Cronograma Físico e Financeiro

Item Descrição Total Por Etapa 30 DIAS 60 DIAS 90 DIAS 120 DIAS 150 DIAS 180 DIAS
1 INTRODUÇÃO E ACOMPANHAMENTO TÉCNICO 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
249.061,76 49.812,35 39.849,88 39.849,88 39.849,88 39.849,88 39.849,88
2 MOVIMENTO DE TERRA. 100,00% 50,00% 25,00% 15,00% 10,00%
130.588,70 65.294,35 32.647,18 19.588,31 13.058,87
3 ESTRUTURAS EM CONCRETO ARMADO 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
579.915,50 115.983,10 92.786,48 92.786,48 92.786,48 92.786,48 92.786,48
4 PAREDES/ PAINEIS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
133.086,46 26.617,29 21.293,83 21.293,83 21.293,83 21.293,83 21.293,83
5 COBERTURA 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
145.343,97 29.068,79 23.255,04 23.255,04 23.255,04 23.255,04 23.255,04
6 REVESTIMENTO E TRATAMENTO DE SUPERFÍCIES 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
496.998,40 99.399,68 79.519,74 79.519,74 79.519,74 79.519,74 79.519,74
7 ESQUADRIAS/FERRAGENS/VIDROS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
150.832,72 30.166,54 24.133,24 24.133,24 24.133,24 24.133,24 24.133,24
8 PISOS/ SOLEIRA/ PINGADEIRA/ RODAPÉ 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
108.880,16 21.776,03 17.420,83 17.420,83 17.420,83 17.420,83 17.420,83
9 INSTALAÇÕES HIDRO SANITÁRIAS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
140.563,34 28.112,67 22.490,13 22.490,13 22.490,13 22.490,13 22.490,13
10 INSTALAÇÕES ELÉTRICAS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
116.696,12 23.339,22 18.671,38 18.671,38 18.671,38 18.671,38 18.671,38
11 CFTV E REDE 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
43.060,20 8.612,04 6.889,63 6.889,63 6.889,63 6.889,63 6.889,63
12 INSTALAÇÕES DE SPDA 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
36.553,26 7.310,65 5.848,52 5.848,52 5.848,52 5.848,52 5.848,52
13 DETECÇÃO E PROTEÇÃO CONTRA INCÊNDIOS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
5.521,70 1.104,34 883,47 883,47 883,47 883,47 883,47
14 PINTURAS 100,00% 15,00% 25,00% 35,00% 15,00% 10,00%
96.954,22 14.543,13 24.238,56 33.933,98 14.543,13 9.695,42
15 INSTALAÇÕES DE AR CONDICIONADO 100,00% 15,00% 25,00% 35,00% 15,00% 10,00%
31.038,07 4.655,71 7.759,52 10.863,32 4.655,71 3.103,81
16 PROGRAMAÇÃO VISUAL 100,00% 20,00% 20,00% 20,00% 20,00% 20,00%
24.304,47 4.860,89 4.860,89 4.860,89 4.860,89 4.860,89
17 FECHAMENTOS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
102.088,93 20.417,79 16.334,23 16.334,23 16.334,23 16.334,23 16.334,23
18 PORTÃO 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
7.317,71 1.463,54 1.170,83 1.170,83 1.170,83 1.170,83 1.170,83
19 PAVIMENTAÇÃO EXTERNA 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
62.741,28 12.548,26 10.038,60 10.038,60 10.038,60 10.038,60 10.038,60
20 EQUIPAMENTOS PARA AMBIENTES EXTERNOS 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
81.040,18 16.208,04 12.966,43 12.966,43 12.966,43 12.966,43 12.966,43
21 PAISAGISMO 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
6.746,11 1.349,22 1.079,38 1.079,38 1.079,38 1.079,38 1.079,38
22 FINALIZAÇÃO DA OBRA 100,00% 20,00% 16,00% 16,00% 16,00% 16,00% 16,00%
3.653,22 730,64 584,52 584,52 584,52 584,52 584,52
Porcentagem 20,32% 16,42% 16,41% 16,63% 15,23% 15,0%
Custo 559.314,55 451.923,08 451.663,43 457.933,23 419.275,90 412.876,29
Porcentagem Acumulado 20,32% 36,73% 53,14% 69,77% 85,0% 100,0%
Custo Acumulado 559.314,55 1.011.237,62 1.462.901,06 1.920.834,29 2.340.110,19 2.752.986,48