CRONOGRAMA DE IMPLANTAÇÃO

Gerência de Implantação de Projetos Correntes Corredor Sudeste


Reforço da Ponte de Acesso ao Píer - CPBS
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Finish Date
Reforço da Ponte de Acesso ao Píer - CPBS 2.7% 1282.00 12-Dec-19 15-Jun-23 2.04% 1282.00 12-Dec-19 A 15-Jun-23 0.00

Engenharia 85% 955.00 12-Dec-19 23-Jul-22 85% 955.00 12-Dec-19 A 23-Jul-22 0.00

Inicial 100% 1.00 12-Dec-19 12-Dec-19 100% 1.00 12-Dec-19 A 12-Dec-19 A 0.00

E1000 Abertura do TAP 100% 1.00 12-Dec-19 12-Dec-19 100% 1.00 12-Dec-19 A 12-Dec-19 A 0.00

Detalhado 100% 90.00 13-Dec-19 11-Mar-20 100% 134.00 13-Dec-19 A 25-Apr-20 A 0.00

ED1000 Análise Crítica do projeto desenvolvimento pela Engenharia Portuária 100% 7.00 13-Dec-19 19-Dec-19 100% 71.00 13-Dec-19 A 21-Feb-20 A 0.00

EP1000 PQ e check de maturidade para contratação 100% 8.00 21-Feb-20 28-Feb-20 100% 64.00 21-Feb-20 A 24-Apr-20 A 0.00

ER1000 Construtibilidade 100% 1.00 21-Feb-20 21-Feb-20 100% 0.00 21-Feb-20 A 21-Feb-20 A 0.00

ER1010 CAPEX 100% 1.00 11-Mar-20 11-Mar-20 100% 64.00 21-Feb-20 A 25-Apr-20 A 0.00

Requisição de Compra 0% 20.00 04-Jul-22 23-Jul-22 0% 20.00 04-Jul-22 23-Jul-22 0.00

C0010 Preparação do processo de contratação 0% 7.00 04-Jul-22 10-Jul-22 0% 7.00 04-Jul-22* 10-Jul-22 0.00

C0020 Emissão / Aprovação RT Físic a 0% 3.00 11-Jul-22 13-Jul-22 0% 3.00 11-Jul-22 13-Jul-22 0.00

C1000 Emissão / Aprovação RC no S AP 0% 10.00 14-Jul-22 23-Jul-22 0% 10.00 14-Jul-22 23-Jul-22 0.00

Licenciamento 100% 526.00 31-Jul-20 07-Jan-22 34% 526.00 31-Jul-20 A 07-Jan-22 -91.00

L0010 Elaboração e emissão da RIPLA 100% 7.00 31-Mar-21 06-Apr-21 0% 232.00 13-Apr-21 A 01-Dec-21 -91.00

L0020 Avaliação e retorno da RIPLA 100% 38.00 01-Dec-21 07-Jan-22 0% 38.00 01-Dec-21 07-Jan-22 -91.00

L1000 Liberação regulatório 100% 60.00 31-Jul-20 28-Sep-20 100% 242.00 31-Jul-20 A 30-Mar-21 A 0.00

Contratação Obras e Serviços 0% 72.00 24-Jul-22 03-Oct-22 0% 72.00 24-Jul-22 03-Oct-22 0.00

Obra Civil 0% 72.00 24-Jul-22 03-Oct-22 0% 72.00 24-Jul-22 03-Oct-22 0.00

Contratação 0% 72.00 24-Jul-22 03-Oct-22 0% 72.00 24-Jul-22 03-Oct-22 0.00

A1000 Visita técnica 0% 0.00 24-Jul-22 24-Jul-22 0% 0.00 24-Jul-22 24-Jul-22 0.00

A1010 Recebimento de propostas 0% 20.00 24-Jul-22 12-Aug-22 0% 20.00 24-Jul-22 12-Aug-22 0.00

A1020 Análise técnica de propostas e aprovação 0% 20.00 13-Aug-22 01-Sep-22 0% 20.00 13-Aug-22 01-Sep-22 0.00

