Você está na página 1de 2

13/03/18 13:23

Baker Hughes, a GE company


BANIT - BASE DE LOGÍSTICA DE FLEXÍVEIS
CRONOGRAMA OPERACIONAL

ID Área de Processo Linha / Compr. / Recurso Atividade - Nº e Descrição Origem Destino Ø Poço / Projeto % Baseline Start Finish Duration Predecessors
Complete Duration Mon 12 Mar Tue 13 Mar Wed 14 Mar
6 12 18 0 6 12 18 0 6
Text7: ARRUMAÇÃO DE ÁREA 0% 0,66h 10/03/18 05:20 10/03/18 13:40 7,83h

770 ARRUMAÇÃO IMPRODUTIVA 506-03/2018 MOV. BOBINA NOV 079 GE V J35 GE V L25 N/A N/A 0% 0,66 hrs 10/03/18 05:20 10/03/18 06:00 0,66 hrs 769
DE ÁREA
771 ARRUMAÇÃO IMPRODUTIVA 507-03/2018 MOV. BOBINA WBR186 GE V I30 GE V E29 N/A N/A 0% 0,66 hrs 10/03/18 06:00 10/03/18 07:09 0,66 hrs 770
DE ÁREA
772 ARRUMAÇÃO IMPRODUTIVA 508-03/2018 MOV. BOBINA NOV003 GE V J36 GE V I30 N/A N/A 0% 0,66 hrs 10/03/18 07:09 10/03/18 07:49 0,66 hrs 771
DE ÁREA
774 ARRUMAÇÃO IMPRODUTIVA 510-03/2018 MOV. BOBINA WBR201 10 X 5,4 GE V L37 GE V E33 N/A N/A 0% 0,66 hrs 10/03/18 07:55 10/03/18 08:35 0,66 hrs 773
DE ÁREA
777 ARRUMAÇÃO IMPRODUTIVA 513-03/2018 MOV. BOBINA NOV071 GE V M 37 GE V I28 N/A N/A 0% 0,66 hrs 10/03/18 09:42 10/03/18 10:22 0,66 hrs 776
DE ÁREA
778 ARRUMAÇÃO IMPRODUTIVA 514-03/2018 MOV. BOBINA WBR012 GE V N37 GE V J15 N/A N/A 0% 0,66 hrs 10/03/18 10:22 10/03/18 11:01 0,66 hrs 777
DE ÁREA
779 ARRUMAÇÃO IMPRODUTIVA 515-03/2018 MOV. BOBINA WBR221 BAIA 1 GE V J16 N/A N/A 0% 0,66 hrs 10/03/18 11:01 10/03/18 11:41 0,66 hrs 778
DE ÁREA
780 ARRUMAÇÃO IMPRODUTIVA 516-03/2018 MOV. BOBINA WBR022 BAIA 3 GE V 030 N/A N/A 0% 0,66 hrs 10/03/18 11:41 10/03/18 12:21 0,66 hrs 779
DE ÁREA
781 ARRUMAÇÃO IMPRODUTIVA 517-03/2018 MOV. RD-BL 06 BAIA 1 BAIA 3 N/A N/A 0% 0,66 hrs 10/03/18 12:21 10/03/18 13:00 0,66 hrs 780
DE ÁREA
782 ARRUMAÇÃO IMPRODUTIVA 518-03/2018 MOV. BOBINA 024-7844 7,8 X L31 BAIA 3 N/A N/A 0% 0,66 hrs 10/03/18 13:00 10/03/18 13:40 0,66 hrs 781
DE ÁREA 4,4
Text7: BAIA 3 0% 15h 06/03/18 19:40 09/03/18 22:10 70h

654 BAIA 3 C570L08 RISER DE 409-03/2018 AMARRAR E ENTREGAR PARA WBR022 N/A N/A IA-RJS-709 0% 15 hrs 06/03/18 19:40 09/03/18 22:10 70 hrs 653
TOPO MOVIMENTAÇÃO 8,6 X 4,4
655 BAIA 3 LINKBELT 410-03/2018 - AMARRÇÃO DE EXTREMIDADE N/A N/A N/A N/A 0% 3 hrs 09/03/18 19:10 09/03/18 22:10 3 hrs 654FF

