Você está na página 1de 29

NORMA ABNT NBR

BRASILEIRA 12218

Segunda edição
03.05.2017

Projeto de rede de distribuição de água para


abastecimento público — Procedimento
Project of water distribution network for public supply — Procedure

ICS 93.025; 91.140.60 ISBN 978-85-07-06942-3

Número de referência
ABNT NBR 12218:2017
23 páginas

© ABNT 2017
ABNT NBR 12218:2017

© ABNT 2017
7RGRVRVGLUHLWRVUHVHUYDGRV$PHQRVTXHHVSHFL¿FDGRGHRXWURPRGRQHQKXPDSDUWHGHVWDSXEOLFDomRSRGHVHU
UHSURGX]LGDRXXWLOL]DGDSRUTXDOTXHUPHLRHOHWU{QLFRRXPHFkQLFRLQFOXLQGRIRWRFySLDHPLFUR¿OPHVHPSHUPLVVmRSRU
escrito da ABNT.

ABNT
$Y7UH]HGH0DLRžDQGDU
20031-901 - Rio de Janeiro - RJ
7HO
)D[
DEQW#DEQWRUJEU
ZZZDEQWRUJEU

ii © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

Sumário Página

Prefácio ................................................................................................................................................v
1 Escopo ................................................................................................................................1
2 Referências normativas .....................................................................................................1
 7HUPRVHGH¿QLo}HV ...........................................................................................................1
4 Requisitos gerais .............................................................................................................10
4.1 Desenvolvimento do projeto ...........................................................................................10
4.1.1 Elementos necessários para o desenvolvimento do projeto.......................................10
4.1.2 Elementos a considerar no desenvolvimento do projeto ............................................10
4.1.3 Atividades necessárias ao desenvolvimento do projeto .............................................10
4.1.4 Elementos que devem compor o projeto ....................................................................... 11
 5HTXLVLWRVHVSHFt¿FRV ....................................................................................................12
5.1 Área a ser abastecida ......................................................................................................12
 9D]}HVSDUDGLPHQVLRQDPHQWR .......................................................................................12
5.3 Pressão de serviço...........................................................................................................13
5.4 Rede de distribuição de água existente .........................................................................13
 7UDoDGRGDVWXEXODo}HV ..................................................................................................13
5.6 Dimensionamento ............................................................................................................14
5.7 Zona de pressão ...............................................................................................................15
5.8 Distrito de medição e controle (DMC) ............................................................................15
5.9 Setor de manobra (SM) ...................................................................................................15
5.10 Sistema de proteção contra incêndio por meio de hidrante urbano – SPCIHU ........16
5.11 Componentes da rede e equipamentos acessórios .....................................................18
5.11.1 Válvula de manobra .........................................................................................................18
5.11.2 Válvula de descarga .........................................................................................................18
5.11.3 Ventosa..............................................................................................................................18
5.11.4 Booster ..............................................................................................................................19
5.11.5 Válvula redutora de pressão (VRP) ................................................................................19
5.11.6 Medidores ou controladores de pressão .......................................................................19
5.11.7 Medidores ou controladores de vazão ...........................................................................20
5.12 Ligação predial .................................................................................................................20
5.12.1 Dispositivo de interligação do usuário à rede...............................................................20
5.12.2 Ramal de interligação da rede à ligação predial do usuário ........................................20
5.12.3 Unidade de medição de consumo ..................................................................................20
5.12.4 Pontos para monitoramento da qualidade da água ......................................................20
5.13 Travessia ...........................................................................................................................20
5.14 Ancoragem........................................................................................................................21
 &RQGLo}HVPHFkQLFDV......................................................................................................21
 'LVSRVLo}HVFRQVWUXWLYDV ................................................................................................21
 (VSHFL¿FDo}HVWpFQLFDV ..................................................................................................22
 (VSHFL¿FDo}HVWpFQLFDVGRVVHUYLoRVHPDWHULDLV .......................................................22
 (VSHFL¿FDomRWpFQLFDGRVFRPSRQHQWHVHHTXLSDPHQWRVDFHVVyULRV ......................22

© ABNT 2017 - Todos os direitos reservados iii


ABNT NBR 12218:2017

5.18 Orçamento ........................................................................................................................23


5.19 Plano de implantação e execução da obra ....................................................................23
5.19.1 Etapas de implantação ....................................................................................................23
5.19.2 Plano de execução da obra .............................................................................................23
 2XWUDVFRQGLo}HV .............................................................................................................23

Tabelas
Tabela 1 – Tabela de distribuição de hidrantes na rede de distribuição de água .......................16
7DEHOD±7DEHODGHFODVVL¿FDomRGHKLGUDQWHV ............................................................................17

iv © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

Prefácio

$$VVRFLDomR%UDVLOHLUDGH1RUPDV7pFQLFDV $%17 pR)RUR1DFLRQDOGH1RUPDOL]DomR$V1RUPDV


%UDVLOHLUDVFXMRFRQWH~GRpGHUHVSRQVDELOLGDGHGRV&RPLWrV%UDVLOHLURV $%17&% GRV2UJDQLVPRV
GH 1RUPDOL]DomR 6HWRULDO $%17216  H GDV &RPLVV}HV GH (VWXGR (VSHFLDLV $%17&((  VmR
HODERUDGDVSRU&RPLVV}HVGH(VWXGR &( IRUPDGDVSHODVSDUWHVLQWHUHVVDGDVQRWHPDREMHWRGD
QRUPDOL]DomR

2V'RFXPHQWRV7pFQLFRV$%17VmRHODERUDGRVFRQIRUPHDVUHJUDVGD'LUHWLYD$%173DUWH

$$%17FKDPDDDWHQomRSDUDTXHDSHVDUGHWHUVLGRVROLFLWDGDPDQLIHVWDomRVREUHHYHQWXDLVGLUHLWRV
GHSDWHQWHVGXUDQWHD&RQVXOWD1DFLRQDOHVWHVSRGHPRFRUUHUHGHYHPVHUFRPXQLFDGRVj$%17D
TXDOTXHUPRPHQWR /HLQžGHGHPDLRGH 

5HVVDOWDVHTXH1RUPDV%UDVLOHLUDVSRGHPVHUREMHWRGHFLWDomRHP5HJXODPHQWRV7pFQLFRV1HVWHV
FDVRVRVÏUJmRVUHVSRQViYHLVSHORV5HJXODPHQWRV7pFQLFRVSRGHPGHWHUPLQDURXWUDVGDWDVSDUD
H[LJrQFLDGRVUHTXLVLWRVGHVWD1RUPD

$$%171%5IRLHODERUDGDQR&RPLWr%UDVLOHLURGH6DQHDPHQWR $%17&% SHOD&RPLVVmR


GH(VWXGRGH3URMHWRVSDUD6LVWHPDVGH6DQHDPHQWR &( 23URMHWRGH5HYLVmRFLUFXORX
HP&RQVXOWD1DFLRQDOFRQIRUPH(GLWDOQžGHD

(VWD VHJXQGD HGLomR FDQFHOD H VXEVWLWXL D HGLomR DQWHULRU $%17 1%5   D TXDO IRL
tecnicamente revisada.

2(VFRSRHPLQJOrVGHVWD1RUPD%UDVLOHLUDpRVHJXLQWH

Scope
This Standard establishes the conditions required in the project of water distribution network for public
supply.

© ABNT 2017 - Todos os direitos reservados v


NORMA BRASILEIRA ABNT NBR 12218:2017

Projeto de rede de distribuição de água para abastecimento público —


Procedimento

1 Escopo
(VWD1RUPDHVWDEHOHFHRVUHTXLVWRVSDUDDHODERUDomRGHSURMHWRGHUHGHGHGLVWULEXLomRGHiJXDSDUD
DEDVWHFLPHQWRS~EOLFR

2 Referências normativas
2VGRFXPHQWRVUHODFLRQDGRVDVHJXLUVmRLQGLVSHQViYHLVjDSOLFDomRGHVWHGRFXPHQWR3DUDUHIH-
UrQFLDVGDWDGDVDSOLFDPVHVRPHQWHDVHGLo}HVFLWDGDV3DUDUHIHUrQFLDVQmRGDWDGDVDSOLFDPVH
DVHGLo}HVPDLVUHFHQWHVGRUHIHULGRGRFXPHQWR LQFOXLQGRHPHQGDV 

$%17 1%5  Estudos de concepção de sistemas públicos de abastecimento de água –


Procedimento

$%17 1%5  Projeto de sistema de bombeamento de água para abastecimento público –
Procedimento

3 7HUPRVHGH¿QLo}HV
3DUDRVHIHLWRVGHVWHGRFXPHQWRDSOLFDPVHRVVHJXLQWHVWHUPRVHGH¿QLo}HV

3.1
alcance do plano
GH¿QLomRGRDQR¿QDOGHDEUDQJrQFLDGRSODQRHRXHVWXGR

3.2
DOWXUDPDQRPpWULFD
VRPDGDDOWXUDJHRPpWULFD GLIHUHQoDGHFRWDV HQWUHRVQtYHLVGHVXFomRHGHVFDUJDGRÀXLGRFRPDV
SHUGDVGHFDUJDGLVWULEXtGDVHORFDOL]DGDVDRORQJRGHWRGRRVLVWHPD

3.3
as-built
H[SUHVVmRHPLQJOrVTXHVLJQL¿FD³FRPRFRQVWUXtGR´

3.4
berço para assentamento de tubulação
FDPDGDGHVRORRXRXWURPDWHULDOVLWXDGDHQWUHRIXQGRGDYDODHDJHUDWUL]LQIHULRUGDWXEXODomR
FRPD¿QDOLGDGHGHUHJXODUL]DomRGRIXQGRGDYDODVXSRUWHHSURWHomRGDWXEXODomRHGHVXDVSDUWHV
integrantes

3.5
booster
ver 3.33

© ABNT 2017 - Todos os direitos reservados 1


ABNT NBR 12218:2017

3.6
cadastro
FRQMXQWRGHLQIRUPDo}HVGRVHOHPHQWRVHGDGRVWpFQLFRVGHXPDLQVWDODomRH[LVWHQWHDSUHVHQWDGR
SRU PHLR GH WH[WRV H UHSUHVHQWDo}HV JUi¿FDV HP HVFDOD DGHTXDGD 3UHIHUHQFLDOPHQWH GLJLWDOL]DGR
HJHRUUHIHUHQFLDGR

3.7
capacidade nominal
YD]mRRXYROXPHHPFRQGLo}HVQRUPDLVGHIXQFLRQDPHQWRSDUDDTXDODLQVWDODomRpSURMHWDGD

3.8
carga móvel
FDUJDRULXQGDGRWUiIHJRGHYHtFXORV

3.9
carga da vala
FDUJDWRWDODTXHDWXEXODomRHVWiVXMHLWDGHYLGRDXPDRXYiULDVGDVFDUJDVDVHJXLULQGLFDGDV

௘D  peso do reaterro

௘E  FDUJDHVWiWLFDGLVWULEXtGDDFLPDGRUHDWHUUR

௘F  FDUJDPyYHO

3.10
classe de rigidez (CR)
UHVLVWrQFLDGHXPWXERjGHIRUPDomRVREXPDFDUJDH[WHUQDDSOLFDGDVHJXQGRXPSODQRGLDPHWUDO

3.11
categoria de consumidor
TXDOL¿FDomRGRFRQVXPLGRUGHDFRUGRFRPRXVRSULQFLSDOTXHID]GDiJXD

3.12
FRH¿FLHQWHNNN

— .FRH¿FLHQWHGHYDULDELOLGDGHPi[LPDGLiULDGRÀX[R

— NFRH¿FLHQWHGHYDULDELOLGDGHPi[LPDKRUiULDGRÀX[R

— NFRH¿FLHQWHGHYDULDELOLGDGHPtQLPDGRÀX[R

3.13
componentes e equipamentos acessórios
GLVSRVLWLYRVLQVWDODGRVSDUDRWLPL]DUDVDWLYLGDGHVGHRSHUDomRHRXPDQXWHQomRQRVLVWHPD

3.14
conduto principal
WXEXODomR GD UHGH GH GLVWULEXLomR GH PDLRU GLkPHWUR FRP D ¿QDOLGDGH GH DEDVWHFHU WXEXODo}HV
secundárias

2 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

3.15
conduto secundário
WXEXODomRGDUHGHGHGLVWULEXLomRGHPHQRUGLkPHWURFRPDIXQomRGHDEDVWHFHURVSRQWRVGHFRQVXPR

