CRONOGRAMA DE IMPLANTAÇÃO

Gerência de Implantação de Projetos Correntes Corredor Sudeste


Pavimentação nas Áreas CEAM / CPBS - RJ
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Finish Date
Pavimentação nas Áreas CEAM / CPBS - RJ 2% 1646.00 21-Aug-18 22-Feb-23 2% 1646.00 21-Aug-18 A 22-Feb-23 0.00

Engenharia 100% 764.00 21-Aug-18 22-Sep-20 100% 896.00 21-Aug-18 A 02-Feb-21 A 0.00

Inicial 100% 524.00 21-Aug-18 26-Jan-20 100% 524.00 21-Aug-18 A 26-Jan-20 A 0.00

E1000 TAP 100% 1.00 21-Aug-18 21-Aug-18 100% 1.00 21-Aug-18 A 21-Aug-18 A 0.00

E1020 Emissão de Solicitação Engenharia - SE 100% 1.00 01-Jan-20 01-Jan-20 100% 1.00 01-Jan-20 A 01-Jan-20 A 0.00

E1040 Liberação orçamentária para desenvolvimento da engenharia 100% 5.00 02-Jan-20 06-Jan-20 100% 5.00 02-Jan-20 A 06-Jan-20 A 0.00

E1050 Elaboração / Aprovação da ADP 100% 10.00 07-Jan-20 16-Jan-20 100% 10.00 07-Jan-20 A 16-Jan-20 A 0.00

E2000 Topografia 100% 10.00 17-Jan-20 26-Jan-20 100% 10.00 17-Jan-20 A 26-Jan-20 A 0.00

Detalhada 100% 240.00 27-Jan-20 22-Sep-20 100% 372.00 27-Jan-20 A 02-Feb-21 A 0.00

ED0900 Análise Critica 100% 5.00 27-Jan-20 31-Jan-20 100% 5.00 27-Jan-20 A 31-Jan-20 A 0.00

ED1000 Projeto detalhado (Revisão) 100% 30.00 03-Feb-20 03-Mar-20 100% 365.00 03-Feb-20 A 02-Feb-21 A 0.00

EP1000 PQ e check de maturidade para contratação - Guarda Chuva 100% 10.00 04-Mar-20 13-Mar-20 100% 35.00 04-Mar-20 A 07-Apr-20 A 0.00

ER1000 Construtibilidade - Guarda Chuva 100% 1.00 22-Sep-20 22-Sep-20 100% 1.00 22-Sep-20 A 22-Sep-20 A 0.00

ER1010 CAPEX - Guarda Chuva 100% 7.00 01-Jun-20 07-Jun-20 100% 7.00 01-Jun-20 A 07-Jun-20 A 0.00

Contratação Obras e Serviços 0% 54.00 01-Aug-22 23-Sep-22 0% 54.00 01-Aug-22 23-Sep-22 0.00

Obra 0% 54.00 01-Aug-22 23-Sep-22 0% 54.00 01-Aug-22 23-Sep-22 0.00

Requisição de Compra - Guarda Chuva 0% 7.00 01-Aug-22 07-Aug-22 0% 7.00 01-Aug-22 07-Aug-22 0.00

C0010 Solicitação Plano de Trabalho Contratada 0% 7.00 01-Aug-22 07-Aug-22 0% 7.00 01-Aug-22* 07-Aug-22 0.00

Contratação - Guarda Chuva 0% 47.00 08-Aug-22 23-Sep-22 0% 47.00 08-Aug-22 23-Sep-22 0.00

C1010 Visita técnica 0% 2.00 08-Aug-22 09-Aug-22 0% 2.00 08-Aug-22 09-Aug-22 0.00

C1020 Recebimento de propostas 0% 17.00 10-Aug-22 26-Aug-22 0% 17.00 10-Aug-22 26-Aug-22 0.00

C1030 Análise técnica de propostas e aprovação 0% 15.00 27-Aug-22 10-Sep-22 0% 15.00 27-Aug-22 10-Sep-22 0.00

CT1000 Assinatura da AS 0% 13.00 11-Sep-22 23-Sep-22 0% 13.00 11-Sep-22 23-Sep-22 0.00

Obras 0% 151.00 24-Sep-22 22-Feb-23 0% 151.00 24-Sep-22 22-Feb-23 0.00

Obra - Guarda Chuva 0% 151.00 24-Sep-22 22-Feb-23 0% 151.00 24-Sep-22 22-Feb-23 0.00

Mobilização 0% 30.00 24-Sep-22 24-Oct-22 0% 30.00 24-Sep-22 24-Oct-22 0.00

O1010 Mobilização de Recursos 0% 30.00 24-Sep-22 23-Oct-22 0% 30.00 24-Sep-22 23-Oct-22 0.00

O1020 Montagem / Aprovaç ão do canteiro final de obras c onforme E PS-519 0% 0.00 24-Oct-22 24-Oct-22 0% 0.00 24-Oct-22 24-Oct-22 0.00

Planejamento 0% 11.00 24-Sep-22 04-Oct-22 0% 11.00 24-Sep-22 04-Oct-22 0.00

O1040 Elaboração / Aprovação do Plano de Trabalho da Obra (PTO) 0% 11.00 24-Sep-22 04-Oct-22 0% 11.00 24-Sep-22 04-Oct-22 0.00

Construção 0% 121.00 24-Oct-22 22-Feb-23 0% 121.00 24-Oct-22 22-Feb-23 0.00

O1100 Execução de camadas 0% 20.00 24-Oct-22 12-Nov-22 0% 20.00 24-Oct-22 12-Nov-22 0.00

O1110 Execução das Bocas de lobo 0% 14.00 13-Nov-22 26-Nov-22 0% 14.00 13-Nov-22 26-Nov-22 0.00

O1120 Revestimento asfáltico 0% 39.00 13-Nov-22 21-Dec-22 0% 39.00 13-Nov-22 21-Dec-22 0.00

O1130 Assentamento de meio fio 0% 91.00 23-Nov-22 21-Feb-23 0% 91.00 23-Nov-22 21-Feb-23 0.00

O1140 Execução das sarjetas 0% 71.00 23-Nov-22 01-Feb-23 0% 71.00 23-Nov-22 01-Feb-23 0.00

O1150 Execução da calçada 0% 53.00 23-Nov-22 14-Jan-23 0% 53.00 23-Nov-22 14-Jan-23 0.00

TO1000 Conclusao de todo o escopo incluindo segregação dos materiais 0% 0.00 22-Feb-23 22-Feb-23 0% 0.00 22-Feb-23 22-Feb-23 0.00

Desmobilização 0% 30.00 23-Jan-23 22-Feb-23 0% 30.00 23-Jan-23 22-Feb-23 0.00

O2000 Desmobilização do canteiro de obras e de todos os recursos 0% 0.00 22-Feb-23 22-Feb-23 0% 0.00 22-Feb-23 22-Feb-23 0.00

O2010 Demobilização final(entrega documentação de encerramento do contrato, 0% 30.00 23-Jan-23 22-Feb-23 0% 30.00 23-Jan-23 22-Feb-23 0.00
relatório final de obras e As built).

Primary Baseline Remaining Work Milestone Page 1 of 1 Data Atualização: 01-Dec-21

Actual Work Critical Remaining Work Summary © Primavera Systems, Inc.