CRONOGRAMA DE IMPLANTAÇÃO

Gerência de Implantação de Projetos Correntes Corredor Sudeste


Adequação de caminho de acesso ao pátio de minério TIG (Controle de acesso)
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023 2024
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
Finish Date
2.42% TIG
Adequação de caminho de acesso ao pátio de minério 1440.00 11-Nov-19 de
(Controle 20-Oct-23
acesso) 1.14% 1440.00 11-Nov-19 A 20-Oct-23 0.00

Engenharia 84.5% 1127.00 11-Nov-19 11-Dec-22 45% 1166.00 11-Nov-19 A 19-Jan-23 -39.00

Inicial 100% 642.00 11-Nov-19 13-Aug-21 100% 642.00 11-Nov-19 A 13-Aug-21 A 0.00

E1000 TAP 100% 14.00 11-Nov-19 25-Nov-19 100% 14.00 11-Nov-19 A 25-Nov-19 A 0.00

E1010 Aprovação da declaração de escopo 100% 35.00 26-Oct-20 30-Nov-20 100% 35.00 26-Oct-20 A 30-Nov-20 A 0.00

E1020 Emissão de solicitação de Autorização de 100% 1.00 15-May-21 15-May-21 100% 1.00 15-May-21 A 15-May-21 A 0.00
Desenvolvimento de Projeto
E1030 Elaboração / Aprovação do Plano de Trabalho 100% 90.00 16-May-21 13-Aug-21 100% 90.00 16-May-21 A 13-Aug-21 A 0.00

E1040 Elaboração / Aprovação da ADP 100% 11.00 31-May-21 11-Jun-21 100% 11.00 31-May-21 A 11-Jun-21 A 0.00

Detalhado 99.35% 174.00 11-Jun-21 01-Dec-21 48.39% 213.00 11-Jun-21 A 09-Jan-22 -39.00

ED1010 Projeto detalhado Civil (arquitetura, infraestrutura, 100% 150.00 11-Jun-21 07-Nov-21 60% 183.00 11-Jun-21 A 10-Dec-21 -33.00
metálica)
ED1020 Projeto detalhado Elérica (automação, 100% 150.00 11-Jun-21 07-Nov-21 60% 183.00 11-Jun-21 A 10-Dec-21 -33.00
instrumentação, telecom)
EP1000 PQ e documentação para contratação 100% 20.00 08-Nov-21 27-Nov-21 0% 20.00 11-Dec-21 30-Dec-21 -33.00

ER1000 Construtibilidade 100% 7.00 15-Nov-21 21-Nov-21 0% 7.00 18-Dec-21 24-Dec-21 -33.00

ER1010 CAPEX 90% 10.00 22-Nov-21 01-Dec-21 0% 10.00 31-Dec-21 09-Jan-22 -39.00

Requisição de Compra 0% 25.00 17-Nov-22 11-Dec-22 0% 25.00 26-Dec-22 19-Jan-23 -39.00

C0010 Preparação do processo de contratação 0% 15.00 17-Nov-22 01-Dec-22 0% 15.00 26-Dec-22 09-Jan-23 -39.00

C0020 Emissão / Aprovação RT Físic a 0% 5.00 02-Dec-22 06-Dec-22 0% 5.00 10-Jan-23 14-Jan-23 -39.00

C1000 Emissão / Aprovação RC no S AP 0% 5.00 07-Dec-22 11-Dec-22 0% 5.00 15-Jan-23 19-Jan-23 -39.00

Comitê Orçamentário 24% 380.00 04-Dec-20 18-Dec-21 24% 419.00 04-Dec-20 A 26-Jan-22 -39.00

Engenharia 100% 158.00 04-Dec-20 11-May-21 100% 158.00 04-Dec-20 A 11-May-21 A 0.00

CO0010 Cadastro / liberação do projeto na Ferramenta de 100% 7.00 04-Dec-20 11-Dec-20 100% 7.00 04-Dec-20 A 11-Dec-20 A 0.00
captura / Criação do PEP
CO0020 Submissão da documentação no Sharepoint 100% 1.00 02-Mar-21 02-Mar-21 100% 1.00 02-Mar-21 A 02-Mar-21 A 0.00

CO0030 Aprovação da documentação no Sharepoint 100% 10.00 03-Mar-21 13-Mar-21 100% 10.00 03-Mar-21 A 13-Mar-21 A 0.00

CO0040 Aprovação do projeto pelo controladoria (email de 100% 59.00 13-Mar-21 11-May-21 100% 59.00 13-Mar-21 A 11-May-21 A 0.00
acordo da Gestão Econômica)

Obra 0% 17.00 02-Dec-21 18-Dec-21 0% 17.00 10-Jan-22 26-Jan-22 -39.00

CO1010 Submissão da documentação no Sharepoint 0% 5.00 02-Dec-21 06-Dec-21 0% 5.00 10-Jan-22 14-Jan-22 -39.00

CO2000 Aprovação da documentação no Sharepoint / 0% 9.00 07-Dec-21 15-Dec-21 0% 9.00 15-Jan-22 23-Jan-22 -39.00
liberação orçamentária
CO2010 Liberação orçamentária / Apro vação no SAP 0% 3.00 16-Dec-21 18-Dec-21 0% 3.00 24-Jan-22 26-Jan-22 -39.00
(controladoria)

