ID Task Task Name Duration Start Finish Actual Start Actual Finish Predecessors % CompleteMar 19, '23 Mar

Finish Actual Start Actual Finish Predecessors % CompleteMar 19, '23 Mar 26, '23 Apr 2, '23
Mode W T F S S M T W T F S S M T W
1 Projeto CIP - ADM 67 days Fri 3/24/23 Fri 6/30/23 Fri 3/24/23 NA 13%
2 Preparação do projeto 19 days Fri 3/24/23 Thu 4/20/23 Fri 3/24/23 Thu 4/20/23 100%
3 Recebimento das informações do projeto existente 1 day Fri 3/24/23 Fri 3/24/23 Fri 3/24/23 Fri 3/24/23 100%
4 Análise da documentação recebida do cliente pela DG 7 days Mon 3/27/23 Tue 4/4/23 Mon 3/27/23 Tue 4/4/23 3 100%
5 Kick off 1 day Wed 4/5/23 Wed 4/5/23 Wed 4/5/23 Wed 4/5/23 4 100%
6 Visita de campo 5 days Mon 4/10/23 Fri 4/14/23 Mon 4/10/23 Fri 4/14/23 100%
7 Elaboração relatório de visita 4 days Mon 4/17/23 Thu 4/20/23 Mon 4/17/23 Thu 4/20/23 6 100%
8 Avaliação projeto conceitual 26 days Thu 3/30/23 Tue 5/9/23 Thu 3/30/23 NA 31%
9 Processos 22 days Thu 3/30/23 Wed 5/3/23 Thu 3/30/23 NA 32%
10 PFD - Opção 1 3 days Thu 3/30/23 Mon 4/3/23 Thu 3/30/23 Mon 4/3/23 3FS+3 days 100%
11 PFD - Opção 2 2 days Tue 4/4/23 Wed 4/5/23 Tue 4/4/23 Wed 4/5/23 10 100%
12 PFD - Opção 3 2 days Thu 4/6/23 Mon 4/10/23 Thu 4/6/23 Mon 4/10/23 11 100%
13 Critérios de Projeto 1 day Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 7 100%
14 PFDs - opções refinadas 6 days Mon 4/17/23 Tue 4/25/23 NA NA 10,11,12,6 0%
15 Balanço de massa - CIP 8 days Mon 4/17/23 Thu 4/27/23 NA NA 14SS 0%
16 Memorial de equipamentos e tubulação 3 days Fri 4/28/23 Wed 5/3/23 NA NA 15 0%
17 Utilidades 4 days Fri 4/28/23 Thu 5/4/23 NA NA 0%
18 Balanço de utilidades 3 days Fri 4/28/23 Wed 5/3/23 NA NA 7,15 0%
19 Planilha de consumo de utilidades 1 day Thu 5/4/23 Thu 5/4/23 NA NA 18 0%
20 Mecânica 9 days Thu 4/20/23 Thu 5/4/23 Thu 4/20/23 NA 25%
21 Critérios de Projeto 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 7 100%
22 Locação do empreendimento 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 21SS 100%
23 Arranjo Mecânico - Opção 1 5 days Wed 4/26/23 Wed 5/3/23 NA NA 14 0%
24 Arranjo Mecânico - Opção 2 4 days Fri 4/28/23 Thu 5/4/23 NA NA 23FS-3 days 0%
25 Arranjo Mecânico - Opção 3 3 days Tue 5/2/23 Thu 5/4/23 NA NA 24FF 0%
26 Automação 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 100%
27 Critérios de Projeto - Automação 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 7 100%
28 Critérios de Projeto - Instrumentos 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 7 100%
29 Elétrica 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 100%
30 Critérios de Projeto 2 days Thu 4/20/23 Mon 4/24/23 Thu 4/20/23 Mon 4/24/23 7 100%
31 Ambiental 1 day Thu 5/4/23 Thu 5/4/23 NA NA 0%
32 Lista de Efluentes 1 day Thu 5/4/23 Thu 5/4/23 NA NA 15,18 0%
33 Aprovação dos critérios de projeto pela ADM 3 days Tue 4/25/23 Thu 4/27/23 NA NA 30,28,27,21,13 0%
34 Apresentação comparativa entre as 3 opções 1 day Fri 5/5/23 Fri 5/5/23 NA NA 9,20 0%
35 Escolha da opção a ser seguida - ADM 2 days Mon 5/8/23 Tue 5/9/23 NA NA 34 0%
36 Projeto Básico 37 days Wed 5/10/23 Fri 6/30/23 NA NA 33 0%
37 Processos 34 days Wed 5/10/23 Tue 6/27/23 NA NA 0%
38 Lista de Equipamentos 2 days Wed 5/10/23 Thu 5/11/23 NA NA 35 0%
39 P&ID - opção escolhida 5 days Fri 5/12/23 Thu 5/18/23 NA NA 38 0%
40 P&IDs - interligações do processo 19 days Fri 5/19/23 Thu 6/15/23 NA NA 39 0%
41 Lista de Linhas 1 day Fri 6/16/23 Fri 6/16/23 NA NA 40 0%

