Duration (weeks)
Optimistic Most Pessimistic
Activity Likely Expected Duration
Id. Dependencies
A01 2 3 5 3.2
A02 2 4 7 4.2
A03 2 5 8 5
A04 A01 3 5 9 5.4
A05 A01 4 6 8 6
A06 A02 1 3 6 3.2
A07 A03 1 3 7 3.4
A08 A04 1 2 4 2.2
A09 A06 1 2 4 2.2
A10 A06 2 3 5 3.2
A11 A07 1 2 3 2
A12 A05, A08 1 2 4 2.2
A13 A10, A11 3 4 6 4.2
A14 A09, A12 6 8 12 8.4
A15 A09, A12 1 2 3 2
A16 A13, A15 1 3 6 3.2