0,26x3,59 x 59 unidades =
0,127m³ x 59 unidades
pilares P1, P2, P3, P4, P5, P6, P7, P8, P9, P10, P11, P12, P13, P17, P18, P19, P27, P28, P29, P32, P33,
P34, P35, P36, P37, P38, P39, P40, P41, P42, P43, P46, P48, P49, P50, P51, P52, P53, P54, P55, P59,
P60, P61, P62, P63, P64, P65, P66, P67, P68, P69, P70, P71, P72, P73, P75, P76, P77, P80.
pescoço
h = 0,50m
altura do pilar em si
h = 3,00m
altura total do pilar
h = 3,50m
pilares P1, P2, P3, P4, P5, P6, P7, P8, P9, P10, P11, P12, P13, P17, P18, P19, P27, P28, P29, P32, P33,
P34, P35, P36, P37, P38, P39, P40, P41, P42, P43, P46, P48, P49, P50, P51, P52, P53, P54, P565, P59,
P60, P61, P62, P63, P64, P65, P66, P67, P68, P69, P70, P71, P72, P73, P75, P76, P77, P80.
Concreto
(0,41 x 0,26x3,50) x 59 unidades =
0,127m³ x 59 unidades =
6,490m³
1,870m³
0,597m³
5,734m³
2,158m³
0,969m³
0,597m³
0,235m³
0,832m³
4,432m³
0,505m³
0,353m³
0,340m³
0,280m³
4,368m³
1,068m³
1,361m³
0,678m³
0,552m³
6,490m³
1,870m³
0,597m³
5,984m³
2,158m³
0,4000m³
2,352m³
14,700m³
82,500m³
1,221m³
0,825m³
5,341m³
0,600m³
1,000m³
0,218m³
0,508m³
1,862m³
7,493m³
7,493m³
2,240m³
0,670m³