3.16
conduto forçado
DTXHOHHPTXHRÀXLGRRFXSDWRWDOPHQWHDVHomRGHHVFRDPHQWRFRPSUHVVmRGLIHUHQWHGDDWPRVIpULFD

3.17
FRQH[}HV
SHoDVGHVWLQDGDVjXQLmRPXGDQoDGHGLUHomRWDPSRQDPHQWRGHULYDo}HVRXUHSDURVGDWXEXODomR

3.18
consumidor singular
grande consumidor
DTXHOHTXHDSUHVHQWDXPFRQVXPRVLJQL¿FDWLYDPHQWHPDLRUTXHRFRQVXPRPpGLRHVSHFt¿FRDGRWDGR
para a área

3.19
consumidor especial
DTXHOH TXH GHYH WHU VHX DWHQGLPHQWR SULRUL]DGR HP GHFRUUrQFLD GH PRWLYRV MXVWL¿FiYHLV
LQGHSHQGHQWHPHQWHGHDVSHFWRVHFRQ{PLFRVUHODFLRQDGRVDRVHXDWHQGLPHQWR

3.20
consumo
TXDQWLGDGHGHiJXDXWLOL]DGDSHORFRQVXPLGRUHPXPGHWHUPLQDGRSHUtRGR

3.21
consumo de água
TXDQWLGDGHGHiJXDXWLOL]DGDSHORXVXiULR

3.22
curva característica da bomba
FXUYDQDTXDODFDGDYDORUGDDOWXUDPDQRPpWULFDFRUUHVSRQGHDXPDVyYD]mRLQGLFDGDSHORIDEULFDQWH
do equipamento

3.23
curva característica do sistema
FXUYDTXHUHSUHVHQWDRVSRQWRVGHRSHUDomRGRVLVWHPDFRUUHODFLRQDQGRDFDSDFLGDGHGHWUDQVSRUWH
QDWXEXODomRFRPDXQLGDGHIRUQHFHGRUDGHHQHUJLD VLVWHPDGHERPEHDPHQWRUHVHUYDWyULR

3.24
data de início do plano
GDWDGHLQtFLRHVWDEHOHFLGDFRPRUHIHUHQFLDOQRGHVHQYROYLPHQWRGRSODQHMDPHQWRHVWXGRVRXSURMHWRV
para um sistema

3.25
data de início de operação
GDWDSUHYLDPHQWH¿[DGDSDUDLQtFLRGDRSHUDomRGRVLVWHPD

© ABNT 2017 - Todos os direitos reservados 3


ABNT NBR 12218:2017

3.26
deformação diametral
ovalização
GLIHUHQoD HQWUH R GLkPHWUR H[WHUQR PpGLR H R GLkPHWUR H[WHUQR PtQLPR GR WXER GHIRUPDGR SRU
FRPSUHVVmRGLDPHWUDO

3.27
deformação diametral relativa
TXRFLHQWHGDGHIRUPDomRGLDPHWUDOSHORGLkPHWURH[WHUQRPpGLRH[SUHVVRFRPRSRUFHQWDJHP

3.28
GLkPHWURLQWHUQR
GLPHQVmRFRUUHVSRQGHQWHDRGLkPHWURH[WHUQRGHVFRQWDGDVGXDVYH]HVDHVSHVVXUDGDSDUHGH

3.29
GLkPHWURH[WHUQR
pDPDLRUGLPHQVmRPHGLGDQDVHomRWUDQVYHUVDOGHXPDWXEXODomR

3.30
GLkPHWURQRPLQDO '1
VLPSOHVQ~PHURTXHVHUYHSDUDFODVVL¿FDUHPGLPHQV}HVRVHOHPHQWRVGHWXEXODo}HV WXERVMXQWDV
FRQH[}HVDFHVVyULRV

127$ 2GLkPHWURQRPLQDO '1 QmRpREMHWRGHPHGLomRQHPGHXWLOL]DomRSDUD¿QVGHFiOFXORV

3.31
distrito de medição e controle DMC
iUHDGHOLPLWDGDHLVROiYHOTXHSRVVLELOLWDDJHVWmRGRVLVWHPDSRUPHLRGRPRQLWRUDPHQWRPHGLomR
HFRQWUROHGHYD]}HVHRXSUHVV}HVSHUPLWLQGRGH¿QLULQGLFDGRUHVRSHUDFLRQDLVDYDOLDUHFRQWURODU
perdas

3.32
espessura de parede da tubulação (e)
PHGLGDHQWUHDVVXSHUItFLHVH[WHUQDHLQWHUQDHPTXDOTXHUSRQWRGDVHomRWUDQVYHUVDOGDWXEXODomR

3.33
estação elevatória (EE)
FRQMXQWRGHHVWUXWXUDVHHTXLSDPHQWRVGHVWLQDGRDSURPRYHURUHFDOTXHGRÀXLGRFRPD¿QDOLGDGH
GH HIHWXDU D VXD HOHYDomR GH QtYHO H FRPSHQVDU DV SHUGDV GH FDUJD QD OLQKD 1R FDVR SDUWLFXODU
HPTXHDSUHVVmRGHPRQWDQWHpVXSHULRUjDWPRVIpULFDDHVWDomRHOHYDWyULDSDVVDDWHUDGHVLJQDomR
de booster HVWDomRLPSXOVLRQDGRUD

3.34
etapas de implantação
FRQMXQWRGHREUDVGRVLVWHPDTXHDWHQGHjVFRQGLo}HV jVVROLFLWDo}HV GHIXQFLRQDPHQWRHPFDGD
XPGRVLQWHUYDORVGRSHUtRGRGRKRUL]RQWHGRSURMHWR

3.35
golpe de aríete
IHQ{PHQR UHVXOWDQWH GR WUDQVLWyULR KLGUiXOLFR TXDQGR RFRUUH YDULDomR EUXVFD GH SUHVVmR DFLPD RX
DEDL[RGRYDORUQRUPDOGHIXQFLRQDPHQWR

4 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

3.36
horizonte do estudo
horizonte do projeto
GH¿QLomRGRSHUtRGRGHWHPSRTXHRVLVWHPDWHPTXHRSHUDUDWHQGHQGRDRSUHYLVWR2KRUL]RQWHGR
HVWXGRRXGRSURMHWRSRGHVHUGLYLGLGRHPHWDSDV

3.37
junta
SRQWRGHXQLmRHQWUHWXEXODo}HVRXHQWUHWXEXODomRHFRQH[mRFRPDVPHVPDVFRQGLo}HVGHRSHUDomR
GD WXEXODomR TXH SHUPLWH R VHTXHQFLDPHQWR GR VLVWHPD JDUDQWLQGR D HVWDQTXHLGDGH QD LQWHUIDFH
HQWUHDVH[WUHPLGDGHVHDVFRQGLo}HVPHFkQLFDVHVWDEHOHFLGDV

3.38
ligação predial de água
WUHFKRGRVLVWHPDGHGLVWULEXLomRGHiJXDTXHREMHWLYDRDEDVWHFLPHQWRGHXPRXPDLVXVXiULRVFRP-
SUHHQGLGRDSDUWLUGDWRPDGDGiJXDQDUHGHGHGLVWULEXLomRDWpDXQLGDGHGHPHGLomRGHFRQVXPR
LQFOXVLYH

3.39
macromedição
SURFHVVR UHIHUHQWH j PHGLomR HVWLPDomR H PRQLWRUDPHQWR GH SDUkPHWURV RSHUDFLRQDLV KLGUiXOL-
FRV HP SRQWRV GH FRQWUROH GH VLVWHPDV GH DEDVWHFLPHQWR GH iJXD HRX GH HVJRWDPHQWR VDQLWiULR
FRPRYD]mRSUHVVmRHQtYHO&RPLQVWDODomRSDUDPHGLomRSHUPDQHQWHRXQmR2EMHWLYDFRQWURODU
DVSHUGDVWRWDLVPRQLWRUDURFRQWUROHRSHUDFLRQDODYDOLDUDVGHPDQGDVHRGHVHPSHQKRGRVHWRU
de saneamento

3.40
máxima pressão de operação MPO (pressão máxima)
Pi[LPDSUHVVmRDTXHRVFRPSRQHQWHVGRVLVWHPDSRGHPHVWDUVXEPHWLGRVHPVHUYLoR

3.41
micromedição
PHGLomR GR FRQVXPR UHDOL]DGD QR SRQWR GH DEDVWHFLPHQWR GH iJXD RX GH FRQWULEXLomR GH HVJRWR
VDQLWiULR GH XP GHWHUPLQDGR XVXiULR LQGHSHQGHQWH GH VXD FDWHJRULD RX IDL[D GH FRQVXPR
&RPSUHHQGHDPHGLomRSHUPDQHQWHGRYROXPHGHiJXDFRQVXPLGRUHJLVWUDGRSHULRGLFDPHQWHSRU
PHLR GD LQGLFDomR SURSLFLDGD SHOD XQLGDGH GH PHGLomR GH FRQVXPR 2EMHWLYD PHGLU R FRQVXPR H
FRQWULEXLUFRPRFRQWUROHGDVSHUGDVWRWDLV

3.42
módulo reativo do solo (E’) (Pa)
IDWRULQGLFDWLYRGDFDSDFLGDGHGHVXSRUWHGRVRORGHHQYROYLPHQWRODWHUDOGRWXER

3.43
operadora
HQWLGDGHUHVSRQViYHOSHODDGPLQLVWUDomRGRVLVWHPDGHDEDVWHFLPHQWRGHiJXDHRXGHHVJRWDPHQWR
sanitário

3.44
perdas aparentes
YROXPHGHiJXDFRQVXPLGRPDVQmRFRQWDELOL]DGRSHODRSHUDGRUD

3.45
perdas reais
YROXPHGHiJXDSURGX]LGRTXHQmRFKHJDDRFRQVXPLGRU¿QDO

© ABNT 2017 - Todos os direitos reservados 5


ABNT NBR 12218:2017

3.46
perdas totais de água
soma das perdas reais e perdas aparentes

3.47
plano de execução da obra
GHWDOKDPHQWR GDV IDVHV H[HFXWLYDV GD REUD RX GR HPSUHHQGLPHQWR SHUPLWLQGR R SODQHMDPHQWR H
D JHVWmR GD H[HFXomR FRPSDWLELOL]DQGR DV SURJUDPDo}HV GH SDUDGDV GR VLVWHPD FRP DV HWDSDV
FRQVWUXWLYDVGRVVHUYLoRV

3.48
população abastecida
DTXHODDWHQGLGDSHORVLVWHPDGHDEDVWHFLPHQWRGHiJXD

3.49
população de projeto
DTXHODSURMHWDGDSDUDVHUDWHQGLGDHPXPGHWHUPLQDGRSHUtRGR

3.50
SRSXODomR¿QDO
população de alcance do plano
DTXHODSUHYLVWDSDUDRDQRGHDOFDQFHGRSODQRRXSURMHWR

3.51
SRSXODomRÀXWXDQWH
população temporária
DTXHODTXHXWLOL]DWHPSRUDULDPHQWHRVLVWHPDRFDVLRQDQGRLPSDFWRVDHOH

3.52
população inicial
DTXHODDVHUDWHQGLGDQRDQRGHLQtFLRGHRSHUDomRGDXQLGDGH

3.53
população residente
DTXHODSHUPDQHQWHQDiUHDHPHVWXGR

3.54
população total
VRPDGDVSRSXODo}HVUHVLGHQWHHÀXWXDQWHRXWHPSRUiULDDWHQGtYHOQRDOFDQFHGRSODQRRXSURMHWR

3.55
pressão devida às cargas acidentais
SUHVVmRDWXDQWHQDVXSHUItFLHVXSHULRUGDWXEXODomRUHVXOWDQWHGDVFDUJDVRFDVLRQDLVQmRSUHYLVWDV
QRVFiOFXORV

3.56
pressão devida às cargas móveis
SUHVVmRDWXDQWHQDVXSHUItFLHVXSHULRUGDWXEXODomRUHVXOWDQWHGDVFDUJDVUHSUHVHQWDGDVSHORWUiIHJR
QDVXSHUItFLHGRWHUUHQR

3.57
pressão devida à carga de solo
pressão estática do solo
SUHVVmRDWXDQWHQDVXSHUItFLHVXSHULRUGDWXEXODomRUHVXOWDQWHGDVFDUJDVGHYLGDVDRSHVRGRVROR

6 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

3.58
pressão de serviço
SUHVVmRDWXDQWHQRVFRPSRQHQWHVGRVLVWHPDTXDQGRGDRFRUUrQFLDGRUHJLPHKLGUiXOLFRSHUPDQHQWH

3.59
pressão de serviço máxima
SUHVVmRPi[LPDDWXDQWHQRVFRPSRQHQWHVGRVLVWHPDTXDQGRGDRFRUUrQFLDGRUHJLPHWUDQVLWyULR

3.60
SUHVVmRGLQkPLFDGLVSRQtYHO
VLPSOHVPHQWHSUHVVmRGLQkPLFD
SUHVVmR HP GHWHUPLQDGR SRQWR GD WXEXODomR UHIHUHQFLDGD DR QtYHO GR WHUUHQR VRE FRQGLomR GH
consumo

3.61
pressão estática disponível
simplesmente pressão estática
SUHVVmR HP GHWHUPLQDGR SRQWR GD WXEXODomR UHIHUHQFLDGD DR QtYHO GR WHUUHQR VRE FRQGLomR GH
FRQVXPRQXOR

3.62
pressão hidrostática interna
SUHVVmRUDGLDODSOLFDGDSRUXPÀXLGRDRORQJRGHWRGDDSDUHGHLQWHUQDGRVFRPSRQHQWHVGRVLVWHPD

3.63
pressão nominal (PN)
SUHVVmRGHUHIHUrQFLDSDUDRVFRPSRQHQWHVGRVLVWHPDLQGLFDGDSHORIDEULFDQWHH[SUHVVDSRUXP
Q~PHURLQWHLURGHXQLGDGHGHSUHVVmR

3.64
profundidade da vala
GLVWkQFLD YHUWLFDO HQWUH D VXSHUItFLH GR WHUUHQR H D JHUDWUL] LQIHULRU H[WHUQD GD WXEXODomR DFUHVFLGR
GREHUoRVRERWXERTXDQGRKRXYHU

3.65
ramal condominial de água
WXEXODomRFRPSUHHQGLGDHQWUHDXQLGDGHGHPHGLomRHXPDXQLGDGHGHDOLPHQWDomRGHYiULDVOLJDo}HV
DWHQGLGDVSRUUHGHFRQGRPLQLDO

3.66
ramal predial de água
WXEXODomRFRPSUHHQGLGDHQWUHDUHGHGHGLVWULEXLomRGHiJXDHDXQLGDGHGHPHGLomRGHFRQVXPR

3.67
UHDWHUUR¿QDO
WUHFKRGRDWHUURFRPSUHHQGLGRHQWUHRDWHUURVXSHULRUHRQtYHOGRWHUUHQR

3.68
reaterro lateral
WUHFKRGRDWHUURVLWXDGRGHFDGDODGRGDWXEXODomROLPLWDGRSHOREHUoRHSHORSODQRWDQJHQWHjJHUDWUL]
VXSHULRU GD WXEXODomR FRP HVSHVVXUD H JUDX GH FRPSDFWDomR GH¿QLGRV HP SURMHWR FRQVLGHUDQGR
RPDWHULDOGDWXEXODomRDSOLFDGDHRVRORORFDOHGHUHDWHUUR

© ABNT 2017 - Todos os direitos reservados 7


ABNT NBR 12218:2017

3.69
reaterro superior
WUHFKR GH DWHUUR VLWXDGR DFLPD GR SODQR WDQJHQWH j JHUDWUL] VXSHULRU GD WXEXODomR H RXWUR SODQR
SDUDOHORDHVWHFRPHVSHVVXUDHJUDXGHFRPSDFWDomRGH¿QLGRVHPSURMHWRFRQVLGHUDQGRRPDWHULDO
GDWXEXODomRDSOLFDGDHRVRORORFDOHGHUHDWHUUR

3.70
recobrimento
GLIHUHQoDGHQtYHOHQWUHDVXSHUItFLHGRWHUUHQRHDJHUDWUL]VXSHULRUH[WHUQDGDWXEXODomR

3.71
rede de distribuição de água
XQLGDGH GR VLVWHPD GH DEDVWHFLPHQWR FRQVWLWXtGD GH WXEXODo}HV FRPSRQHQWHV H HTXLSDPHQWRV
DFHVVyULRVGHVWLQDGDDGLVSRQLELOL]DUiJXDSRWiYHODRVFRQVXPLGRUHV

3.72
rede malhada
UHGHFRQVWLWXtGDSRUWXEXODo}HVLQWHUOLJDGDVHPFLUFXLWRVIHFKDGRV

3.73
rede mista
UHGHFRQVWLWXtGDSRUWUHFKRVFRPUHGHPDOKDGDHUDPL¿FDGD

3.74
UHGHUDPL¿FDGD
WXEXODomRSULQFLSDOTXHDOLPHQWDWXEXODo}HVVHFXQGiULDVQmRIRUPDQGRFLUFXLWRVIHFKDGRV

3.75
setor de abastecimento
SDUWHGRVLVWHPDTXHSRGHHQJOREDUUHVHUYDWyULRVHVWDo}HVHOHYDWyULDVUHGHVSULPiULDVVHFXQGiULDV
HDFHVVyULRVGLYLGLGDGHIRUPDDSHUPLWLUXPPHOKRUJHUHQFLDPHQWRGRVLVWHPD

3.76
setor de manobra
PHQRUVXEGLYLVmRGDUHGHGHGLVWULEXLomRFXMRÀX[RGDiJXDSRGHVHULVRODGRRXGLUHFLRQDGRSDUD
SHUPLWLUPDQXWHQo}HVHRXLQWHUYHQo}HVPDQWHQGRRDEDVWHFLPHQWRGRUHVWDQWHGDUHGH

3.77
setorização operacional
GLYLVmRGDUHGHGHGLVWULEXLomRHPVHWRUHVGHPHQRUGLPHQVmRFRQVLGHUDQGRDVFRQGLo}HVWRSROyJLFDV
HRSHUDFLRQDLVFRPRREMHWLYRGHRWLPL]DUDJHVWmRGRVLVWHPD

3.78
sistema de abastecimento de água
FRQMXQWR GH LQVWDODo}HV GHVWLQDGDV D FDSWDU WUDQVSRUWDU WUDWDU UHVHUYDU H GLVWULEXLU iJXD
FRPSUHHQGHQGRDVXQLGDGHVRSHUDFLRQDLVQHFHVViULDVDRDEDVWHFLPHQWR

3.79
sobrepressão
SUHVVmRPi[LPDSURYRFDGDSRURQGDVGHFXUWDGXUDomRGHFRUUHQWHVGHWUDQVLWyULRVKLGUiXOLFRV

8 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

3.80
VyOLGRVQmR¿OWUiYHLVVyOLGRVHPVXVSHQVmR
SDUFHOD GDV SDUWtFXODV VyOLGDV FRQWLGDV QD iJXD RX QR HVJRWR H TXH VmR UHWLGDV SHOR SURFHVVR
GH¿OWUDomRXWLOL]DQGRSDSHOGH¿OWURGHGLYHUVRVPDWHULDLV

3.81
subpressão
SUHVVmRPtQLPDSURYRFDGDSRURQGDVGHFXUWDGXUDomRGHFRUUHQWHVGHWUDQVLWyULRVKLGUiXOLFRV

3.82
teste de estanqueidade
WpFQLFDGHLQVSHomRQmRGHVWUXWLYDTXHSHUPLWHLGHQWL¿FDUPHGLUHORFDOL]DUYD]DPHQWRVGHXPÀXLGR
HPVLVWHPDVTXHRSHUDPFRPSUHVVmRSRVLWLYDRXLQ¿OWUDomRHPVLVWHPDVVRELQÀXrQFLDGHYiFXR

3.83
transitório hidráulico
HVFRDPHQWRQmRSHUPDQHQWHHPUHJLPHYDULDGRTXHRFRUUHHQWUHXPUHJLPHSHUPDQHQWHHRXWUR

3.84
unidade linear
FRQMXQWRGHWXEXODo}HVFRPSRQHQWHVHHTXLSDPHQWRVDFHVVyULRVGHVWLQDGRVDWUDQVSRUWDURÀXLGR
FRPRDGXWRUDUHGHGHGLVWULEXLomRUHGHFROHWRUDOLQKDGHUHFDOTXHLQWHUFHSWRUHVHPLVViULRV

3.85
unidade não linear
unidade localizada
FRQMXQWRFRPSRVWRGHLQVWDODo}HVHTXLSDPHQWRVHSHoDVHVSHFLDLVLPSODQWDGRHPSRQWRVHVWUDWpJLFRV
GR VLVWHPD HP iUHDV SUHYLDPHQWH GHOLPLWDGDV FRPR FDSWDomR HOHYDWyULD HVWDomR GH WUDWDPHQWR
UHVHUYDWyULR

3.86
unidade operacional
SDUWHGRVLVWHPDTXHWHPXPDIXQomRHVSHFt¿FDSRGHQGRVHUXPDXQLGDGHOLQHDURXQmROLQHDU

3.87
vazão
YROXPHGHXPÀXLGRSRUXQLGDGHGHWHPSR

3.88
YD]mRPpGLD
YROXPH GH XP ÀXLGR SRU XQLGDGH GH WHPSR DYDOLDGR SDUD FDGD HWDSD GR SODQR RX SURMHWR
GHVSUH]DQGRVHDYDULDELOLGDGHGLiULD N HKRUiULD N GRÀX[R

3.89
zona de pressão
iUHD DEUDQJLGD SHOD GLYLVmR GR VHWRU GH DEDVWHFLPHQWR QD TXDO DV SUHVV}HV HVWiWLFD H GLQkPLFD
REHGHFHPDRVOLPLWHVSUH¿[DGRV

© ABNT 2017 - Todos os direitos reservados 9


ABNT NBR 12218:2017

4 Requisitos gerais
4.1 Desenvolvimento do projeto

4.1.1 Elementos necessários para o desenvolvimento do projeto

௘D  FDUDFWHUL]DomRHGHOLPLWDomRGDiUHDGHHVWXGR

௘E  HOHPHQWRVWRSRJUi¿FRVGLVSRQtYHLVRXDVHUHPHODERUDGRVGHDFRUGRFRPDV1RUPDV%UDVLOHLUDV
HPYLJrQFLD

௘F  FDGDVWURGDVUHGHVGHGLVWULEXLomRGHiJXDHGDVLQWHUIHUrQFLDV

௘G  LQIRUPDo}HVJHRWpFQLFDVHJHROyJLFDV

4.1.2 Elementos a considerar no desenvolvimento do projeto

௘D  GDGRVGRVLVWHPDGHDEDVWHFLPHQWRGHiJXDH[LVWHQWH

௘E  HVWXGRVSODQHMDPHQWRVHSURMHWRVH[LVWHQWHVFRUUHODFLRQDGRV

௘F  HVWXGRGHFRQFHSomRGRVLVWHPDGHDEDVWHFLPHQWRHODERUDGRFRQIRUPHD$%171%5

௘G  SODQRVGLUHWRUHVGRVLVWHPDGHDEDVWHFLPHQWRGHiJXDHGHPDLVSODQRVGLUHWRUHV

௘H  SODQRGHXUEDQL]DomRHOHJLVODomRUHODWLYDDRXVRHRFXSDomRGRVROR

௘I  SODQRGHVDQHDPHQWREiVLFR

௘J  OHYDQWDPHQWRSODQLDOWLPpWULFRGDiUHDGRSURMHWRFRPGHWDOKHVGRDUUXDPHQWRWLSRGHSDYLPHQWR
REUDVHVSHFLDLVLQGLFDomRGDVLQWHUIHUrQFLDV

௘K  SURJUDPDGHFRQWUROHHUHGXomRGHSHUGDV

௘L  FRQGLo}HVPtQLPDVGHVHJXUDQoDHPHGLFLQDGRWUDEDOKRFRQIRUPHOHJLVODomRYLJHQWH

௘M  OHJLVODo}HVSHUWLQHQWHVYLJHQWHV

௘N  FULWpULRVSURFHGLPHQWRVHGLUHWUL]HVGDRSHUDGRUDGRVLVWHPDGHDEDVWHFLPHQWRGHiJXD

4.1.3 Atividades necessárias ao desenvolvimento do projeto

௘D  GHOLPLWDUDiUHDWRWDODVHUDEDVWHFLGD

௘E  LGHQWL¿FDUSDUDRVLVWHPD±JUDQGHVFRQVXPLGRUHVFRQVXPLGRUHVHVSHFLDLViUHDVGHH[SDQVmR
SUHYHQomRHFRPEDWHDLQFrQGLRSRSXODomRÀXWXDQWH

௘F  GH¿QLUDVGHPDQGDVSDUDRGLPHQVLRQDPHQWRGDUHGH

௘G  DQDOLVDUWpFQLFDHHFRQRPLFDPHQWHR V SRQWR V GHDOLPHQWDomRSDUDDUHGHSURMHWDGD

௘H  DQDOLVDUDVLQVWDODo}HVGRVLVWHPDGHGLVWULEXLomRH[LVWHQWHVREMHWLYDQGRVHXDSURYHLWDPHQWR

௘I  GHOLPLWDUDVHWRUL]DomRRSHUDFLRQDO

— GHOLPLWDUDiUHDGHLQÀXrQFLDGRVUHVHUYDWyULRVGDV]RQDVGHSUHVVmR

10 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

— SURMHWDURVGLVWULWRVGHPHGLomRHFRQWUROHGDUHGH '0& DGHVHQYROYHUFRQIRUPHFULWpULRV


GRUHVSRQViYHOSHORVLVWHPDGHDEDVWHFLPHQWRGHiJXDQDIDOWDGHQRUPDHVSHFt¿FD

— GHOLPLWDU RV VHWRUHV GH PDQREUD FRP ORFDOL]DomR H GLPHQVLRQDPHQWR GRV HTXLSDPHQWRV
DFHVVyULRVGDUHGH KLGUDQWHVYHQWRVDVUHJLVWURVGHPDQREUDGHVFDUJD 