Text7: BAIA 4 0% 60h 10/02/18 12:00 21/03/18 01:00 867h

544 BAIA 4 C571D08 RISER DE 140-02/2018 ACOMPANHAR FORNECEDOR WNC102 N/A N/A LC-P7 PO 0% 60 hrs 10/02/18 12:00 20/03/18 06:30 850 hrs 543 140-02/2018 ACOMPANHAR FORNECEDOR NA MONTAGEM DO MODA
TOPO NA MONTAGEM DO MODA 8,6 X 4,4
0%
545 BAIA 4 C571D08 RISER DE 141-02/2018 AMARRAR E ENTREGAR PARA WNC102 N/A N/A LC-P7 PO 0% 15 hrs 20/03/18 07:00 20/03/18 22:30 15 hrs 544
TOPO MOVIMENTAÇÃO 8,6 X 4,4
546 BAIA 4 LINKBELT 142-02/2018 - AMARRÇÃO DE EXTREMIDADE N/A N/A N/A N/A 0% 3 hrs 20/03/18 19:30 20/03/18 22:30 3 hrs 545FF

547 BAIA 4 JUMBO 143-02/2018 MOV. BOBINA WNC102 8,6 X 4,4 BAIA 4 N/A N/A N/A 0% 2 hrs 20/03/18 23:00 21/03/18 01:00 2 hrs 545

Text7: CAXIMBAU 1% 860h 07/03/18 15:00 14/04/18 20:00 860h

728 CAXIMBAU RDBL-12 473-03/2018 - REALIZAR REFORMA, RDBL-12 N/A N/A N/A 1% 860 hrs 07/03/18 15:00 14/04/18 20:00 860 hrs 473-03/2018 - REALIZAR REFORMA, MELHORIA E PRESERVAÇÃO DO RDBL-12
MELHORIA E PRESERVAÇÃO DO RDBL-12
1%
Text7: CESTO 1 85% 16h 12/03/18 15:40 13/03/18 08:40 16,01h
Text7: CESTO 1

708 CESTO 1 LINKBELT 458-03/2018 - DESAMARRÇÃO/AMARRAÇÃO N/A N/A N/A N/A 0% 1 hr 12/03/18 15:40 12/03/18 16:35 0,92 hrs 707 - DESAMARRÇÃO/AMARRAÇÃO DE EXTREMIDADE
458-03/2018
08/03/18 07:31 08/03/18 08:31
DE EXTREMIDADE
0%
709 CESTO 1 34000001 RISER 459-03/2018 - REALIZAR TRANSFERENCIA DO CESTO 1 CESTO 2 N/A P19 95% 16 hrs 12/03/18 15:40 13/03/18 08:40 16 hrs 708 459-03/2018 - REALIZAR TRANSFERENCIA DO CESTO 1 PARA CESTO 2
08/03/18 07:31 09/03/18 00:31
INTERM. 6" 1200M CESTO 1 PARA CESTO 2
95%
710 CESTO 1 LINKBELT 460-03/2018 - DESAMARRÇÃO/AMARRAÇÃO N/A N/A N/A N/A 0% 1 hr 13/03/18 07:47 13/03/18 08:40 0,88 hrs 709FF 460-03/2018 - DESAMARRÇÃO/AMARRAÇÃO DE EXTREMIDADE
08/03/18 23:31 09/03/18 00:31
DE EXTREMIDADE
0%
Text7: FRENTE 1 0% 3h 13/03/18 16:00 13/03/18 19:00 3h
Text7: FRENTE 1

799 FRENTE 1 SOLICITAÇÃO DE NOVAS DEMANDAS 0% 0 hrs 13/03/18 16:00 13/03/18 16:00 0 hrs 798
13/03/18 16:00

800 FRENTE 1 WBR218 7,8 X 4,4 528-03/2018 - REALIZAR LIMPEZA DA BOBINA WBR218 N/A N/A N/A 0% 3 hrs 13/03/18 16:00 13/03/18 19:00 3 hrs 799 528-03/2018 - REALIZAR LIMPEZA DA BOBINA WBR218 7,8 X 4,4
13/03/18 16:00 13/03/18 19:00
WBR218 7,8 X 4,4 7,8 X 4,4
0%
Text7: FRENTE 2 0% 20h 10/03/18 13:50 13/03/18 16:00 69,17h
Text7: FRENTE 2

743 FRENTE 2 SOLICITAÇÃO DE NOVAS DEMANDAS 0% 0 hrs 10/03/18 13:50 10/03/18 13:50 0 hrs

744 FRENTE 2 JUMBO 485-03/2018 MOV. BOBINA WBR230 7,8 X 4,4 BAIA 2 24F2 N/A N/A 0% 0,66 hrs 10/03/18 13:50 10/03/18 14:30 0,66 hrs 743

745 FRENTE 2 LINKBELT 486-03/2018 - DESAMARRÇÃO/AMARRAÇÃO N/A N/A N/A N/A 0% 2 hrs 10/03/18 14:30 10/03/18 17:00 2 hrs 744
DE EXTREMIDADE
746 FRENTE 2 3896B2.2.2 UEH 269M 487-03/2018 - REALIZAR TRATATIVAS WBR230 N/A N/A BFR-006 0% 20 hrs 10/03/18 15:00 11/03/18 12:00 20 hrs 744
CONFORME SIT 16/2018. 7,8 X 4,4
747 FRENTE 2 LINKBELT 488-03/2018 - DESAMARRÇÃO/AMARRAÇÃO N/A N/A N/A N/A 0% 2 hrs 11/03/18 10:00
488-03/2018 11/03/18 12:00
- DESAMARRÇÃO/AMARRAÇÃO2DEhrs 746FF
EXTREMIDADE
DE EXTREMIDADE
748 FRENTE 2 JUMBO 489-03/2018 MOV. BOBINA WBR230 7,8 X 4,4 24F2 S11 N/A N/A 0% 0,66 hrs 11/03/18 12:00 11/03/18 12:40 0,66 hrs 746

797 FRENTE 2 SOLICITAÇÃO DE NOVAS DEMANDAS 0% 0 hrs 13/03/18 12:30 13/03/18 12:30 0 hrs
13/03/18 12:30

798 FRENTE 2 WBR094 8,6 x 4,4 527-03/2018 - REALIZAR LIMPEZA DA BOBINA WBR094 N/A N/A N/A 0% 3 hrs 13/03/18 12:30 13/03/18 16:00 3 hrs 797 527-03/2018 - REALIZAR LIMPEZA DA BOBINA WBR094 8,6 x 4,4
13/03/18 12:30 13/03/18 16:00
WBR094 8,6 x 4,4 8,6 x 4,4
0%
Text7: FRENTE 3 14% 120h 11/03/18 18:30 19/03/18 04:10 166,66h

750 FRENTE 3 2800B2 UEH ~220M 491-03/2018 REALIZAR CORTE CONFORME SIT WBR222 N/A N/A DESCARTE 52% 33 hrs 11/03/18 18:30 13/03/18 19:30 46 hrs 749 491-03/2018 REALIZAR CORTE CONFORME SIT 17/2018
17/03/18 07:40
17/2018 7,8 X 4,4
52%
751 FRENTE 3 2800B2 UEH 120M 492-03/2018 REALIZAR DISSECAÇÃO 019-7844 N/A N/A DESCARTE 0% 120 hrs 13/03/18 19:30 19/03/18 03:30 120 hrs 750 492-03/2018 REALIZAR DISSECAÇÃO CONFORME SIT 17/2018
17/03/18 07:40
CONFORME SIT 17/2018 7,8 X 4,4
0%
506 FRENTE 3 JUMBO 1 150-02/2018 MOV. BOBINA WBR222 7,8 X 4,4 N/A N/A N/A N/A 0% 0,66 hrs 19/03/18 03:30 19/03/18 04:10 0,66 hrs 751

Text7: MANUTENÇÃO 0% 2h 13/03/18 08:00 13/03/18 15:30 7h


Text7: MANUTENÇÃO

795 MANUTENÇÃO RIM DRIVE 7 525-03/2018 - PARADA PARA MANUTENÇÃO N/A N/A N/A N/A 0% 2 hrs 13/03/18 08:00 13/03/18 10:00 2 hrs 525-03/2018 - PARADA PARA MANUTENÇÃO
13/03/18 08:00 13/03/18 10:00
0%

796 MANUTENÇÃO CARROSSEL 2 526-03/2018 - PARADA PARA MANUTENÇÃO N/A N/A N/A N/A 0% 2 hrs 13/03/18 13:00 13/03/18 15:30 2 hrs 526-03/2018 - PARADA PARA MANUTENÇÃO
13/03/18 13:00 13/03/18 15:30
0%

Text7: MOVIMEN TAÇÃO 0% 1h 13/03/18 09:00 13/03/18 10:00 1h


Text7: MOVIMEN TAÇÃO

793 MOVIMEN INCLUSÃO DE NOVAS DEMANDAS 0% 0 hrs 13/03/18 09:00 13/03/18 09:00 0 hrs
13/03/18 09:00
TAÇÃO

Page 1
13/03/18 13:23
Baker Hughes, a GE company
BANIT - BASE DE LOGÍSTICA DE FLEXÍVEIS
CRONOGRAMA OPERACIONAL

ID Área de Processo Linha / Compr. / Recurso Atividade - Nº e Descrição Origem Destino Ø Poço / Projeto % Baseline Start Finish Duration Predecessors
Complete Duration Mon 12 Mar Tue 13 Mar Wed 14 Mar
6 12 18 0 6 12 18 0 6
794 MOVIMEN 524-03/2018 AÇÕES ADMINISTRATIVA DE N/A N/A N/A N/A 0% 1 hr 13/03/18 09:00 13/03/18 10:00 1 hr 793 524-03/2018 AÇÕES ADMINISTRATIVA DE EHS, INTEGRIDADE, COMPLIANCE.
13/03/18 09:00 13/03/18 10:00
TAÇÃO EHS, INTEGRIDADE, COMPLIANCE.
0%
Text7: OPERAÇÕES 0% 1h 13/03/18 03:00 13/03/18 10:00 6,5h
Text7: OPERAÇÕES

785 OPERAÇÕES INCLUSÃO DE NOVAS DEMANDAS 0% 0 hrs 13/03/18 03:00 13/03/18 03:00 0 hrs
13/03/18 03:00

786 OPERAÇÕES 520-03/2018 AÇÕES ADMINISTRATIVA DE N/A N/A N/A N/A 0% 1 hr 13/03/18 03:00 13/03/18 04:00 1 hr 785 520-03/2018 AÇÕES ADMINISTRATIVA DE EHS, INTEGRIDADE, COMPLIANCE.
13/03/18 03:00 13/03/18 04:00
EHS, INTEGRIDADE, COMPLIANCE.
0%
787 OPERAÇÕES INCLUSÃO DE NOVAS DEMANDAS 0% 0 hrs 13/03/18 09:00 13/03/18 09:00 0 hrs
13/03/18 09:00

788 OPERAÇÕES 521-03/2018 AÇÕES ADMINISTRATIVA DE N/A N/A N/A N/A 0% 1 hr 13/03/18 09:00 13/03/18 10:00 1 hr 787 521-03/2018 AÇÕES ADMINISTRATIVA DE EHS, INTEGRIDADE, COMPLIANCE.
13/03/18 09:00 13/03/18 10:00
EHS, INTEGRIDADE, COMPLIANCE.