A1030 Análise comercial / Negociação 0% 22.00 02-Sep-22 23-Sep-22 0% 22.00 02-Sep-22 23-Sep-22 0.00

A1040 Emissão e Aprovação do Relatório de H omolo gação - RH 0% 3.00 24-Sep-22 26-Sep-22 0% 3.00 24-Sep-22 26-Sep-22 0.00

CT1000 Assinatura do contrato 0% 7.00 27-Sep-22 03-Oct-22 0% 7.00 27-Sep-22 03-Oct-22 0.00

Obras 0% 255.00 04-Oct-22 15-Jun-23 0% 255.00 04-Oct-22 15-Jun-23 0.00

Obra Civil 0% 255.00 04-Oct-22 15-Jun-23 0% 255.00 04-Oct-22 15-Jun-23 0.00

Ordem de Serviço 0% 5.00 04-Oct-22 08-Oct-22 0% 5.00 04-Oct-22 08-Oct-22 0.00

O1000 Emissão da OS 0% 5.00 04-Oct-22 08-Oct-22 0% 5.00 04-Oct-22 08-Oct-22 0.00

Mobilização 0% 60.00 09-Oct-22 07-Dec-22 0% 60.00 09-Oct-22 07-Dec-22 0.00

O1100 Montagem / Aprovaç ão do canteiro final de obras c onforme E PS-519 0% 60.00 09-Oct-22 07-Dec-22 0% 60.00 09-Oct-22 07-Dec-22 0.00

O1110 Mobilização de recursos 0% 45.00 09-Oct-22 22-Nov-22 0% 45.00 09-Oct-22 22-Nov-22 0.00

Planejamento 0% 45.00 09-Oct-22 22-Nov-22 0% 45.00 09-Oct-22 22-Nov-22 0.00

O2000 Apresentação / Apro vação da estratégia de mobiliz ação 0% 7.00 09-Oct-22 15-Oct-22 0% 7.00 09-Oct-22 15-Oct-22 0.00

O2010 Elaboração / Aprovação do Plano de Trabalho da Obra (PTO) 0% 45.00 09-Oct-22 22-Nov-22 0% 45.00 09-Oct-22 22-Nov-22 0.00

Construção 0% 230.00 09-Oct-22 26-May-23 0% 230.00 09-Oct-22 26-May-23 0.00

O3000 Fornecimento de andaime 0% 60.00 09-Oct-22 07-Dec-22 0% 60.00 09-Oct-22 07-Dec-22 0.00

O3010 Reforço das vigas VPM 09 0% 80.00 08-Dec-22 25-Feb-23 0% 80.00 08-Dec-22 25-Feb-23 0.00

O3020 Substituição dos aparelhos de apoio. 0% 70.00 26-Feb-23 06-May-23 0% 70.00 26-Feb-23 06-May-23 0.00

TO1000 Conclusão de 100% das obras,(incluindo acabamento na ponte, 0% 20.00 07-May-23 26-May-23 0% 20.00 07-May-23 26-May-23 0.00
segregaçãpo e destinação de residuos)

Primary Baseline Remaining Work Milestone Page 1 of 2 Data Atualização: 01-Dec-21

Actual Work Critical Remaining Work Summary © Primavera Systems, Inc.


CRONOGRAMA DE IMPLANTAÇÃO
Gerência de Implantação de Projetos Correntes Corredor Sudeste
Reforço da Ponte de Acesso ao Píer - CPBS
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Finish Date
Desmobilização 0% 20.00 27-May-23 15-Jun-23 0% 20.00 27-May-23 15-Jun-23 0.00

O4000 Desmobilização do Canteiro de Obras e de Todos os Recurso 0% 10.00 27-May-23 05-Jun-23 0% 10.00 27-May-23 05-Jun-23 0.00

O4010 Desmobilização final (entrega documentação de encerramento do contrato, 0% 10.00 06-Jun-23 15-Jun-23 0% 10.00 06-Jun-23 15-Jun-23 0.00
relatório final da obra e as-built).

Primary Baseline Remaining Work Milestone Page 2 of 2 Data Atualização: 01-Dec-21