Task Project Summary Manual Task Start-only Deadline

Project: 7363- Cronograma_23. Split Inactive Task Duration-only Finish-only Progress


Date: Mon 4/24/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Actual Start Actual Finish Predecessors % CompleteMar 19, '23 Mar 26, '23 Apr 2, '23
Mode W T F S S M T W T F S S M T W
42 Lista de Fluidos 1 day Mon 6/19/23 Mon 6/19/23 NA NA 41 0%
43 Produtos Quimicos e Perigosos 1 day Mon 6/19/23 Mon 6/19/23 NA NA 42SS 0%
44 Folha de dados - equipamentos 17 days Fri 5/19/23 Tue 6/13/23 NA NA 39 0%
45 Parâmetros operacionais e de Produção 6 days Fri 6/16/23 Fri 6/23/23 NA NA 40,44 0%
46 Área Classificada 2 days Tue 6/20/23 Wed 6/21/23 NA NA 53,43 0%
47 Plano de Comissionamento 2 days Mon 6/26/23 Tue 6/27/23 NA NA 45 0%
48 Utilidades 27 days Fri 5/19/23 Tue 6/27/23 NA NA 0%
49 Revisão lista Utilidades 5 days Fri 5/19/23 Thu 5/25/23 NA NA 39 0%
50 Relatório de Tie ins 3 days Fri 6/16/23 Tue 6/20/23 NA NA 40 0%
51 P&IDs utilidades 5 days Wed 6/21/23 Tue 6/27/23 NA NA 50 0%
52 Mecânica 30 days Fri 5/19/23 Fri 6/30/23 NA NA 0%
53 Planta Arranjo mecânico - final 5 days Fri 5/19/23 Thu 5/25/23 NA NA 39 0%
54 Planta Chave 5 days Tue 6/13/23 Mon 6/19/23 NA NA 40FS-3 days 0%
55 Lista de Materiais preliminar 3 days Fri 6/16/23 Tue 6/20/23 NA NA 53,54FF+1 day 0%
56 Lista de Suporte preliminar 2 days Tue 6/20/23 Wed 6/21/23 NA NA 54 0%
57 3D preliminar 9 days Tue 6/20/23 Fri 6/30/23 NA NA 54 0%
58 Automação 33 days Wed 5/10/23 Mon 6/26/23 NA NA 0%
59 Arquitetura de rede 2 days Wed 5/10/23 Thu 5/11/23 NA NA 35 0%
60 Lista de equipamentos de Automação 2 days Wed 5/24/23 Thu 5/25/23 NA NA 61 0%
61 Lista de Instrumentos 3 days Fri 5/19/23 Tue 5/23/23 NA NA 39 0%
62 Folha de Dados Instrumentos 3 days Wed 5/24/23 Fri 5/26/23 NA NA 61 0%
63 Lista de Materiais preliminar 2 days Fri 6/23/23 Mon 6/26/23 NA NA 68 0%
64 Lista I/O 3 days Wed 5/24/23 Fri 5/26/23 NA NA 61 0%
65 Lista de cabos 2 days Thu 6/22/23 Fri 6/23/23 NA NA 67 0%
66 Planta (instrumentos) 1 day Tue 6/20/23 Tue 6/20/23 NA NA 54 0%
67 Planta (rotas) 1 day Wed 6/21/23 Wed 6/21/23 NA NA 54,66 0%
68 Planta (Painéis) 1 day Thu 6/22/23 Thu 6/22/23 NA NA 54,67 0%
69 Memorial Descritivo de Automação e Instrumentação 4 days Mon 5/29/23 Thu 6/1/23 NA NA 64 0%
70 Lista de Hardwares & Softwares 2 days Fri 6/2/23 Mon 6/5/23 NA NA 69 0%
71 Narrativas de Controle 3 days Tue 6/6/23 Fri 6/9/23 NA NA 69,70 0%
72 Check list SAT 1 day Mon 6/12/23 Mon 6/12/23 NA NA 71 0%
73 Elétrica 28 days Wed 5/17/23 Mon 6/26/23 NA NA 0%
74 Lista de motores e consumidores 1 day Wed 5/17/23 Wed 5/17/23 NA NA 38FS+3 days 0%
75 Diagrama Unifilar 3 days Thu 5/18/23 Mon 5/22/23 NA NA 74 0%
76 Rota básica de distribuição de força 5 days Wed 5/31/23 Tue 6/6/23 NA NA 53FS+3 days 0%
77 Memorial de cálculo cabos elétricos 2 days Wed 6/7/23 Fri 6/9/23 NA NA 75,76 0%
78 Memorial de cálculo luminotecnico preliminar 2 days Mon 6/12/23 Tue 6/13/23 NA NA 76,77 0%
79 Planta de locação de luminárias 3 days Wed 6/14/23 Fri 6/16/23 NA NA 78 0%
80 Folha de dados equipamentos elétricos 3 days Mon 6/19/23 Wed 6/21/23 NA NA 79 0%
81 Lista de Equipamentos elétricos 1 day Thu 6/22/23 Thu 6/22/23 NA NA 80 0%
82 Lista de Materiais preliminar 2 days Fri 6/23/23 Mon 6/26/23 NA NA 81 0%