௘J  GH¿QLUHWUDoDURVFRQGXWRVSULQFLSDLVHVHFXQGiULRVOHYDQGRVHHPFRQVLGHUDomRDVHWRUL]DomR
RSHUDFLRQDORVLVWHPDH[LVWHQWHDVDPSOLDo}HVDVLPSODQWDo}HVHPIXQomRGDVYD]}HVPi[LPDV
HPtQLPDVHGRKRUL]RQWHGRHVWXGRRXGRSURMHWR

௘K  UHDOL]DUVLPXODo}HVKLGUiXOLFDVFRQVLGHUDQGRRVSULQFLSDLVFHQiULRVFRPFDOLEUDomRHYDOLGDomR
GRVLVWHPDH[LVWHQWHHGRVLVWHPDSURSRVWR2VUHVXOWDGRVGDVVLPXODo}HVKLGUiXOLFDVGHYHP
DSUHVHQWDU DV FDUDFWHUtVWLFDV RSHUDFLRQDLV GH WRGDV DV XQLGDGHV QHFHVViULDV GR VLVWHPD
GLVWULEXLGRU WXEXODomRHOHYDWyULDboosterYiOYXODUHGXWRUDGHSUHVVmR 

௘L  UHDOL]DUHVWXGRGHWUDQVLHQWHVKLGUiXOLFRVTXDQGRDSOLFiYHO

௘M  GLPHQVLRQDUFRQGXWRVHGH¿QLURVWLSRVGHPDWHULDLVDGHTXDGRV

௘N  GLPHQVLRQDU GLVSRVLWLYRV GH SURWHomR KLGUiXOLFD GD UHGH SDUD DV RSHUDo}HV GH HQFKLPHQWRV
e esvaziamentos;

௘O  DYDOLDURVWHPSRVGHIHFKDPHQWRHDEHUWXUDGHYiOYXODVGRVSULQFLSDLVFRQGXWRVGLVWULEXLGRUHV

௘P  DYDOLDUDUHVLVWrQFLDPHFkQLFDGDVSDUWHVFRPSRQHQWHVGRVLVWHPDGLVWULEXLGRUjVDo}HVLQWHUQDV
HH[WHUQDVDWXDQWHVTXDQGRQHFHVViULR

௘Q  DYDOLDU D SURWHomR GDV SDUWHV FRPSRQHQWHV GR VLVWHPD GLVWULEXLGRU jV Do}HV GH SURFHVVR
FRUURVLYRDJUHVVLYLGDGHGRPHLRjWXEXODomRGHGHWHULRUDomRPHFkQLFDHGHDWDTXHTXtPLFR
quando necessário;

௘R  GHWDOKDUDVHWDSDVGHLPSODQWDomR

௘S  GHWDOKDUDLQWHUGHSHQGrQFLDGDVDWLYLGDGHVHRSODQRGHH[HFXomRGDVREUDV2WLPL]DURWHPSR
GHSDUDOLVDomRGRVLVWHPD

௘T  SUHYHU D LPSODQWDomR GH GLVSRVLWLYRV TXH SHUPLWDP RV SURFHGLPHQWRV GH GHVLQIHFomR GD UHGH
HRQGHQHFHVViULRGHFRUUHomRGDFRQFHQWUDomRGHFORURUHVLGXDO

௘U  FRPSDWLELOL]DURSURMHWRGDVXQLGDGHVGDUHGHFRPRVGHPDLVSURMHWRVFRPSOHPHQWDUHV HVWUXWXUDLV
HOpWULFRVHOHWURPHFkQLFRVDXWRPDomRHWF 

4.1.4 Elementos que devem compor o projeto

4.1.4.1 0HPRULDO GHVFULWLYR H MXVWL¿FDWLYR FRQWHQGR RV HVWXGRV FiOFXORV UHDOL]DGRV VLPXODo}HV
KLGUiXOLFDV

4.1.4.2 3HoDV JUi¿FDV GR SURMHWR HP HVFDODV DGHTXDGDV DWHQGHQGR jV 1RUPDV %UDVLOHLUDV HP
YLJrQFLDHjVUHFRPHQGDo}HVHSDGURQL]Do}HVGDRSHUDGRUDGHYHPDSUHVHQWDU

௘D  RVGHWDOKDPHQWRVGDVLQWHUIHUrQFLDVFRPRXWURVVLVWHPDVHLQIUDHVWUXWXUDVH[LVWHQWHVHSODQHMDGDV
DV LQWHUOLJDo}HV FRPSOH[DV DV WUDYHVVLDV  1DV SHoDV JUi¿FDV GHYHP HVWDU UHSUHVHQWDGDV
D LQWHJUDomR GD VROXomR KLGUiXOLFD SURMHWDGD H D IRUPD H[HFXWLYD GHVWDV LPSOHPHQWDo}HV
em campo;

© ABNT 2017 - Todos os direitos reservados 11


ABNT NBR 12218:2017

௘E  RFDUUHJDPHQWRGRVQyVSODQWDJHUDOFRPWUDoDGRGRVDQpLVSULQFLSDLVHXQLGDGHVORFDOL]DGDV
GHOLPLWDomRGRVGLVWULWRVGHPHGLomRHFRQWUROH '0& GHOLPLWDomRGRVVHWRUHVGHPDQREUD 60 
UHGHGHGLVWULEXLomRH[LVWHQWHUHGHGHGLVWULEXLomRSURMHWDGDHGHPDLVGHWDOKDPHQWRVQHFHVViULRV

4.1.4.3 5HODomRGHPDWHULDLVHHTXLSDPHQWRV

4.1.4.4 5HODomRGRVVHUYLoRV

4.1.4.5 (VSHFL¿FDo}HVWpFQLFDVGHVHUYLoRVPDWHULDLVHHTXLSDPHQWRV

4.1.4.6 2UoDPHQWRGHWDOKDGRGDVREUDVFRQIRUPHHWDSDVGH¿QLGDVjLPSODQWDomR

4.1.4.7 /HYDQWDPHQWRVWRSRJUi¿FRV

4.1.4.8 5HVXOWDGRVGRVHVWXGRVJHRWpFQLFRVTXDQGRQHFHVViULRV

4.1.4.9 5HVXOWDGRVGRVGHPDLVHVWXGRVUHDOL]DGRV

4.1.4.10 5HVXOWDGRVGDVDQiOLVHVDRDWHQGLPHQWRjOHJLVODomRSHUWLQHQWH

4.1.4.11 3ODQRGHRSHUDomRHFRQWUROHTXDQGRDSOLFiYHO

5 5HTXLVLWRVHVSHFt¿FRV

5.1 Área a ser abastecida

5.1.1 'HYHPVHUYHUL¿FDGDVDViUHDVFRQVLGHUDQGRDVGLIHUHQWHVRFXSDo}HVGHVRORUHVLGHQFLDO
FRPHUFLDOS~EOLFDLQGXVWULDOHVSHFLDO

5.1.2 'HYHP VHU YHUL¿FDGDV DV iUHDV GR SHUtPHWUR XUEDQR DWXDO H GH H[SDQVmR GH DFRUGR FRP
RXVRHDRFXSDomRGRVRORGH¿QLGRVHPOHJLVODomRHPYLJRU

5.2 9D]}HVSDUDGLPHQVLRQDPHQWR

5.2.1 $VYD]}HVSDUDGLPHQVLRQDPHQWRGHYHPDWHQGHUDWRGDDiUHDDVHUDEDVWHFLGD

5.2.2 2 KRUL]RQWH GR HVWXGR RX GR SURMHWR GHYH VHU GH¿QLGR SRU FULWpULR WpFQLFR GD RSHUDGRUD
UHVSRQViYHOSHORVLVWHPDGHDEDVWHFLPHQWRGHiJXD

5.2.3 'HYHP VHU FRQVLGHUDGDV DV YD]}HV SDUD DWHQGHU D JUDQGHV FRQVXPLGRUHV FRQVXPLGRUHV
HVSHFLDLViUHDVGHH[SDQVmRSUHYHQomRFRQWUDLQFrQGLRSRSXODomRÀXWXDQWH

5.2.4 2 tQGLFH GH SHUGD WRWDO UHDO H DSDUHQWH  GHYH VHU FRQVLGHUDGR QD YD]mR OHYDQGR
HP FRQVLGHUDomR DV PHWDV UHVXOWDQWHV GDV Do}HV H SODQRV GH FRQWUROH H UHGXomR GH SHUGDV
GDRSHUDGRUDGRVLVWHPDGHDEDVWHFLPHQWRHVXDHYROXomRQRKRUL]RQWHGRHVWXGRRXGRSURMHWR

12 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

5.2.5 'HYHVHUDGRWDGDDYD]mRPi[LPDKRUiULDGHKRUL]RQWHGHSURMHWRHPFDGDHWDSDGH¿QLGD
FRQIRUPHFULWpULRWpFQLFRGDRSHUDGRUDUHVSRQViYHOSHORVLVWHPDGHDEDVWHFLPHQWRGHiJXD

5.2.6 $SOLFDURFRH¿FLHQWHNSDUDDYHUL¿FDomRGDSUHVVmRPi[LPDQRWXUQD

5.2.7 2V FRH¿FLHQWHV N N N GHYHP VHU REWLGRV D SDUWLU GRV GDGRV H[LVWHQWHV QD ORFDOLGDGH
4XDQGRGDLQH[LVWrQFLDGHKLVWyULFRDGRWDURVYDORUHVHUHVSHFWLYDPHQWH

5.3 Pressão de serviço


5.3.1 $SUHVVmRHVWiWLFDPi[LPDQDVWXEXODo}HVGLVWULEXLGRUDVGHYHVHUGHN3DSRGHQGRFKHJDU
DN3DHPUHJL}HVFRPWRSRJUD¿DDFLGHQWDGDHDSUHVVmRGLQkPLFDPtQLPDGHN3DHVHU
UHIHUHQFLDGDDRQtYHOGRWHUUHQR
127$ 6HPSUH TXH SRVVtYHO DGRWDU DV SUHVV}HV HVWiWLFDV HQWUH  N3D H  N3D FRP R REMHWLYR
de diminuir perdas reais.

127$ 1RVFDVRVHPTXHDGLIHUHQoDHQWUHDVSUHVV}HVHVWiWLFDVPi[LPDVHGLQkPLFDVPtQLPDVIRUHP
VLJQL¿FDWLYDVDGRWDUGLVSRVLWLYRVGHFRQWUROHGRWDGRVGHDMXVWHDXWRPiWLFRGHSUHVVmRHPIXQomRGDYDULDomR
de consumo diurno e noturno.

5.3.1.1 2VYDORUHVGHSURMHWRGDSUHVVmRHVWiWLFDVXSHULRUHVjPi[LPDHRVGDSUHVVmRGLQkPLFD
LQIHULRUHVjPtQLPDSRGHPVHUDFHLWRVGHVGHTXHMXVWL¿FDGRVWpFQLFDHRXHFRQRPLFDPHQWH'HYHVHU
YHUL¿FDGRVHHVWDSUHVVmRpVXSRUWDGDSRUWRGRVRVFRPSRQHQWHVGRVLVWHPD

5.3.1.2 1DV WXEXODo}HV VXMHLWDV D WUDQVLHQWHV KLGUiXOLFRV VLJQL¿FDWLYRV GHYHP VHU DYDOLDGDV
DVSUHVV}HVPi[LPDVHPtQLPDVGHVHUYLoRSUHYHQGRGLVSRVLWLYRVGHSURWHomRDRVLVWHPDHOLPLQDQGR
SUHVV}HVQHJDWLYDVFRQWDPLQDomRGDUHGHHRXULVFRGHFRODSVR

5.3.2 7UHFKRVGHFRQGXWRVSULQFLSDLVTXHQmRDEDVWHFHPFRQVXPLGRUHVRXWXEXODo}HVVHFXQGiULDV
QmRHVWmRVXMHLWRVDRVOLPLWHVGHSUHVVmRHVWDEHOHFLGRVHPPDVGHYHPVHUYHUL¿FDGRVTXDQWR
jHVWDELOLGDGHHVWUXWXUDOHjVHJXUDQoDVDQLWiULD

5.4 Rede de distribuição de água existente


5.4.1 $YDOLDUDVLQVWDODo}HVGRVLVWHPDGHGLVWULEXLomRH[LVWHQWHVREMHWLYDQGRVHXDSURYHLWDPHQWR
WRWDORXSDUFLDO

5.4.2 1DHODERUDomRGHQRYRVHVWXGRVHSURMHWRVDVSDUWHVDSURYHLWiYHLVGDUHGHH[LVWHQWHGHYHP
VDWLVID]HUDVFRQGLo}HVGHVWD1RUPDRXDGDSWDUVHDHODPHGLDQWHDOWHUDo}HVRXFRPSOHPHQWDo}HV
HGHYHVHUDQDOLVDGRRLPSDFWRGRVLVWHPDGHGLVWULEXLomRSURMHWDGRVREUHDVLQVWDODo}HVH[LVWHQWHV

5.5 7UDoDGRGDVWXEXODo}HV
5.5.1 (PiUHDVXUEDQDVDVWXEXODo}HVGHYHPVHUORFDOL]DGDVSUHIHUHQFLDOPHQWHHPiUHDVRXYLDV
S~EOLFDVHPSDVVHLRVIRUPDQGRFLUFXLWRVIHFKDGRVHYLWDQGRSRQWDVGHUHGHHiJXDHVWDJQDGD

5.5.2 $R ORQJR GDV WXEXODo}HV SULQFLSDLV LQGHSHQGHQWHPHQWH GRV VHXV GLkPHWURV GHYHP VHU
SUHYLVWDVWXEXODo}HVVHFXQGiULDVGHGLVWULEXLomRSDUDDWHQGHUDVOLJDo}HVSUHGLDLVQRWUHFKR([FHomR
SRGHVHUDFHLWDGHVGHTXHWpFQLFDHHFRQRPLFDPHQWHMXVWL¿FDGDV

5.5.3 1D FRQFHSomR GR WUDoDGR GD UHGH GHYHP VHU UHVSHLWDGDV DV FDUDFWHUtVWLFDV WpFQLFDV GRV
PDWHULDLVDSOLFDGRVSDUDHYLWDUHVIRUoRVHDVVHJXUDUDHVWDQTXHLGDGH

5.5.4 $UHGHSRGHVHUGXSODQRVVHJXLQWHVFDVRV

௘D  TXDQGR R HVWXGR WpFQLFR FRQVLGHUDQGR DVSHFWRV GD RSHUDomR PDQXWHQomR H HFRQ{PLFRV


GHPRQVWUDUTXHHVWDVHMDDVROXomRPDLVLQGLFDGD

© ABNT 2017 - Todos os direitos reservados 13


ABNT NBR 12218:2017

D  TXDQGRDVFDUDFWHUtVWLFDVJHRPpWULFDVHRSHUDFLRQDLVGDVYLDVH[LJLUHP

E  TXDQGR QRV PXQLFtSLRV KRXYHU H[LJrQFLD QD OHJLVODomR HRX D FULWpULR WpFQLFR GD RSHUDGRUD
UHVSRQViYHOSHORVLVWHPDGHDEDVWHFLPHQWRGHiJXD

5.6 Dimensionamento

5.6.1 2SURMHWRGHYHGH¿QLUDSUHVVmRGHVHUYLoRDVSUHVV}HVGHFRUUHQWHVGRVWUDQVLHQWHVKLGUiXOLFRV
R GLkPHWUR LQWHUQR DV YHORFLGDGHV DYDOLDomR GDV SHUGDV GH FDUJD HVWDEHOHFHQGR DV FRQGLo}HV
KLGUiXOLFDVGHIXQFLRQDPHQWRGDWXEXODomR

5.6.2 2GLkPHWURQRPLQDOPtQLPRGRVFRQGXWRVVHFXQGiULRVpGHPP([FHomRSRGHVHUDFHLWD
GHVGHTXHWHFQLFDPHQWHMXVWL¿FDGD

5.6.3 3DUDRGLPHQVLRQDPHQWRKLGUiXOLFRGDVWXEXODo}HVGHYHVHUFRQVLGHUDGRSDUDRKRUL]RQWH
GH SURMHWR R FRH¿FLHQWH GH +D]HQ :LOOLDPV RX HTXLYDOHQWH GD HTXDomR XQLYHUVDO H WDPEpP
RHQYHOKHFLPHQWRLQFUXVWDomRHGHSRVLomRQDVSDUHGHVGDWXEXODomR2VFRH¿FLHQWHVGHYHPVHU
OHYDQWDGRV HP FDPSR RX QD LPSRVVLELOLGDGH GD UHDOL]DomR GDV DYDOLDo}HV HP FDPSR GHYHPVH
DGRWDUYDORUHVH[SOLFLWDGRVQDWHRULDGRVPDQXDLVGHKLGUiXOLFD

5.6.4 $V YHORFLGDGHV Pi[LPDV GH GLPHQVLRQDPHQWR GHYHP FRUUHVSRQGHU D XPD SHUGD GH FDUJD
GHDWpPNP'HYHPVHUHYLWDGDVYHORFLGDGHVPtQLPDVLQIHULRUHVDPV([FHomRSRGHVHU
DFHLWDGHVGHTXHWHFQLFDPHQWHMXVWL¿FDGD

5.6.5 $YHORFLGDGHDGPLWLGDSDUDDIDVHGHHQFKLPHQWRGDWXEXODomRGHYHVHUGDRUGHPGHPV

5.6.6 2 GLPHQVLRQDPHQWR H D DQiOLVH GR IXQFLRQDPHQWR JOREDO GR VLVWHPD KLGUiXOLFR GHYHP
VHU UHDOL]DGRV SRU VLPXODo}HV KLGUiXOLFDV TXH JDUDQWDP UHVLGXDLV Pi[LPRV GH YD]mR H GH FDUJD
SLH]RPpWULFDGH/VHN3DUHVSHFWLYDPHQWH

5.6.7 $VLPXODomRKLGUiXOLFDGRVLVWHPDGHYHLQFOXLURHVWXGRGDVFRQGLo}HVRSHUDFLRQDLVGDUHGH
H[LVWHQWHGDUHGHSURMHWDGDHVXDLQÀXrQFLDQDUHGHH[LVWHQWHjTXDOpLQWHUOLJDGD

127$ 6RPHQWH p GLVSHQVDGD D VLPXODomR KLGUiXOLFD GR VLVWHPD H[LVWHQWH VH WHFQLFDPHQWH MXVWL¿FDGD
HDFHLWDSHODRSHUDGRUD

5.6.8 3DUD DEDVWHFLPHQWR GR VLVWHPD GH SURWHomR FRQWUD LQFrQGLR SRU PHLR GH KLGUDQWH XUEDQR
63&,+8GHYHVHH[HFXWDUVLPXODomRKLGUiXOLFDGDUHGH

5.6.8.1 6LPXODU D RSHUDomR GR V  KLGUDQWH V  SRVVLELOLWDQGR FODVVL¿FiOR V  FRQIRUPH FULWpULRV


HVWDEHOHFLGRVQD7DEHODHRULHQWDomRGDRSHUDGRUD

5.6.8.2 5HFRPHQGDVH QD VLPXODomR SDUD DYDOLDomR GD FDSDFLGDGH GRV KLGUDQWHV D DSOLFDomR
GDGHPDQGDPi[LPDKRUiULDQDUHGHGHGLVWULEXLomR

5.6.9 2GLPHQVLRQDPHQWRGRVFRQGXWRVSULQFLSDLVSRGHVHUIHLWRVXSRQGRFRQVXPRVFRQFHQWUDGRV
QRVSRQWRVQRGDLVHHPSRQWRVVLQJXODUHVLQWHUPHGLiULRVTXHUHSUHVHQWHPRFRQVXPRGLVWULEXtGRDR
ORQJRGRVLVWHPD

5.6.10 2VJUDQGHVFRQVXPLGRUHVHFRQVXPLGRUHVHVSHFLDLVGHYHPWHUVXDVYD]}HVDVVRFLDGDVDRV
pontos nodais.

14 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

5.7 Zona de pressão

5.7.1 2VLVWHPDGLVWULEXLGRUSRGHVHUGLYLGLGRHPiUHDVPHQRUHVGHIRUPDDJDUDQWLUTXHDVSUHVV}HV
HVWiWLFDHGLQkPLFDREHGHoDPDRVOLPLWHVSUH¿[DGRVQHVWD1RUPD

5.7.2 $GHOLPLWDomRGDV]RQDVGHSUHVVmRGHYHFRQVLGHUDURWUDoDGRXUEDQRDVEDUUHLUDVQDWXUDLV
DVFRQGLo}HVWRSROyJLFDVHRSHUDFLRQDLVGDUHGH

5.8 Distrito de medição e controle (DMC)

5.8.1 'HYHVHLQFRUSRUDUQDFRQFHSomRGDUHGHGHGLVWULEXLomRDGHOLPLWDomRGHGLVWULWRVGHPHGLomR
HFRQWUROHFRQVLGHUDQGRDVFRQGLo}HVWRSROyJLFDVHRSHUDFLRQDLVGDUHGHHRVFULWpULRVHVWDEHOHFLGRV
SHODRSHUDGRUD

5.8.2 5HFRPHQGDVHR'0&DEUDQMDXPDiUHDTXHDSUHVHQWHXPDGDVFDUDFWHUtVWLFDVDEDL[RFRP
RREMHWLYRGHSURSRUFLRQDUFRQWUROHHH¿FLrQFLD

௘D  Pi[LPROLJDo}HV

௘E  H[WHQVmRPi[LPDGHNPGHUHGHQR'0&

127$ ÈUHDFRPFDUDFWHUtVWLFDVGLIHUHQWHVVRPHQWHpDFHLWDSHODRSHUDGRUDVHMXVWL¿FDGDWHFQLFDPHQWH

5.8.3 $V GLPHQV}HV PtQLPDV GH XP '0& GHYHP OHYDU HP FRQVLGHUDomR D YLDELOLGDGH WpFQLFD
HFRQ{PLFD¿QDQFHLUDEHPFRPRDVFDUDFWHUtVWLFDVORFDLV

5.8.4 2 SURFHVVR GH GHOLPLWDomR GR '0& GHYH PLQLPL]DU R FXVWR GH LQVWDODomR H PDQXWHQomR
GRVLVWHPDSURFXUDQGRVHJXLUDWRSRORJLDQDWXUDODVIURQWHLUDVKLGUiXOLFDVGDUHGHHWHUFRPREDVH
DV]RQDVGHSUHVVmRHRXWURVVXEVLVWHPDVMiH[LVWHQWHV

5.8.5 3DUDDLPSODQWDomRGR'0&UHFRPHQGDVHRVHFFLRQDPHQWRGDVUHGHVOLPtWURIHVHYLWDQGRVH
DRPi[LPRPDQWHURXLQVWDODUYiOYXODVGHIHFKDPHQWR

5.8.6 $DOLPHQWDomRGR'0&GHYHVHUIHLWDSHORPHQRUQ~PHURGHSRQWRVSRVVtYHO

5.8.7 2 '0& GHYH VHU HTXLSDGR FRP PHGLGRUHV GH YD]mR HP WRGDV DV HQWUDGDV H VDtGDV
HPHGLGRUHVGHSUHVVmRQRVSRQWRVFUtWLFRVGDUHGHTXHSRGHPWHUSUHYLVmRGHLQVWDODomRSHUPDQHQWH
RXGLVSRVLWLYRSDUDVXDLQVHUomRTXDQGRGDUHDOL]DomRGHFROHWDGHGDGRVRSHUDFLRQDLV

5.8.8 2'0&GHYHVHUVXEGLYLGLGRHPVHWRUHVGHPDQREUD

5.9 Setor de manobra (SM)

5.9.1 'HYHVHLQFRUSRUDUQDFRQFHSomRGDUHGHGHGLVWULEXLomRDGHOLPLWDomRGHVHWRUHVGHPDQREUD
FRQVLGHUDQGR DV FRQGLo}HV WRSROyJLFDV H RSHUDFLRQDLV GD UHGH H RV FULWpULRV HVWDEHOHFLGRV SHOD
operadora.

5.9.2 'HYHVHURSHUDGRGHIRUPDDJDUDQWLURDEDVWHFLPHQWRGRUHVWDQWHGDUHGHFRPDVYD]}HV
SUHYLVWDVHGHQWURGRVOLPLWHVGHSUHVVmRHVSHFL¿FDGRVQHVWD1RUPD

5.9.3 'HYH WHU D VXD HVWDQTXHLGDGH JDUDQWLGD SHOR IHFKDPHQWR GR PHQRU Q~PHUR SRVVtYHO
GHYiOYXODV

© ABNT 2017 - Todos os direitos reservados 15


ABNT NBR 12218:2017

5.9.4 5HFRPHQGDVHTXHR60DEUDQMDXPDiUHDTXHDSUHVHQWHXPDGDVFDUDFWHUtVWLFDVDEDL[R

௘D  Pi[LPRGHOLJDo}HV

௘E  H[WHQVmRPi[LPDGDUHGHGR60LJXDODNP

127$ ÈUHDFRPFDUDFWHUtVWLFDVGLIHUHQWHVVRPHQWHpDFHLWDSHODRSHUDGRUDVHMXVWL¿FDGDWHFQLFDPHQWH

5.9.5 260GHYHVHUGRWDGRGRVVHJXLQWHVHTXLSDPHQWRV

௘D  YiOYXODGHPDQREUDSDUDLVRODPHQWRGRVHWRUHRXGLUHFLRQDPHQWRGRÀX[R

௘E  YiOYXOD GH GHVFDUJD SDUD R HVJRWDPHQWR GH iJXD GR VHWRU GH WDO IRUPD TXH VHMD GHVFDUWDGD
VRPHQWHDiJXDPtQLPDQHFHVViULDSDUDDH[HFXomRGRVVHUYLoRVGHPDQXWHQomRHRXOLPSH]D
da rede;

௘F  YHQWRVDSDUDSURWHomRGRVLVWHPDTXHSHUPLWDHOLPLQDURXDGPLWLUDUQDWXEXODomRDX[LOLDQGRQDV
RSHUDo}HVGHHVYD]LDPHQWRHRXGHHQFKLPHQWRGDVUHGHVTXHFRPS}HPRVHWRU

5.10 Sistema de proteção contra incêndio por meio de hidrante urbano – SPCIHU

5.10.1 $RSHUDGRUDGHYHGH¿QLURVSRQWRVGHLQVWDODomRGHKLGUDQWHXUEDQRSDUDFRPEDWHDLQFrQGLR
FRQVLGHUDUDFDSDFLGDGHGDUHGHGHGLVWULEXLomRSDUDDUHJLmRHVSHFt¿FDGHDFRUGRFRPDV7DEHODV
H&RQVXOWDURFRUSRGHERPEHLURVQDIDVHGHFRQFHSomRGDUHGHRXQDDPSOLDomRHUHPDQHMDPHQWR
GHKLGUDQWHV

Tabela 1 – Tabela de distribuição de hidrantes na rede de distribuição de água


População 5DLRGLVWkQFLD Ocupação predominante
8QLIDPLOLDUDGHQVDGDFRPHUFLDO
PLO 3RQWR V QRVLVWHPDGH
SDWULP{QLRS~EOLFRiUHDV
KDELWDQWHV DEDVWHFLPHQWRGHiJXD
KRUL]RQWDOL]DGDV
8QLIDPLOLDUDGHQVDGDFRPHUFLDO
PP SDWULP{QLRS~EOLFRiUHDV
!PLO KRUL]RQWDOL]DGDV
KDELWDQWHV 9HUWLFDOL]DomRDGHQVDGDiUHDGH
PP EDL[DPRELOLGDGH WUkQVLWRLQWHQVRYLDV
HVWUHLWDVGL¿FXOGDGHGHGHVORFDPHQWR
+RVSLWDOSUHVtGLRshoppingiUHDFRP
2FXSDo}HV
PP DOWRDGHQVDPHQWRYHUWLFDOHVFROD
especiais
PXVHXGHSyVLWR
6HWRULQGXVWULDO $VHUGH¿QLGRFRQIRUPH ÈUHDFRPRFXSDomRLQGXVWULDO

16 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

Tabela 2 – 7DEHODGHFODVVL¿FDomRGHKLGUDQWHV
DN 3UHVVmR'LQkPLFDQD
Vazão Cor de
Categoria RDA RDA
LGHQWL¿FDomR
/PLQ /V mm kPa
A > 2 000 > 33 • • Verde
> 1 000 e > 16 a
B > 150 • $PDUHOD
< 2 000 33
>6a
& 360 a 1 000 ” • 9HUPHOKD
16
' < 360 <6 ” • $]XO
5'$5HGHGHGLVWULEXLomRGHiJXD
'1'LkPHWURQRPLQDO

5.10.2 (P FRPXQLGDGHV FRP GHPDQGD WRWDO LQIHULRU D  /V RX SRSXODomR HTXLYDOHQWH D
KDELWDQWHVLQVWDODUKLGUDQWH V HPSRQWR V GRVLVWHPDGHDEDVWHFLPHQWRGHiJXDTXHWHQKDP
FRQGLo}HVWpFQLFDVLQFOXVLYHDFHVVRSDUDDOLPHQWDUYLDWXUDV FDUURVSLSD SDUDFRPEDWHDLQFrQGLR
$iJXDQmRSUHFLVDQHFHVVDULDPHQWHVHUSRWiYHO

5.10.3 $GLVWkQFLDHQWUHKLGUDQWHVGHYHDWHQGHUDRVUHTXLVLWRVHVWDEHOHFLGRVQDWDEHODGHGLVWULEXLomR
GHKLGUDQWHV YHU7DEHOD 

5.10.3.1 $GLVWULEXLomRGHKLGUDQWHVGHYHDWHQGHUDRVUHTXLVLWRVHVWDEHOHFLGRVQDWDEHODGHGLVWULEXLomR
GHKLGUDQWHV YHU7DEHOD &RQVLGHUDUDPRELOLGDGHHDWRSRJUD¿DUHOHYRGDUHJLmRDFDSDFLGDGH
HSUHVVmRGLQkPLFDGDUHGHRSODQRGHXUEDQL]DomRDOHJLVODomRUHODWLYDDRXVRHRFXSDomRGRVROR
DLGHQWL¿FDomRGRWLSRGHRFXSDomRGDUHJLmR

5.10.3.2 1DVHOHomRGRVORFDLVSDUDLQVWDODomRGHKLGUDQWHGDUSUHIHUrQFLDDRVSRQWRVTXHSHUPLWDP
PHOKRU DFHVVR SDUD DV YLDWXUDV GR FRUSR GH ERPEHLURV DWHQGHQGR jV RULHQWDo}HV GR FRQVHOKR
QDFLRQDOGHWUkQVLWRHRXGRUHVSRQViYHOSHORWUkQVLWRORFDO

5.10.4 2VKLGUDQWHVSRGHPVHUGHFROXQDRXVXEWHUUkQHR

5.10.5 (P TXDOTXHU LQWHUYHQomR QD UHGH GH GLVWULEXLomR H[LVWHQWH R 6&3,+8 GHYH VHU UHDYDOLDGR
H DGHTXDGR GH DFRUGR FRP DV FRQGLo}HV HVWDEHOHFLGDV QHVWD 1RUPD FRQVLGHUDQGR RV FULWpULRV
HRULHQWDo}HVGDRSHUDGRUD

5.10.6 1DLQVWDODomRGHKLGUDQWHGHFROXQDGHYHVHDWHQGHUjVOHLVTXHSRVVLELOLWHPDDFHVVLELOLGDGH

5.10.7 ,QGLFDUQRSURMHWRDFODVVL¿FDomRGRKLGUDQWHXUEDQRSRUFRUGHLGHQWL¿FDomRFRQIRUPHWDEHOD
GHFODVVL¿FDomRGHKLGUDQWHV 7DEHOD $SLQWXUDGHLGHQWL¿FDomRGHYHVHUIHLWDQRVWDPS}HVODWHUDLV
HQRWRSRSDUDRVKLGUDQWHVGHFROXQDHQDWDPSDGDFDL[DGHSURWHomRSDUDKLGUDQWHVXEWHUUkQHR

5.10.8 9LDWXUDVGRFRUSRGHERPEHLURVHTXLSDGDVFRPPDQJXHLUDVGHVXFomR PDQJRWH QmRSRGHP


ID]HU VXFomR HP KLGUDQWHV S~EOLFRV SDUD HYLWDU R FRODSVR GD UHGH H D FRQWDPLQDomR GR VLVWHPD
GHGLVWULEXLomRGHiJXD

© ABNT 2017 - Todos os direitos reservados 17


ABNT NBR 12218:2017

5.11 Componentes da rede e equipamentos acessórios

5.11.1 Válvula de manobra

5.11.1.1 1D WXEXODomR SULQFLSDO GHYH VHU SUHYLVWD YiOYXOD GH PDQREUD TXH SHUPLWD D RSHUDomR
GDWXEXODomRHPVXEWUHFKRVFRQIRUPHQHFHVVLGDGHRSHUDFLRQDO

5.11.1.2 1DWXEXODomRVHFXQGiULDGHYHVHUSUHYLVWDYiOYXODGHPDQREUDMXQWRDRSRQWRGHOLJDomR
jWXEXODomRSULQFLSDOHHPSRQWRVLGHQWL¿FDGRVFRPRQHFHVViULRV

5.11.1.3 'HYH VHU DYDOLDGD D RFRUUrQFLD GH WUDQVLHQWHV KLGUiXOLFRV GHFRUUHQWHV GH DEHUWXUD
H IHFKDPHQWR HP YiOYXOD GH UHOHYkQFLD SDUD R IXQFLRQDPHQWR GD UHGH H GHYHP VHU DGRWDGDV
DVPHGLGDVGHSURWHomR

5.11.2 Válvula de descarga

5.11.2.1 'HYHVHUSUHYLVWDYiOYXODGHGHVFDUJDQRVSRQWRVEDL[RVRXHPSRQWRVHVWUDWpJLFRVGDUHGH
FRP LQGLFDomR HP SURMHWR GR SRQWR GH ODQoDPHQWR GD iJXD GD GHVFDUJD TXH GHYH VHU FRQGX]LGD
D ORFDO DGHTXDGR  3DUD R SRQWR GH ODQoDPHQWR GD GHVFDUJD GHYHP VHU YHUL¿FDGDV D FDSDFLGDGH
KLGUiXOLFDHDVH[LJrQFLDVOHJDLV

5.11.2.2 $YiOYXODGHGHVFDUJDGHYHVHULQVWDODGDSDUDOLPSDUHHVYD]LDUDWXEXODomR'HYHPVHU
WRPDGRVFXLGDGRVGHIRUPDDQmRSHUPLWLURUHWRUQRHDHQWUDGDGHiJXDGDGHVFDUJDSDUDRLQWHULRU
da rede.

5.11.2.3 4XDQGRGDGH¿QLomRGRORFDOGHLQVWDODomRGDYiOYXODGHYHVHUREVHUYDGDDIDFLOLGDGHDVHX
DFHVVRHRSHUDomR4XDQGRDYiOYXODIRULQVWDODGDHPFDL[DRXHPSRoRGHYLVLWDVXDRSHUDomRGHYH
ser permitida sem necessidade de ingressar ao seu interior.

5.11.2.4 2 GLPHQVLRQDPHQWR GD YiOYXOD GHYH YHUL¿FDU D FDSDFLGDGH KLGUiXOLFD GH HVYD]LDPHQWR
GDUHGHDEUDQJLGDFRQVLGHUDQGRRSHU¿OGDWXEXODomRDH[WHQVmRRYROXPHGRWUHFKRDVHUHVJRWDGR
R YROXPH GH DU D VHU LQWURGX]LGR SDUD HYLWDU D VXESUHVVmR DV FRQGLo}HV SDUD HVFRDPHQWR GD
iJXD GHVFDUUHJDGD 'HYHVH GH¿QLU R WHPSR Pi[LPR GH HVFRDPHQWR GD WXEXODomR RX GR VLVWHPD
GHGLVWULEXLomRGHIRUPDDDWHQGHUDRWHPSRGHSDUDGDRSHUDFLRQDOGH¿QLGRSHODRSHUDGRUD

5.11.3 Ventosa

5.11.3.1 3UHYHUDLQVWDODomRGHYHQWRVDVQRVSRQWRVHVWUDWpJLFRVGDUHGHSDUDSHUPLWLUDH[SXOVmRH
DGPLVVmRGRDU

5.11.3.2 9HUL¿FDUDQHFHVVLGDGHGHYHQWRVDHPSRQWRVGHDOLPHQWDomRGDUHGHSULQFLSDODSDUWLUGH
HOHYDWyULDV RX boosters QDV VDtGDV GRV UHVHUYDWyULRV QDV WXEXODo}HV RSHUDQGR SRU JUDYLGDGH HP
WUHFKRORQJRGHWXEXODomRVHPGHULYDo}HVHPPXGDQoDVGHGHFOLYLGDGH

5.11.3.3 2 GLPHQVLRQDPHQWR GD YHQWRVD GHYH FRQVLGHUDU D YHORFLGDGH GH HVYD]LDPHQWR H GH
HQFKLPHQWRGDVWXEXODo}HV

5.11.3.4 1DVHOHomRGDYHQWRVDGHYHVHUYHUL¿FDGDDVXDFDSDFLGDGHGHH[SXOVmRHDGPLVVmRGHDU

5.11.3.5 4XDQGRGDGH¿QLomRGRORFDOGHLQVWDODomRGDYHQWRVDGHYHVHUREVHUYDGDDIDFLOLGDGHD
VHXDFHVVRHPDQXWHQomR

18 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

5.11.3.6 4XDQGRDYHQWRVDIRULQVWDODGDHPFDL[DRXSRoRGHYLVLWDSUHYHUGLPHQV}HVTXHSHUPLWDP
DPDQXWHQomRGHIRUPDDGHTXDGDHGUHQDJHPSDUDSURWHJHUDLQVWDODomRGRFRQWDWRFRPiJXDGH
VDWXUDomRGRVRORRXGHLQXQGDomRQmRSHUPLWLQGRDHQWUDGDGHiJXDSDUDRLQWHULRUGDUHGH

5.11.3.7 $ FDL[D RX SRoR GH YLVLWD GH SURWHomR GD YHQWRVD GHYH SHUPLWLU D HQWUDGD H VDtGD GR DU
4XDQGR LQVWDODGD FRP WDPSD GHYH SRVVXLU IXUDomR HP TXDQWLGDGH H GLkPHWUR FRPSDWtYHLV FRP D
QHFHVVLGDGHGHDUGH¿QLGDHPSURMHWR

5.11.4 Booster

5.11.4.1 1DUHGHGHGLVWULEXLomRSRGHVHULQVWDODGRboosterSDUDDWHQGHUjVSUHVV}HVQRDEDVWHFLPHQWR
HVWDEHOHFLGDV QHVWD 1RUPD GHVGH TXH VXD LQVWDODomR VHMD WpFQLFD H HFRQRPLFDPHQWH MXVWL¿FDGD
$GRWDUGLVSRVLWLYRVGHSURWHomRKLGUiXOLFDGRVLVWHPDFRPDMXVWHDXWRPiWLFRGHRSHUDomR

5.11.4.2 4XDQGR GD GH¿QLomR GR ORFDO GH LQVWDODomR GR booster GHYH VHU REVHUYDGD D IDFLOLGDGH
GH DFHVVR SDUD RSHUDomR H PDQXWHQomR D GLVSRQLELOLGDGH GH HQHUJLD HOpWULFD D VHJXUDQoD GDV
LQVWDODo}HV

5.11.4.3 2GLPHQVLRQDPHQWRHGHWDOKDPHQWRGRboosterGHYHDWHQGHUDRVUHTXLVLWRVHVWDEHOHFLGRV
na ABNT NBR 12214.

5.11.4.4 1RVFDVRVHPTXHDGLIHUHQoDGHSUHVV}HVHRXYD]}HVIRUHPVLJQL¿FDWLYDVHPIXQomRGD
YDULDomRGHFRQVXPRDGRWDUGLVSRVLWLYRVGHFRQWUROHFRPDMXVWHDXWRPiWLFRGHSUHVVmRHRXYD]mR

5.11.4.5 1mRpSHUPLWLGDDOLJDomRGHHOHYDWyULDGHXVXiULRjWXEXODomRGDUHGHGHGLVWULEXLomR

5.11.5 Válvula redutora de pressão (VRP)

5.11.5.1 1D UHGH GH GLVWULEXLomR SRGH VHU LQVWDODGD YiOYXOD UHGXWRUD GH SUHVVmR SDUD DWHQGHU
jVSUHVV}HVHVWDEHOHFLGDVQHVWD1RUPDGHVGHTXHVXDLQVWDODomRVHMDWpFQLFDHHFRQRPLFDPHQWH
MXVWL¿FDGD

5.11.5.2 4XDQGR GD GH¿QLomR GR ORFDO GH LQVWDODomR GD YiOYXOD UHGXWRUD GH SUHVVmR GHYHP VHU
REVHUYDGDV D IDFLOLGDGH H D VHJXUDQoD GH DFHVVR SDUD RSHUDomR H PDQXWHQomR D VHJXUDQoD
HDGUHQDJHPGDVLQVWDODo}HV(PiUHDFRPULVFRGHYDQGDOLVPRDGRWDUFDL[DGHSURWHomRFRQGL]HQWH
FRPDVLWXDomR

5.11.5.3 1RGLPHQVLRQDPHQWRHGHWDOKDPHQWRGDYiOYXODUHGXWRUDGHSUHVVmRDWHQGHUjVFRQGLo}HV
KLGUiXOLFDVHVWDEHOHFLGDVSDUDDUHGHGHGLVWULEXLomRQHVWD1RUPD

5.11.5.4 1RV FDVRV HP TXH D GLIHUHQoD GH SUHVV}HV HRX YD]}HV IRUHP VLJQL¿FDWLYDV HP IXQomR
GDYDULDomRGHFRQVXPRDGRWDUGLVSRVLWLYRVGHFRQWUROHFRPDMXVWHDXWRPiWLFRGHSUHVVmR

5.11.6 Medidores ou controladores de pressão

5.11.6.1 1D UHGH GH GLVWULEXLomR SRGH VHU LQVWDODGR PHGLGRU RX FRQWURODGRU SDUD PRQLWRUDPHQWR
H FRQWUROH RSHUDFLRQDO GD SUHVVmR DWXDQWH QD UHGH DWHQGHQGR jV FRQGLo}HV WpFQLFDV SDUD D UHGH
GHGLVWULEXLomRHVWDEHOHFLGDVQHVWD1RUPD

5.11.6.2 4XDQGRGDGH¿QLomRGRORFDOGHLQVWDODomRGHYHPVHUREVHUYDGDVDIDFLOLGDGHHDVHJXUDQoD
GHDFHVVRSDUDRSHUDomRHPDQXWHQomRDVHJXUDQoDHDGUHQDJHPGDVLQVWDODo}HV

© ABNT 2017 - Todos os direitos reservados 19


ABNT NBR 12218:2017

5.11.7 Medidores ou controladores de vazão

5.11.7.1 1D UHGH GH GLVWULEXLomR SRGH VHU LQVWDODGR PHGLGRU RX FRQWURODGRU GH YD]mR SDUD
PRQLWRUDPHQWRHFRQWUROHRSHUDFLRQDOGDYD]mRFRQIRUPHFULWpULRWpFQLFRGDRSHUDGRUDUHVSRQViYHO
SHORVLVWHPDGHDEDVWHFLPHQWRGHiJXD

5.11.7.2 4XDQGRGDGH¿QLomRGRORFDOGHLQVWDODomRGRPHGLGRURXFRQWURODGRUGHYHPVHUREVHUYDGDV
DIDFLOLGDGHHDVHJXUDQoDGHDFHVVRSDUDRSHUDomRHPDQXWHQomRDVHJXUDQoDHDGUHQDJHPGDV
LQVWDODo}HV

5.11.7.3 1R GLPHQVLRQDPHQWR H GHWDOKDPHQWR GR PHGLGRU RX FRQWURODGRU DWHQGHU jV FRQGLo}HV
KLGUiXOLFDVGRVLVWHPDHFULWpULRWpFQLFRGDRSHUDGRUDUHVSRQViYHOSHORVLVWHPDGHDEDVWHFLPHQWRGH
água.

5.12 Ligação predial

5.12.1 Dispositivo de interligação do usuário à rede

5.12.1.1 3URMHWDUGHWDOKHHVSHFt¿FRGDLQVWDODomRSDGUmRGRGLVSRVLWLYRGHLQWHUOLJDomRGRUDPDOGH
OLJDomR SUHGLDO j UHGH GH GLVWULEXLomR ,QFOXLU RULHQWDomR FRP HVSHFL¿FDomR GRV FXLGDGRV D VHUHP
WRPDGRV TXDQWR DR PDQXVHLR GR GLVSRVLWLYR HPEDVDPHQWR UHDWHUUR FRPSDFWDomR QR HQWRUQR GR
GLVSRVLWLYRVLQDOL]DomRYLiULD

5.12.1.2 $OLJDomRSUHGLDOGHYHVHUDWHQGLGDGHDFRUGRFRPDSROtWLFDGHPHGLomRGHFRQVXPRGD
operadora.

5.12.1.3 $LQVWDODomRGDOLJDomRSUHGLDOHGRUDPDOSUHGLDOLQWHUQRGHYHVHUH[HFXWDGDDWHQGHQGRjV
H[LJrQFLDVGDRSHUDGRUDHjOHJLVODomRYLJHQWH

5.12.2 Ramal de interligação da rede à ligação predial do usuário

3URMHWDU GHWDOKH HVSHFt¿FR GD LQVWDODomR SDGUmR GR UDPDO GH LQWHUOLJDomR ,QFOXLU RULHQWDomR FRP
HVSHFL¿FDomR GRV FXLGDGRV D VHUHP WRPDGRV TXDQWR DR HPEDVDPHQWR UHDWHUUR FRPSDFWDomR QR
HQWRUQRGRUDPDOSUHYHQGRWRGDVDVFRQVLGHUDo}HVWpFQLFDVQDLQVWDODomR

5.12.3 Unidade de medição de consumo

3DUD D LQWHUOLJDomR GR XVXiULR j UHGH GH GLVWULEXLomR SUHYHU D LQVWDODomR GH XQLGDGH GH PHGLomR
GH FRQVXPR 2 SDGUmR GD XQLGDGH GH PHGLomR H RV GHWDOKHV GH VXD LQVWDODomR GHYHP VHJXLU
DRULHQWDomRGDRSHUDGRUD$LQVWDODomRGHYHJDUDQWLUDOHLWXUDGRFRQVXPRDSURWHomRHDPDQXWHQomR
da unidade.

5.12.4 Pontos para monitoramento da qualidade da água

3UHYHUSRQWRVSDUDFROHWDGHiJXDHPORFDLVHVWUDWpJLFRVGDUHGHGHGLVWULEXLomRFRQIRUPHOHJLVODomR
YLJHQWH GH FRQWUROH yUJmR UHJXODGRU H YLJLOkQFLD VDQLWiULD DWHQGHQGR jV GLUHWUL]HV HVSHFt¿FDV GD
operadora.

5.13 Travessia

5.13.1 2SURMHWRGDUHGHGHYHFRQWHURVGHWDOKHVFRQVWUXWLYRVGDVWUDYHVVLDVFRPGLPHQVLRQDPHQWR
KLGUiXOLFRHHVWUXWXUDODWHQGHQGRjVRULHQWDo}HVGDVHQWLGDGHVHQYROYLGDVDH[LVWrQFLDGHQRUPDV
HVSHFt¿FDVLQGLFDomRGDFRWDGHHQFKHQWH

20 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

5.13.2 0RYLPHQWRV GLIHUHQFLDLV VLJQL¿FDWLYRV HQWUH D HVWUXWXUD GH DSRLR H D WXEXODomR GHYHP VHU
YHUL¿FDGRVSUHYHQGRVROXomRDGHTXDGD

5.13.3 1RV FDVRV RQGH D WXEXODomR QmR HQWHUUDGD HVWLYHU VXMHLWD D DYDULDV GH TXDOTXHU QDWXUH]D
SURYRFDGDVSRUDJHQWHVUHDLVRXSRWHQFLDLV YDQGDOLVPRLQFrQGLRLPSDFWRFRQWUDDHVWUXWXUD DGRWDU
VROXomRWpFQLFDFRPSDWtYHODRULVFR

5.14 Ancoragem

'HYHVHUDQDOLVDGRRHVIRUoRPi[LPRUHVXOWDQWHH[HUFLGRSHODiJXDQDFRQGLomRRSHUDFLRQDOPDLV
GHVIDYRUiYHOHGHYHVHUSUHYLVWDHVWUXWXUDFDSD]GHDEVRUYHURVHVIRUoRVQRVSRQWRVGHPXGDQoD
GHGLUHomRGHDOWHUDomRGHGLkPHWURQDWUDQVLomRGHGLIHUHQWHVPDWHULDLVDSOLFDGRVGHORFDOL]DomR
GH GLVSRVLWLYRV SDUD IHFKDPHQWR RX FRQWUROH QRV FRQGXWRV SULQFLSDLV QDV GHULYDo}HV TXDQGR
necessário.

5.15 &RQGLo}HVPHFkQLFDV

5.15.1 2SURMHWRGHYHGH¿QLUQDVSHoDVJUi¿FDVDVFRQGLo}HVGHDVVHQWDPHQWRGDWXEXODomRLQGLFDQGR
D FRQVWLWXLomR GR OHLWR GH DVVHQWDPHQWR D HVSHVVXUD GH UHFREULPHQWR H R JUDX GH FRPSDFWDomR
GRVRORGHUHDWHUUROHYDQGRHPFRQWDRWLSRGRPDWHULDOGDUHGHDVFDUJDVDWXDQWHVHRWLSRGHVROR

5.15.2 'HYHVHUYHUL¿FDGRROLPLWHGHGHIRUPDomRGLDPHWUDOTXDQGRQHFHVViULR

5.15.3 $YDOLDUDVFRQGLo}HVGHDJUHVVLYLGDGHGRPHLRHRXGRHQWRUQR6HQHFHVViULRSUHYHUSURWHomR
DGHTXDGDGDWXEXODomRFRQWUDRSURFHVVRFRUURVLYRRXRDWDTXHTXtPLFR

5.15.4 3DUDWXEXODo}HVVXMHLWDVDWUDQVLHQWHVKLGUiXOLFRVVLJQL¿FDWLYRVDYDOLDUDFRQGLomRPHFkQLFD
GDWXEXODomRHGDVHVWUXWXUDVSDUDHYLWDURFRODSVR

5.15.5 'HYHPVHUYHUL¿FDGDVDVFRQGLo}HVGHLQVWDODomRHDVYDULDo}HVWpUPLFDVHRXGHLQWHPSpULHV
DWXDQWHVYLVDQGRPDQWHUDVFRQGLo}HVGHIXQFLRQDPHQWRHVHJXUDQoDQRVLVWHPD

5.15.6 'HYH VHU DYDOLDGD D LQWHUFDPELDELOLGDGH HQWUH RV GLIHUHQWHV PDWHULDLV DSOLFDGRV QD UHGH
4XDQGRQmRKRXYHUSUHYHURVGHYLGRVHOHPHQWRVSDUDDWUDQVLomR

5.15.7 4XDQGRGDH[HFXomRGHFkPDUDVGHPDQREUDRXRXWURVHOHPHQWRVTXHFRQ¿QHPXPFRQMXQWR
GHSHoDVHVSHFLDLVSUHYHUDFHVVyULRTXHIDFLOLWHDPRQWDJHPHGHVPRQWDJHPSDUDPDQXWHQomR

5.16 'LVSRVLo}HVFRQVWUXWLYDV

5.16.1 2SURMHWRGHYHLQGLFDUSDUDDIDVHGHH[HFXomRGDVREUDVDREULJDWRULHGDGHQRDWHQGLPHQWR
jVQRUPDVQDFLRQDLVjVHVSHFL¿FDo}HVGDRSHUDGRUDHWDPEpPjVLQVWUXo}HVGRIDEULFDQWH

5.16.2 2 SURMHWR GHYH FRQWHPSODU DV IDVHV FRQVWUXWLYDV H LQGLFDU VROXomR SDUD DV LQWHUIHUrQFLDV
GH WUiIHJR H WUDQVHXQWHV PpWRGR FRQVWUXWLYR GH WUDYHVVLDV HVSDoRV SDUD WUiIHJR RX DFHVVR
SDUD PDQXWHQomR H GHPDLV GHWDOKHV QHFHVViULRV j H[HFXomR GD REUD DWHQGHQGR DRV DVSHFWRV
GHVHJXUDQoD

5.16.3 2 SURMHWR GHYH SUHYHU QR RUoDPHQWR R FDQWHLUR GH REUD FRP DV LQVWDODo}HV QHFHVViULDV
HRDFRQGLFLRQDPHQWRDGHTXDGRGRVPDWHULDLV,QGLFDUHDSUHVHQWDURVFULWpULRVDGRWDGRVQRRUoDPHQWR
para os respectivos itens.

5.16.4 2 SURMHWR GHYH DSUHVHQWDU R GHWDOKDPHQWR QRV SRQWRV GH LQWHUIHUrQFLDV QR FDPLQKDPHQWR
da rede.

© ABNT 2017 - Todos os direitos reservados 21


ABNT NBR 12218:2017

5.16.5 2SURMHWRSRGHSUHYHUDLQVWDODomRGHVLQDOL]DomRGHLGHQWL¿FDomRSDUDWXEXODo}HVHVWUDWpJLFDV
HPDWHQGLPHQWRjVHVSHFL¿FDo}HVGDRSHUDGRUDHjOHJLVODomRYLJHQWH

5.16.6 2SURMHWRGHYHSUHYHUQRRUoDPHQWRDUHDOL]DomRGRWHVWHKLGURVWiWLFROLPSH]DHGHVLQIHFomR
GDUHGHQD¿QDOL]DomRHHQWUHJDGDREUD

5.16.7 2SURMHWRSRGHSUHYHUQRRUoDPHQWRDHODERUDomRGHFDGDVWURJHRUUHIHUHQFLDGRGRVLVWHPD
SURMHWDGR FRQIRUPH H[HFXWDGR SRU PHLR GH UHODWyULRPHPRULDO IRWRJUi¿FRYtGHR GD LPSODQWDomR
GDVUHGHVTXDQGRQHFHVViULRGHDFRUGRFRPjVH[LJrQFLDVGDRSHUDGRUD

5.16.8 1R SURMHWR GHYH VHU DSUHVHQWDGR R SODQR GH RSHUDomR GD UHGH DEUDQJHQGR DV iUHDV
FRQWHPSODGDVTXDQGRQHFHVViULRDWHQGHQGRjVGLUHWUL]HVGDRSHUDGRUD

5.16.9 3DUDHIHLWRGHDEHUWXUDGDYDODHVFRUDPHQWRDVVHQWDPHQWRHUHDWHUURGDWXEXODomRRSURMHWR
GHYHXWLOL]DURVUHVXOWDGRVGRVHVWXGRVJHRWpFQLFRVD¿PGHRULHQWDUDH[HFXomRGDREUD

5.16.10 2 SURMHWR GHYH LQGLFDU D ORFDOL]DomR H GLVSRQLELOLGDGH GR PDWHULDO GH HPSUpVWLPR
VHQHFHVViULRHDGHVWLQDomR¿QDOGRVHQWXOKRVHUHVtGXRVGDFRQVWUXomRFLYLOSDUDORFDODGHTXDGR
HOLFHQFLDGR2VFXVWRVLQFLGHQWHVGHYHPVHUFRQVLGHUDGRVQRRUoDPHQWRDWHQGHQGRjVH[LJrQFLDV
vigentes.

5.16.11 1DV LQVWDODo}HV VXEDTXiWLFDV R SURMHWR GHYH OHYDU HP FRQVLGHUDomR DOpP GRV HVIRUoRV
GHFRUUHQWHV GR UHFREULPHQWR SUHVVmR KLGURVWiWLFD LQWHUQD H DOWXUD GD FROXQD G¶iJXD D DGHTXDGD
DQFRUDJHPGDWXEXODomRQROHLWRVXEDTXiWLFRHPIXQomRGRHPSX[RGDIRUPDomRGHHYHQWXDLVJDVHV
LQWHUQRVFRUUHQWHVDTXiWLFDVRQGDVGHIXQGRYDULDo}HVGHPDUpV

5.16.12 $ SLQWXUD GH LGHQWL¿FDomR GRV KLGUDQWHV XUEDQRV GHYH VHU IHLWD QRV WDPS}HV ODWHUDLV
HQRWRSRSDUDRVKLGUDQWHVGHFROXQDHQDWDPSDGDFDL[DGHSURWHomRSDUDKLGUDQWHVVXEWHUUkQHR
TXDQGRGDLPSODQWDomRQRVLVWHPDGLVWULEXLGRUGHDFRUGRFRPDWDEHODGHFODVVL¿FDomRGHKLGUDQWHV
YHU7DEHOD 

5.17 (VSHFL¿FDo}HVWpFQLFDV

$VHVSHFL¿FDo}HVWpFQLFDVGHYHPVHUGHWDOKDGDVFODUDVHREMHWLYDVFRQWHQGRWRGRVRVHOHPHQWRV
QHFHVViULRV j FDUDFWHUL]DomR GRV VHUYLoRV D VHUHP H[HFXWDGRV GRV PDWHULDLV HTXLSDPHQWRV
HOHWURPHFkQLFRVHDFHVVyULRVDVHUHPXWLOL]DGRV

5.17.1 (VSHFL¿FDo}HVWpFQLFDVGRVVHUYLoRVHPDWHULDLV

5.17.1.1 $ WXEXODomR H FRQH[}HV LQGLFDGDV QR SURMHWR GHYHP DWHQGHU jV 1RUPDV %UDVLOHLUDV HP
YLJrQFLD

5.17.1.2 2VVHUYLoRVGHYHPHVWDUHPFRQIRUPLGDGHFRPDV1RUPDV%UDVLOHLUDVHPYLJrQFLD

5.17.2 (VSHFL¿FDomRWpFQLFDGRVFRPSRQHQWHVHHTXLSDPHQWRVDFHVVyULRV

5.17.2.1 $V HVSHFL¿FDo}HV GHYHP FRQWHU GHWDOKDPHQWRV VX¿FLHQWHV SDUD D SHUIHLWD FRPSUHHQVmR
GDFDUDFWHUL]DomRGRVFRPSRQHQWHVHHTXLSDPHQWRVDFHVVyULRVSDUDDVXDDTXLVLomRPRQWDJHP
LQVWDODomRRSHUDomRHPDQXWHQomR

5.17.2.2 $V HVSHFL¿FDo}HV GHYHP LQFOXLU D H[LJrQFLD GH JDUDQWLDV TXDQWR jV DOWHUDo}HV UHSDURV
VXEVWLWXLo}HVUHSRVLo}HVHFRQVHUWRVGHWRGRHTXDOTXHUPDWHULDOTXHDSUHVHQWDUDQRPDOLDVYtFLRV
RX GHIHLWRV GHFRUUHQWHV GH PDWpULDSULPD HPSUHJDGD HP VXD SURGXomR HRX GHFRUUHQWHV GH HUURV

22 © ABNT 2017 - Todos os direitos reservados


ABNT NBR 12218:2017

GH FRQFHSomR GR SURMHWR HRX GD IDEULFDomR GR FRPSRQHQWH RX GR HTXLSDPHQWR DR DWHQGLPHQWR
jV FRQGLo}HV LQGLFDGDV QD SURSRVWD GH IRUQHFLPHQWR j DVVLVWrQFLD WpFQLFD j UHSRVLomR GH SHoDV
GRFRPSRQHQWHRXGRHTXLSDPHQWRDFHVVyULRHVSHFL¿FDGR

5.17.2.3 3DUD FDGD WLSR GH FRPSRQHQWH RX HTXLSDPHQWR GHYH VHU H[LJLGD D FRPSURYDomR GR
DWHQGLPHQWR jV QRUPDV WpFQLFDV SHUWLQHQWHV 3RGHQGR VHU H[LJLGRV GRFXPHQWRV HVSHFt¿FRV
FRPRODXGRVWpFQLFRVHRXRODXGRGDPDWpULDSULPDGRPDWHULDORXHTXLSDPHQWRWHVWHVHHQVDLRV
FRPSOHPHQWDUHV

5.17.2.4 1D HVSHFL¿FDomR GHYH FRQVWDU D H[LJrQFLD GH IRUQHFLPHQWR GH PDQXDO GH LQVWDODomR
RSHUDomRHPDQXWHQomRHPSRUWXJXrVDFRPSDQKDGRGHVHXRULJLQDOVHIRUGHRULJHPHVWUDQJHLUD

5.18 Orçamento

5.18.1 2 RUoDPHQWR GR SURMHWR GHYH DSUHVHQWDU R TXDQWLWDWLYR H R FXVWR GRV VHUYLoRV H PDWHULDLV
DSDUWLUGHHVSHFL¿FDo}HVGHWDOKDGDVHFRPSRVLo}HVGHFXVWRVHVSHFt¿FRVTXDQGRQHFHVViULDV

5.18.2 2RUoDPHQWRGRSURMHWRGHYHFRQVLGHUDUWRGDVDVHWDSDVQHFHVViULDVjLPSODQWDomRGDUHGH
GHVGHRVVHUYLoRVSUHOLPLQDUHVDWpDGHVPRELOL]DomRGDREUD

5.19 Plano de implantação e execução da obra

5.19.1 Etapas de implantação

$V HWDSDV GH LPSODQWDomR GD UHGH GHYHP VHU GHWDOKDGDV DWHQGHQGR DRV HVWXGRV GH YLDELOLGDGH
WpFQLFDHFRQ{PLFDH¿QDQFHLUDHGLUHWUL]HVGH¿QLGDVSHODRSHUDGRUD

5.19.2 Plano de execução da obra

2SURMHWRGHYHGH¿QLURPpWRGRH[HFXWLYRGDREUDHFRQVLGHUDUDLQWHUGHSHQGrQFLDGDVDWLYLGDGHVGH
IRUPDDRWLPL]DUDVSDUDOLVDo}HVQHFHVViULDV

5.20 2XWUDVFRQGLo}HV

$VSHoDVJUi¿FDVGHYHPHVWDUGHDFRUGRFRPDV1RUPDV%UDVLOHLUDVHPYLJrQFLDHDWHQGHUjVGLUHWUL-
]HVHVSHFt¿FDVGDRSHUDGRUD

© ABNT 2017 - Todos os direitos reservados 23