Licenciamento 48.63% 70.00 07-Nov-21 15-Jan-22 0% 70.00 10-Dec-21 17-Feb-22 -33.00

Licenciamento ambiental 48.63% 70.00 07-Nov-21 15-Jan-22 0% 70.00 10-Dec-21 17-Feb-22 -33.00

L0010 Elaboração e emissão da RIPLA 100% 10.00 07-Nov-21 16-Nov-21 0% 10.00 10-Dec-21 19-Dec-21 -33.00

L0020 Avaliação e retorno da RIPLA 23.33% 60.00 17-Nov-21 15-Jan-22 0% 60.00 20-Dec-21 17-Feb-22 -33.00

L1000 Atividade de licenciamento conforme necessidade 23.33% 60.00 17-Nov-21 15-Jan-22 0% 60.00 20-Dec-21 17-Feb-22 -33.00
do projeto conforme retorno da RIPLA (T EXTO
EDITÁVEL)
Contratação Obras e Serviços 0% 64.00 14-Dec-22 15-Feb-23 0% 64.00 22-Jan-23 26-Mar-23 -39.00

Obra 0% 64.00 14-Dec-22 15-Feb-23 0% 64.00 22-Jan-23 26-Mar-23 -39.00

Contratação 0% 64.00 14-Dec-22 15-Feb-23 0% 64.00 22-Jan-23 26-Mar-23 -39.00

C1010 Visita técnica 0% 7.00 14-Dec-22 20-Dec-22 0% 7.00 22-Jan-23 28-Jan-23 -39.00

C1020 Esclarecimento técnico / Recebimento de propostas 0% 15.00 21-Dec-22 04-Jan-23 0% 15.00 29-Jan-23 12-Feb-23 -39.00

C1030 Análise técnica de propostas e aprovação 0% 15.00 05-Jan-23 19-Jan-23 0% 15.00 13-Feb-23 27-Feb-23 -39.00

C1040 Análise comercial / Negociação 0% 20.00 20-Jan-23 08-Feb-23 0% 20.00 28-Feb-23 19-Mar-23 -39.00

CT1000 Assinatura do contrato 0% 7.00 09-Feb-23 15-Feb-23 0% 7.00 20-Mar-23 26-Mar-23 -39.00

Obras 0% 241.00 21-Feb-23 20-Oct-23 0% 202.00 01-Apr-23 20-Oct-23 0.00

Obra 0% 241.00 21-Feb-23 20-Oct-23 0% 202.00 01-Apr-23 20-Oct-23 0.00

Mobilização 0% 45.00 21-Feb-23 07-Apr-23 0% 45.00 01-Apr-23 16-May-23 -39.00

O1000 Emissão da OS 0% 0.00 21-Feb-23 0% 0.00 01-Apr-23 -39.00

O1100 Mobilização de recursos 0% 30.00 22-Feb-23 23-Mar-23 0% 30.00 02-Apr-23 01-May-23 -39.00

Primary Baseline Remaining Work Milestone Page 1 of 2 Data Atualização: 01-Dec-21

Actual Work Critical Remaining Work Summary © Primavera Systems, Inc.


CRONOGRAMA DE IMPLANTAÇÃO
Gerência de Implantação de Projetos Correntes Corredor Sudeste
Adequação de caminho de acesso ao pátio de minério TIG (Controle de acesso)
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023 2024
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
Finish Date
O1110 Montagem / Aprovaç ão do canteiro final de obras 0% 45.00 22-Feb-23 07-Apr-23 0% 45.00 02-Apr-23 16-May-23 -39.00
conforme EPS-519
O1200 Apresentação / Apro vação da estratégia de 0% 7.00 22-Feb-23 28-Feb-23 0% 7.00 02-Apr-23 08-Apr-23 -39.00
mobilização
O1210 Elaboração / Aprovação do Plano de Trabalho da 0% 45.00 22-Feb-23 07-Apr-23 0% 45.00 02-Apr-23 16-May-23 -39.00
Obra (PTO)
Construção 0% 171.00 08-Apr-23 25-Sep-23 0% 132.00 17-May-23 25-Sep-23 0.00

O2000 Atividades da OBRA 0% 166.00 08-Apr-23 20-Sep-23 0% 127.00 17-May-23 20-Sep-23 0.00

TO1000 Conclusão de todo o escopo 0% 5.00 21-Sep-23 25-Sep-23 0% 5.00 21-Sep-23 25-Sep-23 0.00

Desmobilização 0% 30.00 21-Sep-23 20-Oct-23 0% 30.00 21-Sep-23 20-Oct-23 0.00

O3000 Desmobilização do Canteiro de Obras e de Todos 0% 15.00 21-Sep-23 05-Oct-23 0% 15.00 21-Sep-23 05-Oct-23 0.00
os Recurso
O3010 Desmobilização final (entrega documentação de 0% 30.00 21-Sep-23 20-Oct-23 0% 30.00 21-Sep-23 20-Oct-23 0.00
encerramento do contrato, relatório final da obra e
as-built).

Primary Baseline Remaining Work Milestone Page 2 of 2 Data Atualização: 01-Dec-21