Task Project Summary Manual Task Start-only Deadline

Project: 7363- Cronograma_23. Split Inactive Task Duration-only Finish-only Progress


Date: Mon 4/24/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Actual Start Actual Finish Predecessors % CompleteMar 19, '23 Mar 26, '23 Apr 2, '23
Mode W T F S S M T W T F S S M T W
83 Planta de aterramento 2 days Wed 6/7/23 Fri 6/9/23 NA NA 76 0%
84 Estudo de cargas elétricas 3 days Mon 6/12/23 Wed 6/14/23 NA NA 83 0%
85 Arranjos Elétricos de Força e Comando 4 days Thu 6/15/23 Tue 6/20/23 NA NA 84 0%
86 Estruturas 17 days Fri 6/2/23 Tue 6/27/23 NA NA 0%
87 Plano de Bases 2 days Wed 6/21/23 Thu 6/22/23 NA NA 90 0%
88 Plano de Cargas 2 days Fri 6/23/23 Mon 6/26/23 NA NA 87 0%
89 Planta e cortes da plataforma 5 days Tue 6/6/23 Tue 6/13/23 NA NA 94 0%
90 Planta de cortes e coberturas metálicas 5 days Wed 6/14/23 Tue 6/20/23 NA NA 89 0%
91 Lista de materiais preliminar 3 days Wed 6/21/23 Fri 6/23/23 NA NA 90 0%
92 Plano QAQC 1 day Mon 6/26/23 Mon 6/26/23 NA NA 91 0%
93 Layout geral do site (area CIP) 1 day Tue 6/27/23 Tue 6/27/23 NA NA 88 0%
94 Dimensionamento estruturas de concreto 2 days Fri 6/2/23 Mon 6/5/23 NA NA 53FS+5 days 0%
95 Ambiental 4 days Fri 5/19/23 Wed 5/24/23 NA NA 0%
96 P&ID - interligação rede efluentes 3 days Fri 5/19/23 Tue 5/23/23 NA NA 39 0%
97 Relatório de Tie ins 1 day Wed 5/24/23 Wed 5/24/23 NA NA 96 0%
98 Geral 25 days Fri 5/26/23 Fri 6/30/23 NA NA 0%
99 Estimativa de Custo 3 days Wed 6/28/23 Fri 6/30/23 NA NA 37,48,58,73,86,95,53
0%
100 Relatório de Engenharia Básica 4 days Tue 6/27/23 Fri 6/30/23 NA NA 99FF 0%
101 Estudo de Acesso ao site 2 days Fri 5/26/23 Mon 5/29/23 NA NA 53 0%
102 WBS 1 day Fri 6/30/23 Fri 6/30/23 NA NA 100FF 0%
103 Apresentação de encerramento 4 days Tue 6/27/23 Fri 6/30/23 NA NA 100SS 0%
104 Cronograma de marcos 4 days Tue 6/27/23 Fri 6/30/23 NA NA 100SS 0%

Task Project Summary Manual Task Start-only Deadline

Project: 7363- Cronograma_23. Split Inactive Task Duration-only Finish-only Progress


Date: Mon 4/24/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
Apr 2, '23 Apr 9, '23 Apr 16, '23 Apr 23, '23 Apr 30, '23 May 7, '23 May 14, '23 May 21, '23 May 28, '23 Jun 4, '23 Jun 11, '23 Jun 18, '23 Jun 25, '23 Jul 2, '23
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Project Summary Manual Task Start-only Deadline

Project: 7363- Cronograma_23. Split Inactive Task Duration-only Finish-only Progress


Date: Mon 4/24/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
Apr 2, '23 Apr 9, '23 Apr 16, '23 Apr 23, '23 Apr 30, '23 May 7, '23 May 14, '23 May 21, '23 May 28, '23 Jun 4, '23 Jun 11, '23 Jun 18, '23 Jun 25, '23 Jul 2, '23
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Project Summary Manual Task Start-only Deadline

Project: 7363- Cronograma_23. Split Inactive Task Duration-only Finish-only Progress


Date: Mon 4/24/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5
Apr 2, '23 Apr 9, '23 Apr 16, '23 Apr 23, '23 Apr 30, '23 May 7, '23 May 14, '23 May 21, '23 May 28, '23 Jun 4, '23 Jun 11, '23 Jun 18, '23 Jun 25, '23 Jul 2, '23
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Project Summary Manual Task Start-only Deadline

Project: 7363- Cronograma_23. Split Inactive Task Duration-only Finish-only Progress


Date: Mon 4/24/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone